An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Readout Chamber Status TRD Status Meeting 28.2.06 Clemens Adler

  2. News • Will have regular meeting few days before status meeting, via Video/Skype dedicated to chamber construction issues. • Chambers from Dubna/Bucharest will be tested (leakrate/HV) at Hd (by Clemens) • Some chambers with long O2 decay time constant (‘Virtual Leaks’) • > will be marked on chamber and in Database

  3. News cont. • Chambers from Bucharest will be shipped march,6. March 11 Bucharest people will come to unpack and examine chambers. • Broken Dubna Chambers: • 2 Technicians from Dubna are at GSI now: • 15 Chambers will be repaired • 3 chambers have broken Rohacell on the chamber side of radiator: could be repaired, but question of gas tightness (Christian will think about it).

  4. Production Status Since Christmas: 40 more (finished) chambers: Global rate: 6 chambers/week

  5. Production rate

  6. Production Schedule (60% TRD) • If we get more money: • 100% of chambers (324 for 60%, 270 for 50%) will be achieved in any case without need for any changes by end of Okt 2006. • If no more money flows: • Heidelberg/GSI could take over some L0C1 production from Frankfurt • Dubna will delay if 60%TRD, OK if 50%TRD

  7. New 75% chambers complete Milestone • New milestone is required: 75% of chambers complete. • Counting chambers (regardless of type): • 75% (of 50%=203 chambers): 11.4.06 • 75% (of 60%=243 chambers): 12.6.06 ->75% interpolation between 50% and 100% milestone: 5/2006 ->75% Milestone: 6/2006 or 7/2006 • Same definition: 100%(270 chambers) achieved in 20.7. 2006

  8. Production Rate Frankfurt: • Theoretical rate: 1 chamber/ week • Optimistic: 3 ch/4 weeks (0.75) → 100% of 50/60%: 15.2.2007 100% of 100%: Jan. 2008 • Conservative: 0.5 ch/week 100% of 50/60%: 17.7.2007 100% of 100%: Nov. 2008

  9. Production Rate cont. • Bucharest: • Since April 2005: average rate of 1 ch./week • Since christmas: average rate of 1.6 ch./week • Optimistic: 1.5 ch./weeks → 100% of 50/60%: 12. 9. 2006 100% of 100%: 14.8. 2007 • Conservative: 4ch/3weeks (1.3 ch/w) → 100% of 50/60%: 5.10. 2006 100% of 100%: 18.10. 2007

  10. Production Rate cont. • GSI • Since April 2005: average rate of 1 ch./week • Since christmas: average rate of 1.5 ch./week • Optimistic: 1.5 ch/week → 100% of 50/60%: 5.7. 2006 100% of 100%: 6.7. 2007 • Conservative: 4 ch./3 weeks (1.3) → 100% of 50/60%: 20.7. 2006 100% of 100%: 4.9. 2007

  11. Production Rate cont. • Dubna • Since April 2005: average rate of 1 ch./week • Since christmas: average rate of 0.7 ch./week • Optimistic: 1.5 ch./ week → 100% of 50%: 1.4. 2006 100% of 60/100%: 17.10. 2006 • Conservative: 1ch./week → 100% of 50%: 11.4. 2006 100% of 60/100%: 26.1. 2007

  12. Production Rate cont. • Heidelberg: • Since April 2005: average rate of 0.4 ch./week • Since christmas: average rate of 0.7 ch./week • Optimistic: 4 ch./6 weeks (0.7) → 100% of 50/60%: 28.6. 2006 100% of 100%: 13.8. 2007 • Conservative: 0.5 ch/week → 100% of 50/60%: 11.9. 2006 100% of 100%: 28.1. 2008