Project Status. J. Roberts PALM-3000 System Coordination Meeting #17 9/2/10. Components. Electronics DM cables expected next week HODM boxes still in debug, but mostly functional LODM and TTM boards go to fab next week Infrastructure Electrical work complete

ion
Download Presentation

Project Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Status J. Roberts PALM-3000 System Coordination Meeting #17 9/2/10

  2. Components • Electronics • DM cables expected next week • HODM boxes still in debug, but mostly functional • LODM and TTM boards go to fab next week • Infrastructure • Electrical work complete • Add fiber between computer room and AO lab next week • Cooling work progressing - All hardware expected by mid-October • Software • RTC working at min 1000Hz with servo control of HODM • 2kHz working, but not fully tested with HODM • GUI – ACAM, HOWFS pixels, HODM residuals and positions, Motor control, and HWFP parameters are complete • Currently working on debugging and improving the database, which is also essential to the stability of the overall system • Optics • Optical relay fully aligned with RMS WFE of ~60nm at science, mostly 0 astigmatism • CMM measurements of all optics complete • Next to be installed will be the LODM and the new HOWFS • After the review, once the computers are set up at Palomar

  3. Lab Work • First closed loop results show stability and improvement even at very low gains • The gains are: integral=.01, leaky/flatmap=.001. It's using centroid offsets that null out the base wavefront error. The RTC is running at 500Hz. • The movie shows HODM residuals (nm of surface error). The junk at the bottom is optical. The junk in the upper right is a problem with the P3k control electronics

  4. I&T Review • We’re proposing to have a review of progress and our I&T plan on September 22nd • Proposed Agenda • System Overview (incl. management overview) • Systems Engineering (modes, performance) • Subsystem Details (work complete, work remaining) • Optics & Mechanics • Software • Computers & Electronics • Infrastructure • I&T plan • Remaining work before shipping - plans, schedule, etc • Remaining work before 1st light - plans, schedule, etc • Risk review • Lab Demo • Executive Session