Progress on and status of the forward multiplicity detector
This presentation is the property of its rightful owner.
Sponsored Links
1 / 8

Progress on and Status of the Forward Multiplicity Detector PowerPoint PPT Presentation


  • 49 Views
  • Uploaded on
  • Presentation posted in: General

Progress on and Status of the Forward Multiplicity Detector. Kristj án Gulbrandsen Niels Bohr Institute. Assembly and Transport. FMD3. FMD2. CERN. Arrival and Unpacking. Shipped and unpacked TPC cleanroom used for testing and verification. Installation.

Download Presentation

Progress on and Status of the Forward Multiplicity Detector

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Progress on and status of the forward multiplicity detector

Progress on and Status of theForward Multiplicity Detector

Kristján Gulbrandsen

Niels Bohr Institute

Kristján Gulbrandsen, NBI


Assembly and transport

Assembly and Transport

FMD3

FMD2

CERN

Kristján Gulbrandsen, NBI


Arrival and unpacking

Arrival and Unpacking

  • Shipped and unpacked

  • TPC cleanroom used for testing and verification

Kristján Gulbrandsen, NBI


Installation

Installation

  • Case carried to main building

  • Brought to pit via elevator

  • Crane put case on scaffolding

  • Unpacked and carried to IP

  • Installed in halves around beampipe on temporary support

  • Cabled up

Kristján Gulbrandsen, NBI


Issues

Issues

  • Some readout cables severed during packaging for shipping

  • Some fixable module damage

    • Damaged bonding wires

    • Damaged hybrid connector

  • HV patch cable connector damaged

    • Changed to different type connector for FMD2

  • Some power cable cross-sections increased

    • -2V supply for FMD3 had cross-section doubled

    • Cables for FMD1 and FMD2 quadrupled in cross-section (cables also twice as long)

Kristján Gulbrandsen, NBI


Testing

Testing

  • Commissioned using DAQ and Trigger subsystems

  • HV from CAEN power supply, LV from test power supplies (not CAEN)

  • Commissioning testing showed noise consistent with lab tests

  • Some optimization can be performed

    • Should be done after we have final LV power supplies

Kristján Gulbrandsen, NBI


Progress on and status of the forward multiplicity detector

DCS

  • PVSS control/monitoring of HV, LV, and detector implemented

  • Some debugging required - HV control has been used

  • Alexander Kurepin of T0 group collaborating to finish DCS work

Kristján Gulbrandsen, NBI


Remaining tasks

Remaining Tasks

  • Install FMD2 on June 24

  • Finish A-side cabling

  • FMD2 testing at service chariot - end of July after TPC is in IP

  • FMD1 is under construction, installation - early October

  • DCS integration from early August

  • Commissioning with CAEN LV power supplies (when?)

  • Install final trigger configuration

    • Final TTC fiber

    • Fan-in Fan-out

Kristján Gulbrandsen, NBI


  • Login