AMS-02 Integration Cables Status and Electrical Integrated Testing Status

Alpha Magnetic Spectrometer. AMS-02 Integration Cables Status and Electrical Integrated Testing Status. Tim Urban / ESCG January 10, 2007. Alpha Magnetic Spectrometer. Integration Cables and Electrical Integrated Testing Status Presentation Outline. Integration Cables Status

Download Presentation

AMS-02 Integration Cables Status and Electrical Integrated Testing Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Alpha Magnetic Spectrometer AMS-02 Integration Cables Status and Electrical Integrated Testing Status Tim Urban / ESCG January 10, 2007

  2. Alpha Magnetic Spectrometer Integration Cables and Electrical Integrated Testing Status Presentation Outline • Integration Cables Status • Electrical Integrated Testing Status: • I/F Design Description: Power and Data Interfaces for Integrated AMS-02 Payload Testing • Upcoming Tests: • Pad Ops Preliminary Interface Test (POPIT) • PDS EM Power Quality Test (PQT) January 10, 2007 T. J. Urban / ESCG 2

  3. Alpha Magnetic Spectrometer JSC Provided Integration Cables Design, Fabrication and Delivery Status • Design: • The integration cables design and drafting are complete. • The cables are summarized in the table on the next page. • The lengths of 6 cables are being updated based upon their redesign so that they may be used as test cables (discussed later). • Of twenty different cable designs, four are complete through cable drawing checking. The remaining checking will be completed January 19, 2007. • The cable drawings will be released at JSC when they complete checking. • Procurement: • All materials required for flight cable fabrication have been ordered. • 88% of these materials have been received and are in bonded storage. • The remainder of these materials are due by end of Jan ‘07 (1 item in Feb). • All fabrication tools have been ordered and received. January 10, 2007 T. J. Urban / ESCG 3

  4. Alpha Magnetic Spectrometer JSC Provided Integration Cables Design, Fabrication and Delivery Status Cable Summary January 10, 2007 T. J. Urban / ESCG 4

  5. Alpha Magnetic Spectrometer JSC Provided Integration Cables Design, Fabrication and Delivery Status • Fabrication: • The estimate for JSC cable fabrication labor is complete. • JSC work will begin this month, and be complete by the end of April ’07. • Four cable designs (total qty. 6) will be completely fabricated at JSC. • Six cable designs (total qty. 12) will be 67% fabricated at JSC, with the remaining 33% completed at CERN in August ’07. • Ten cable designs (total qty. 18) will be 67% fabricated at JSC, with the remaining 33% completed at KSC in February ’09. • JSC cable fabrication tech. will perform cable completion at CERN & KSC. • Delivery: • Thirteen cable designs (total qty. 25) delivered to CERN in July ’07. • Two AFD cable designs (total qty. 4) delivered to Shuttle FCE later in ’07. • Five cable designs (total qty. 7) delivered to KSC in December ‘08. January 10, 2007 T. J. Urban / ESCG 5

  6. Alpha Magnetic Spectrometer JSC Provided Integration Cables Design, Fabrication and Delivery Status • Miscellaneous: • During CERN payload pre-integration and integration, UUSS and LUSS real estate required for subsequent KSC work should be marked and reserved: • Integration cable routing • Hardware installation: EVA Connector Panel, ROEU PDA, PVGF • JSC ESCG (D. Nguyen) to continue working closely with AMS-02 cable routing modeling team. • JSC ESCG to provide EVA rated cable labels for use by AMS-02 at CERN (4 week delivery ARO – purchased next week). • MIT (X. Cai) will use existing 1553 cables in upcoming J-Crate ESS to verify 1553 RT stub length of 25 feet is acceptable at hot and cold temperatures. (design validation) • The modified PVGF cable harness will be designed to include the fuse required to protect the SSRMS wiring from over-current / over-temperature from AMS-02 heaters powered during SSRMS operations. January 10, 2007 T. J. Urban / ESCG 6

  7. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Interface Design Description January 10, 2007 T. J. Urban / ESCG 7

  8. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Interface Design Description Payload Integration Cable Schematic January 10, 2007 T. J. Urban / ESCG 8

  9. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Interface Design Description • For payload testing: • The payload flight model Interface Panel A will be used to provide GSE cable interface capabilities for STS power and data services. • A new non-flight Test Connector Panel (TCP) will be used to provide GSE cable interface capabilities for ISS power and data services. • This scheme will be used at: • Europe: Functional, beam, TVT and EMI Tests • KSC: • Post-delivery functional. • Interface Panel A connector savers will be used until ROEU ODA GSE is available. • TCP will be used for all ground tests prior to installation of EVA Connector Panel / UMA and ACASS UMA is available. January 10, 2007 T. J. Urban / ESCG 9

  10. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Interface Design Description • Interface Panel A Concept: • GSE connector savers will be installed on all Interface Panel A flight connectors. • For the power connections (5 of 6), GSE cables will be mated directly to the connector savers. • For the sixth connection, 1553 & RS-422 data, a connector-saver to Trompeter adaptor (channel quantity TBC) will be utilized so that CERN GSE data cables will be simple, existing twin-ax cables. January 10, 2007 T. J. Urban / ESCG 10

  11. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Interface Design Description • Test Connector Panel Concept: • A non-flight test connector panel will be mounted to the UUSS (forward & starboard) to connect the GSE provided “ISS” power and data services to the PDS and J-Crate. • This requires 6 flight cables to have new, interim, test cable configuration designs: -305 and -307 [test] instead of -301 and -303 [flight]. • The test configuration cables will be fully assembled at JSC, then delivered to CERN (July ’07). • The payload PDS, J-Crate and JPD connectors will be “FLIGHT” routed and connected to boxes at CERN – never to be disturbed. • The other ends of these cables, with extra length coiled, will be attached to the Test Connector Panel. • At KSC, the TCP will be removed and the -305/-307 cables will be re-routed and re-configured to the -301/-303 cables at the flight EVA Connector Panel. January 10, 2007 T. J. Urban / ESCG 11

