1 / 12

Geospatial One-Stop

Geospatial One-Stop. FGDC Coordination Meeting 11/5/02 Myra Bambacus Acting Executive Director. Current Project Management Activities. Geospatial One-Stop Management Team. Scott Cameron Managing Partner. Board of Directors. Tony Frater G-G Portfolio Manager. Myra Bambacus Acting

mercedese
Download Presentation

Geospatial One-Stop

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Geospatial One-Stop FGDC Coordination Meeting 11/5/02 Myra Bambacus Acting Executive Director

  2. Current Project Management Activities

  3. Geospatial One-Stop Management Team Scott Cameron Managing Partner Board of Directors Tony Frater G-G Portfolio Manager Myra Bambacus Acting Executive Director Milo Robinson Rob Dollison Project Mgmt Support Leslie Wollack Outreach TBD Deputy Director TBD Module 1 Standards Development & Modeling TBD Modules 2 & 3 Existing Data Inventory Planned Data Acquisition Jeff de La Beaujardiere Modules 4 & 5 Portal Manager

  4. Geospatial One-Stop Project Plan

  5. Portal Plan – Version 1

  6. Framework Theme 1st Working Draft Available for Public Review Approved ANSI Standard Cadastral 11/26/02 2/12/03 8/21/03 Elevation 12/13/02 4/15/03 9/30 Geodetic Control 2/12/03 5/1/03 9/30 Government Units 1/8/03 3/27/03 9/30 Hydrography 11/15/02 2/3/03 8/12/03 Orthoimagery 11/14/02 1/17/03 7/28/03 Standards Summary Continued

  7. Trans – Roads Framework Theme 11/19/02 1st Working Draft 2/4/03 Available for Public Review Approved ANSI Standard 8/14/03 Trans – Air 12/24/02 3/11/03 9/18/03 Trans – Rail 12/19/02 3/6/03 9/15/03 Trans - Transit 12/05/02 2/21/03 9/11/03 Standards Summary Continued

  8. Kick Start of Portal • Acting Executive Director appoints a Portal Lead • Under the auspices of the Geospatial Applications and Interoperability Working Group (GAI WG) • In Coordination with FGDC and OGC • Participation in action • Proposed Start of Method with Schedule presented to the Board of Directors 10/9/02 • Vision: Portal will be the mechanism for other “portals” to plug into for access by all sectors

  9. Board Results • Motions Passed • Charter • Homeland Security Standard Request of 9/30 • First Gov to Host GOS Web site • Extend state and local participation further • Methodology for Portal Development Plan

  10. Geospatial One-Stop Portal Concept • Portal is an online access point for geospatial data, maps of data, and metadata about data • Information is stored at data provider sites, not in Portal • Portal utilizes open standards for interoperability • Geospatial web service specifications • Metadata and content standards • Portal builds upon NSDI by providing direct access to data specific to task & location • Web-based user interface for human access • Application interface for GIS/DSS access

  11. Portal Implementation Plan • Implement Portal via OGC Interoperability Initiative • Plan approved by Geo 1-Stop Board Oct 9 • Multi-vendor solution with proven track record • Geo 1-Stop agencies provide cost-sharing resources • Portal Team is developing: • requirements • conceptual architecture • selection criteria

  12. Portal Status • First task complete: Call For Additional Requirements • to broad spectrum of state/local/tribal/federal groups • Next step: develop RFQ to be issued by OGC • spell out technical requirements in detail • include responses from Call For Additional Rqmts • Major milestones: • RFQ release Dec 6 • Initiative kickoff early February 2003 • Portal demonstrated & installed late May

More Related