Project & Quality Management Day 3 Technology Project Management

Project & Quality Management Day 3 Technology Project Management. Syllabus Core: PQM. Three main topics Project Management Quality Management Reliability Management. Structure of the Presentation. Project Management Overview of project management, Project planning;

adli
Download Presentation

Project & Quality Management Day 3 Technology Project Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project & Quality Management • Day 3 Technology • Project Management

  2. Syllabus Core: PQM • Three main topics • Project Management • Quality Management • Reliability Management

  3. Structure of the Presentation Project Management • Overview of project management, • Project planning; • Work Breakdown Structure, • The Gantt Chart, • Network Diagram, • Critical Path Diagram, • Project planning for Technology projects, • Using Microsoft Project to generate charts.

  4. What is Project Management? • A set of techniques used for managing projects • Origins in industry - large projects • Bridge Building • New Product Development • Road Building

  5. What is a Project? • “Any task within an organisation that does not fit neatly into ‘business-as-usual’” • Port Tunnel • Luas • Development of New Engine • Set up a Quality System in Company • Technology Design & Make project.

  6. What is a Project? • Projects have the following characteristics: • Each project is specific and unique. • Each project has a specific deliverable item when complete. • This deliverable is aimed at meeting a specific need or purpose. • There is usually a specific due datefor completion of the project. • Design is not necessarily a central part of the project activity.

  7. What is Managed? • PM focuses on the management of resources and time in a systematic manner. • The administration of the project • The supervision of the project • The organisation of the project

  8. What is Managed? • For the student it means: • Analysing the objectives of the project, • Defining the tasks needed to achieve these objectives, • Controlling the execution of them.

  9. Who manages the projeect? • Large projects usually involve a project team.

  10. What do Project Managers do? • Projects have 3 objectives, • Finish on time. • Meet the specifications that satisfy • the brief. • Meet the budget. • Students are the project managers of their own tasks!

  11. Importance of Planning • Unexpected events may happen during the • project and may cause delays. • Breakdown of machinery, • Problems with resources/supplies, • Labour shortages, etc. • Project planning can minimise the effect of these unexpected delays.

  12. Project Planning • What is a project plan? • Can be as simple as a list of sequences for a small project • Can be more complex with charts, tables, costings etc. for a larger project

  13. Project Planning • Analyse the brief, • List the steps involved, • Draw up a Work Breakdown Structure (WBS). • A WBS is a diagram that shows • Primary Tasks • Sub-Tasks

  14. Example • Draw up a Work Breakdown Structure for the erection of a garden shed. • The shed will come prefabricated but will need to be assembled. • A foundation will need to be prepared in advance.

  15. List of Tasks

  16. Place order forshed Garden Shed Buy Blocks and Cement Prepare Foundation Assemble Shed when it arrives WBSforGardenShed

  17. The Gantt Chart – a Preview • A Gantt Chart is a horizontal bar chart showing the times for each task

  18. Looking at the Gantt Chart • Delivery time for the shed is nine days, • One day for buying materials, • Two days for making the foundation, • One day for assembly. • Note: • Making the foundation is timed so that it is ready just in time for the delivery of the shed • Could have been completed at an earlier date if desired.

  19. Day 0 1 2 3 4 5 6 7 8 9 10 Order Shed from Supplier Buy Blocks Build Foundation Assemble Exercises • Redraw the Gantt chart so that the maximum amount of time is allowed for the curing of the foundation.

  20. Exercises • Shown is a picture of a Christmas Tree Star • Draw a WBS for the Star • Draw a Gantt chart for manufacturing the Star

  21. List of Tasks:Star

  22. WBS for Star Mark Out Drill Cut Out & File Structure Sub Task Assemble Test Star Sub Task Solder Circuit Circuit

  23. Gantt Chart for Star Day 0 1 2 3 4 5 6 7 8 9 10 Mark Out Drill Cut Out & File Solder Circuit Assemble Test

  24. Network Diagrams • For larger or more complex projects a network diagram is required. • Network Diagrams show: • The relationships between the tasks, • 2. The sequence in which each task is performed, • 3. The interdependencies between the tasks.

