1 / 26

What can we do? against inefficient budget execution

What can we do? against inefficient budget execution. May. 6, 2014. Seongbak Wi Ministry of Strategy and Finance, Korea Secondee to Inter-American Development Bank. Contents. Ⅰ Raising an issue. Ⅱ M&E in Korea and strengthening the method.

adamdaniel
Download Presentation

What can we do? against inefficient budget execution

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. What can we do? against inefficient budget execution May. 6, 2014 Seongbak Wi Ministry of Strategy and Finance, Korea Secondee to Inter-American Development Bank

  2. Contents Ⅰ Raising an issue Ⅱ M&E in Korea and strengthening the method Ⅲ Challenges and remarks

  3. I. Raising an issue

  4. Ⅰ. Raising an issue 1. Raising an issue Object of budget Budget a bridge and no output No monitoring, no sanction 세계경제 전망(%)

  5. Ⅰ. Raising an issue 1. Raising an issue Request a building construction Cost : US$9 -> US$15 -> US$ 30 세계경제 전망(%)

  6. Ⅰ. Raising an issue 1. Raising an issue • M&E helps projects implemented as planned and budgeted. - Line ministries and executing entities have desire to increase the scale of projects or to use money for personal purpose • For M&E to be effective, we need some strong methods, such as sanctions against bad executions. 세계경제 전망(%)

  7. Ⅱ. M&E in Korea and strengthening the method

  8. Ⅱ. M&E in Korea and strengthening the method 1. External supervision of project Execution ▶ Project execution is supervised by government - payment will be done after checking the process and proof. ▶ Administration of Audit and Inspection : - fire-off, cut in salary, warning, … ▶ Prosecutors , - imprisonment, fine ▶ Parliament and people’s monitoring 세계경제 전망(%)

  9. Ⅱ . M&E in Korea and strengthening the method ▶ Existence of output vs ▶Feasibility and Efficiency 세계경제 전망(%)

  10. Ⅱ. . M&E in Korea and strengthening the method 2. Re-assessment of Feasibility ▶ Projects start after feasibility test, However, their feasibilities can change after the initiation ▶ Re-assess of Feasibility will be done    - If TPC has increased by more than 20%    - If new demand forecast is smaller by 30% than the initial one ▶ What if a project appears not to be feasible by reassessment? 세계경제 전망(%)

  11. Ⅱ. . M&E in Korea and strengthening the method 2. Re-assessment of Feasibility ▶ Sanctions by Re-assessment of Feasibility (1)    : Example of stopped projects which completed detailed design - Janghowon~Jumdong national road(BC=0.24) - Bukmyun~Bugok natinal road(BC-0.26) - Sungnam~Janghown natinal road(BC-0.83) - Imchun~Kanhkyung local road(BC=43) - Boryung new harbour (BC=0.24) 세계경제 전망(%)

  12. Ⅱ. . M&E in Korea and strengthening the method 2. Re-assessment of Feasibility ▶ Counter action by re-assessment of feasibility (2) : adjustment of total costs 세계경제 전망(%)

  13. Ⅱ. . M&E in Korea and strengthening the method 3. Total Project Cost Management ▶ MOSF watch the execution of projects to prevent excessive increase in total cost induced by modification of construction size or design . ▶ TPC rule - Line ministries should report to MOSF and get approval - difference between designed project cost and the cost in bidding - changes in total project cost 세계경제 전망(%)

  14. Ⅱ . M&E in Korea and strengthening the method 3. Total Project Cost Management ▶ what if an entity violate TPC rule? - execution of projects without report of changes project cost ▶ Sanctions, introduced in 2000 - Cut in supplementary expenses of projects - Cut in operational expenditures of the relevant line ministry - No budgeting the unapproved increment 세계경제 전망(%)

  15. Ⅱ. . M&E in Korea and strengthening the method 3. Total Project Cost Management ▣ Effect of Introducing Sanctions to TPC Management 세계경제 전망(%)

  16. Ⅱ. . M&E in Korea and strengthening the method 4. Budget Waste Reporting System ▶Concept : On-line monitoring system open to the public - operating 309 portal sites : 50 in central governments, 246 in local governments, 13 in state-owned enterprises - Number of reported projects by people are increasing (2009) 1,390 -> (2012) 3,474 세계경제 전망(%)

  17. Ⅱ. . M&E in Korea and strengthening the method 4. Budget Waste Reporting System ▶Following actions - MOSF reviews reported issues, - reassess feasibility, in-depth evaluation ▶ Possible sanctions - cut in the project cost, cut in the budget, stop the project . 세계경제 전망(%)

  18. Ⅱ. . M&E in Korea and strengthening the method 4. Budget Waste Reporting System ▶Case : Reconstruction of national road between Yoju-Yangpyung - Projects : from 2 lanes to 4 lanes, - reported issue : another road is being built. - Reassessment of feasibility - cut in TPC, straightening the lanes $117 mil. → $ 60 mil. 세계경제 전망(%)

  19. Ⅱ. . M&E in Korea and strengthening the method 5. Performance Evaluation 1. Self- evaluation ▶ concept - MOSF gives check lists for line ministries to evaluate projects - Line ministries assess performance of programs - Considers for the next year’s budgeting ▶ counteractions - cut in the next year’s budget in case of poor performance 세계경제 전망(%)

  20. Ⅱ. . M&E in Korea and strengthening the method 5. Performance Evaluation Linkage between Self Evaluation and Budgeting

  21. Ⅱ. . M&E in Korea and strengthening the method 5. Performance Evaluation 2. In-depth Evaluation ▶ concept - Evaluate appropriateness, effectiveness, sustainability - in-depth evaluation on some selected projects ▶ counteractions - Some cases, if some problems were found, are sent to Reassessment of feasibility test - cut in the project cost, cut in the next year’s budget, stopping the project 세계경제 전망(%)

  22. Ⅲ. Challenges and remarks

  23. Ⅲ. Challenges and remarks Challenges in M&E Difficulty in monitoring Tetrapod for breakwater 세계경제 전망(%)

  24. Ⅲ Challenges and remarks Challenges in Sanctions ▶ Limitation on effectiveness - Once a project was launched, it is hard to stop it. - it is also hard to restore to the initial condition ▶ Reluctance to sanction - People want to give favor to someone rather than sanction ▶ Is Restriction always desirable? 세계경제 전망(%)

  25. Ⅲ. Challenges and remarks Concluding Remarks ▶ Effective M&E is as important as planning and budgeting. - to secure a project to be realized as planned ▶ M&E requires counteractions to be effective - Strong counteractions, sanctions, will help feedback and launching a new efficient project 세계경제 전망(%)

  26. Muchas gracias seongbakw@iadb.org 26