An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Electrical Power Status Thomas Nehring Conventional Facilities Advisory Committee Review October 5-6, 2010

  2. Outline • Main Substation • Ductbank and Feeder • Unit substations • Going Forward • Conclusions

  3. Main Substation • Main substation ~ 80% complete • 69kV Tower Work ~90% complete • Included 69kV bus mods, new insulators, new switches, new fuses • To be done - Installation & wiring of Potential Transformer • 69kV Breaker ~ 80% complete • Break installed • To be done – secondary wiring and testing • Main transformer ~ 90% complete • One radiator needs to be replaced, damaged during shipment • One weld needs to be repaired • Oil needs to be processed into tank • Balance of testing to be done, winding ratios and bushing tests have been done • Controls and instrumentation to be wired

  4. Main Substation - continued • Main substation - continued • 15kV Bus Duct and Low Voltage Wireway ~ 10% complete • Bus duct in fabrication, to arrive during October • Provisions for installation have started, opening on wall, supports • 15kV Switchgear ~ 80% complete • Switchgear installed • Bus tie to existing Bus 2 to be completed during October • Control wiring to main transformer and 69kV breaker remain • DC wiring to battery to be completed • Testing remains • Switchgear to be energized during October • 15kV Feeder ~ 30% complete • Raceway installed from switchgear to interface point (pull box located near south-east corner of building) • Feeder cable to be installed October

  5. Main Substation - continued

  6. Main Substation - continued

  7. Main Substation - continued

  8. Main Substation - continued

  9. Main Substation - continued • Main substation - continued • Miscellaneous Items Completed • 125 Vdc Battery • Lighting in yard • Secondary containment • Fire wall • Miscellaneous Items to be Completed • DC wiring • Interior lighting modifications • Steam piping modifications • Door replacement • Fire proofing of Building 603 • Grounding ~ 50% complete • Commercial Items • Approximately 4 change orders to be completed

  10. Ductbanks & Feeders Ductbank to be Installed

  11. Ductbanks & Feeders • 15kV ductbank complete less three segments • 480V ductbanks complete less one segment • 15kV Feeders • Cable pulling started late September • 480V Feeders • Cable pulling to start October

  12. Unit Substations & Switchgear

  13. Unit Substations & Switchgear • 6 of 8 unit substations installed • SUS- 2, 3, 5, LB, RF-1, RF-2 on location and assembled • final wiring and testing remains • SUS-4 yard ready for switchgear • SUS-1 last substation yard to be build, should be completed in October • 4 of 8 indoor switchgear lineups installed • Swgr’s 1, 2, 3 & 4

  14. Unit Substations & Switchgear

  15. Going Foward • Start-up: • Follow F & O’s BORE process • Ensure documentation and labeling complete • Perform standard tests for start-up • Manufacturer representative to be present during start-up • Have F & O participate to be present during start-up and review • Operations & Maintenance • Establish operation & maintenance program in F & O system • Turn over to F & O

  16. Conclusions • Power will be available for Beneficial Occupancy • Initial start-up power will be taken from Bus 2, approximately 7 MVA available • Substation contract will be completed around December 2010 • Main transformer will then be used, 20 MVA available • Operation of equipment to be coordinated with F & O tower line crew