  12. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Interface Design Description • Test Connector Panel Concept (continued): • The GSE power connections (2 of 6) at the TCP will be made via simple GSE connectors/cables. • The GSE data connections (4 of 6) at the TCP will be made via circular connector to Trompeter or ST fiber connectors. This will allow the CERN GSE cables to be simple, existing twin-ax or ST fiber cables. January 10, 2007 T. J. Urban / ESCG 12

  13. GSE & Test Cable & Adaptor Schematic 13

  14. Test Connector Panel Test Cable Routing Text Connector Panel Concept & Routing 14

  15. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Interface Design Description Responsibilities and Actions • JSC ESCG: • Provide Test cables and Adaptors • 6 test cables – quantity 1 each • Adaptor, circular to 8 channel twin-ax – quantity 2 • Adaptor , circular to 2 channel twin-ax – quantity 3 • Adaptor , circular to 4 channel fiber ST – quantity 2 • Loop-back connector, sub-miniature D 9 pin – quantity 3 • Design • Procurement of materials • Fabrication • Provide 6 connector savers for Interface Panel A – quantity 1 each • Provide mating connectors for 7 other GSE cables – quantity 2 each • Loan tools required for assembly of these 7 GSE cables January 10, 2007 T. J. Urban / ESCG 15

  16. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Interface Design Description Responsibilities and Actions (continued) • CERN / MIT: • Provide Trompeter twin-ax and fiber ST GSE cables. • Provide cables and chamber feed-throughs required for interfacing GSE cables / adaptors during payload TVT and EMI tests. • Assemble 7 GSE cables – quantity 2 each. • THE DATE ALL ITEMS ARE NEEDED IS TBD (probably 3rd quarter 2007). January 10, 2007 T. J. Urban / ESCG 16

  17. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests Pad Operations Preliminary Interface Test January 10, 2007 T. J. Urban / ESCG 17

  18. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests Pad Operations Preliminary Interface Test • Purpose: • Pin to pin verification of AMS-02 payload to AMS-02 GSE data channels via the STS Mobile Launch Platform (MLP) and T0 Umbilical wiring. • Transmission signal quality evaluation. • “Stake a claim” on required KSC MLP GSE cables and equipment. • Where: • KSC: MLP in Vertical Assembly Building (no Orbiter). • When: • April 2007, one week • Who: • PADSOFT: Dennett • ESCG: Urban and D. Nguyen • MIT: Lebedev, Koutsenko, Cai January 10, 2007 T. J. Urban / ESCG 18

  19. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests - POPIT 1553 Communications Test Configuration 1 January 10, 2007 T. J. Urban / ESCG 19

  20. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests - POPIT 1553 Communications Test Configuration 2 January 10, 2007 T. J. Urban / ESCG 20

  21. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests - POPIT RS-422 Communications Test January 10, 2007 T. J. Urban / ESCG 21

  22. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests - POPIT Responsibilities and Actions • ESCG / Urban to compile and distribute required materials list: • ESCG: Cables to be designed & fabricated and materials procurement • KSC: MLP and T0 Test cables and test equipment • STS / USA: Test PDIP • CERN / MIT: • Computers • Software (1553) – changes recommended by PADSOFT in test plan, will be forwarded by ESCG / Urban. • PADSOFT: RS-422 Software • Items must be ready for shipment by end of March ‘07. • This test will require KSC Test Readiness Review (March ’07). • Other issues: KSC access and Visas January 10, 2007 T. J. Urban / ESCG 22

  23. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests PDS EM Power Quality Test January 10, 2007 T. J. Urban / ESCG 23

  24. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests PDS EM Power Quality Test • Purpose: • Characterize PDS EM performance under load, and its affect on STS and ISS input power, as a design validation test. To include (from P. Lipoma): • Electrical Power Characteristics • Steady State Voltage • Ripple Characteristics • Transient Voltages • Normal Voltage Range • Electrical Power Interface • Power Bus Isolation • RPC Soft Start/Stop Compatibility • Surge Current • Reverse Energy • Other RPC Characteristics • Complex Load Impedance • Large Signal Stability • Electrical Power Constraints January 10, 2007 T. J. Urban / ESCG 24

  25. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests PDS EM Power Quality Test • Where: • JSC: Electrical Power Systems Laboratory (EPSL) • When: • June 2007, one week • Who: • JSC: EPSL staff • ESCG: Urban, Lipoma and D. Nguyen • MIT: Koutsenko, Koulemzine, Capell or Lebedev • CGS: Alia January 10, 2007 T. J. Urban / ESCG 25

  26. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests Block Diagram January 10, 2007 T. J. Urban / ESCG 26

  27. Alpha Magnetic Spectrometer Electrical Integrated Testing Status Upcoming Tests PDS EM Power Quality Test • Responsibilities and Actions : • ESCG coordination with JSC EPSL, including test plan and test procedures. • EPSL will provide test facility, input 120 VDC, and test equipment. • List of items to be provided by CGS: • Payload simulating load • Special test equipment • Cables • List of items to be provided by CERN / MIT: • PDS EM • Computer and CAN software • Cables • Date equipment should be ready to ship is the end of May ’07. • Other issues: JSC access and Visas January 10, 2007 T. J. Urban / ESCG 27