  25. Drawing up a Network Diagram • Start with task list and draw up a WBS • Decide on the order of tasks WBS Network Diagram Gantt Chart

  26. Sample WBS A WBS needs to be analysed and redrawn frequently to arrive at the best production sequence. (Use ‘Post its’)

  27. Network Table The tasks and theirpredecessorscan be drawn as a table

  28. Part Complete Network Diagram Note that task C has A as a predecessor D and E have B as predecessors. A and B have no predecessors and are connected to the starting node.

  29. Complete Network Diagram Exercise:Complete the diagram using the remainder of the tasks

  30. Network Diagram for Garden Shed • Draw up a network diagram for the garden shed project described previously.

  31. Some Definitions and Terms • Terms used for network diagrams: • Activity – A task or set of tasks required by the project. • Network – Diagram of nodes representing activities connected by directional arrows that defines the project and shows the relations between all of the activities. Networks are usually drawn with a ‘Start’ node on the left and a ‘Finish’ node on the right. • Path – A series of connected activities in the network • Critical Path – the set of activities on a path from the project’s start event to its finish event that if delayed, will delay the completion date of the project. • Critical Time – The time required to complete all activities on the critical path.

  32. Adding Times to the Network Diagram • Duration of each task can be added to network diagram • From this, start and finish times can be found for each task • Some tasks can be allowed to vary their start and finish times without affecting overall time taken

  33. Example Consider the following project

  34. Network with Tasks & Times

  35. Adding Further Information • We can add the following information to each node in the diagram: • Earliest Start Time (EST) • Earliest Finish Time (EFT) • Latest Start Time (LST) • Latest Finish Time (LFT)

  36. Critical Path Diagram • Critical path in orange • See notes for a detailed explanation

  37. Conclusions from Critical Path Diagram • Critical path is path that requires the most time (A-E-H-J) • Critical time is 21 days which is the earliest possible completion time • Any delay on critical path will delay the project • Some delay (within limits) can be tolerated on other tasks.

  38. Critical Path Diagram for the Garden Shed • Complete the critical path diagram for the garden shed • State critical path and critical time

  39. Solution • CP: Order Shed – Assemble • CT= 10 Days

  40. CalculatingActivitySlack Slack or Float is the amount of time a non-critical task can be delayed Slack = Latest Finish Time – Earliest Finish Time or Latest Start Time – Earliest Start Time Slack = LFT-EFT = LST-EST

  41. SlackTimes from Shed Example • Both non-critical tasks have a slack of • (9-3)=(7-1)=(7-1)=(6-0) = 6 days

  42. The Gantt Chart • Generated from network diagram • Gives visual representation of activities and times • Gantt charts can show: • Timeline for each task • Dependencies of tasks • Critical path

  43. Network Diagram • Using the Network Diagram from previous example

  44. Application of PM to Tech. Projects • Now we will apply the techniques we have met to a hypothetical LC project. • The procedure for project work is: • List the tasks and sub-tasks involved • Draw up a WBS • Draw up a Network Table • Draw up a Network Diagram • Insert times and determine the Critical Path

  45. Consider the following project brief • Design and manufacture a personal alarm that will incorporate an electronic circuit as well as a suitable casing • From analysing the brief: • General plan on how to approach the project • Identify the main tasks involved • Derive a Work Breakdown Schedule • Draw up a Network Diagram • Add times and find the critical path, critical time and slack for the activities.

  46. A possible WBS for the project Research Circuit Design Circuit Order Components Circuit Sub Task Manufacture & Assemble Test Personal Alarm Sub Task Casing User Survey Design Specification Design Casing Order Materials

  47. Network Table • First draw up a list of tasks and preceding tasks

  48. Network Diagram 7 7