Progress on and status of the forward multiplicity detector
Download
1 / 8

Progress on and Status of the Forward Multiplicity Detector - PowerPoint PPT Presentation


  • 87 Views
  • Uploaded on

Progress on and Status of the Forward Multiplicity Detector. Kristj án Gulbrandsen Niels Bohr Institute. Assembly and Transport. FMD3. FMD2. CERN. Arrival and Unpacking. Shipped and unpacked TPC cleanroom used for testing and verification. Installation.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Progress on and Status of the Forward Multiplicity Detector' - makaio


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Progress on and status of the forward multiplicity detector

Progress on and Status of theForward Multiplicity Detector

Kristján Gulbrandsen

Niels Bohr Institute

Kristján Gulbrandsen, NBI


Assembly and transport
Assembly and Transport

FMD3

FMD2

CERN

Kristján Gulbrandsen, NBI


Arrival and unpacking
Arrival and Unpacking

  • Shipped and unpacked

  • TPC cleanroom used for testing and verification

Kristján Gulbrandsen, NBI


Installation
Installation

  • Case carried to main building

  • Brought to pit via elevator

  • Crane put case on scaffolding

  • Unpacked and carried to IP

  • Installed in halves around beampipe on temporary support

  • Cabled up

Kristján Gulbrandsen, NBI


Issues
Issues

  • Some readout cables severed during packaging for shipping

  • Some fixable module damage

    • Damaged bonding wires

    • Damaged hybrid connector

  • HV patch cable connector damaged

    • Changed to different type connector for FMD2

  • Some power cable cross-sections increased

    • -2V supply for FMD3 had cross-section doubled

    • Cables for FMD1 and FMD2 quadrupled in cross-section (cables also twice as long)

Kristján Gulbrandsen, NBI


Testing
Testing

  • Commissioned using DAQ and Trigger subsystems

  • HV from CAEN power supply, LV from test power supplies (not CAEN)

  • Commissioning testing showed noise consistent with lab tests

  • Some optimization can be performed

    • Should be done after we have final LV power supplies

Kristján Gulbrandsen, NBI


DCS

  • PVSS control/monitoring of HV, LV, and detector implemented

  • Some debugging required - HV control has been used

  • Alexander Kurepin of T0 group collaborating to finish DCS work

Kristján Gulbrandsen, NBI


Remaining tasks
Remaining Tasks

  • Install FMD2 on June 24

  • Finish A-side cabling

  • FMD2 testing at service chariot - end of July after TPC is in IP

  • FMD1 is under construction, installation - early October

  • DCS integration from early August

  • Commissioning with CAEN LV power supplies (when?)

  • Install final trigger configuration

    • Final TTC fiber

    • Fan-in Fan-out

Kristján Gulbrandsen, NBI


ad