1 / 5

GEM Production and HBD Reconstruction Update

This update provides information on the completion of GEM production at WIS and the progress of HBD reconstruction, including the testing and installation of GEM foils, the status of defective GEMs, and other related activities.

hragsdale
Download Presentation

GEM Production and HBD Reconstruction Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HBD Status Craig Woody BNL DC Meeting October 3, 2007

  2. GEM Production Completed at WIS • Framing and full testing of the 55 GEM foils (25 Au plated and 30 standard) ordered from CERN have been completed • On each foil, the production consists of the following steps (same procedure as last year): 1. 100V test in air before framing 2. 100V test after framing 3. 100V test after soldering SMD resistors (steps 1-3 are done in a clean room) 4. 550V test in CF4 5. Gain mapping in Ar/CO2 at 484V (steps 4 and 5 are done inside stainless steel test box) • Results A. Out of the 30 Standard GEMs: 28 passed all tests in the first try. 1 was damaged by us 1 had a production defect and was not framed. B. Out of the 25 Au plated GEMs: 16 passed all tests in the first try. 4 failed test #4 in the first try. They passed this test the second time after washing in de-ionized water. 4 failed test #4 even after the washing and were declared bad. 1 was accidentally damaged by us. • Status • The defective GEMs (1 standard and 4 Au plated) were sent to CERN for replacement. • All good GEMs including spares from last year are already at SUNY (with the exception of 15 standard GEMs that are at WIS). C.Woody, DC Meeting, 10/3/07

  3. HBD West Reconstruction Things are going more slowly than expected • Upon arrival at Stony Brook, GEMs are full tested • again in nitrogen and then given a long term test • in CF4. Modules are required to reach full gain • (~ 5000) and hold voltage for many hours. • This is very time consuming, but is equivalent • to the test and conditioning they would undergo • in situ at the IR • Presently takes ~ 1 week to fully test and install • one module • Several GEMs have failed the long term test • (sparked and damaged foils) • We plan to speed the testing and conditioning • process up by ~ factor 2 by sending a second • test box from Weizmann to Stony Brook 3 fully tested modules installed in HBD West Have reduced external capacitance to a minimum and installed relay protection circuit to protect GEM from damage from sparks C.Woody, DC Meeting, 10/3/07

  4. HBD East Removed • HBD East was removed from the East • Carriage on 10/1 and moved to Stony Brook • Presently under N2 gas flow waiting for • rebuilding after HBD West • Gas system will be modified to increase flow • to ~ 10 lpm C.Woody, DC Meeting, 10/3/07

  5. Other Activities • Further investigation of BERTAN PS for testing shown that it might be dangerous. Currently not in use. WIS sent a CAEN PS model 471 for the single GEM test. Currently in transit • WIS will send next week its stainless steel test box to speed up conditioning (present bottleneck in the stack assembly) • All new HV divider boards are out of production, the first one is ready with all resistors • Work on protection relay boards is ongoing • Question: Is is possible to install HBD West after the shield wall is closed ? C.Woody, DC Meeting, 10/3/07

More Related