An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SAFCA Board Update Dan Tibbitts Senior Project Manager Common Features Levee Programs Branch Sacramento District 15 March 2012

  2. Actions since last Board Briefing Funding: • ARCF well funded for FY-12 Natomas PAC: • Activities on Natomas on hold pending project authorization ARCF GRR: • A meeting with Corps HQ and South Pacific Division was held on 2 March. It was agreed that the Feasibility Scoping Meeting held in March 2009 was adequate for the GRR. WRDA 1996 & 1999 Project Sites: • Real estate coordination for construction contracts awards in September continues • Critical programmatic agreement for permanent easements is not being pursued by DWR.

  3. Cooperation with SAFCA & CVFPB Natomas PAC: • Corps activities on hold pending authorization • Sponsor continues to work crediting package request ARCF GRR: • The collaboration with the sponsors continue on GRR activities • Team refining preliminary designs on alternatives • Schedule revisions are being worked by the project team ARCF WRDA 96 & 99 Project Sites: • 10 designs under contract with P&S due in May 2012 continue on schedule • Turn over of 4 completed WRDA sites in 2012

  4. Challenges Funding: ARCF is well funded for this fiscal year. No funding in Presidents FY-13 budget for GRR. ARCF Natomas Basin: • Encroachments on levees • Project Cooperation Agreement (PCA) Amendment • Crediting Report ARCF GRR: • Encroachments and vegetation on levees • Funding to continue GRR activities in 2013 ARCF WRDA 1996 & 1999 Sites: • Real estate certification being worked by State Real Estate Office for Summer 2012 • State certification of permanent easrments is critical for award of planned construction contracts this year • Design continues on remaining WRDA sites for completion in May 2012 • 4 EAIS will be presented at State Board Meeting for approval in August • State approval critical for bid opening and awards of planned construction contracts this year

  5. Major Actions Natomas PAC: • Natomas PAC authorization - TBD • Crediting Report (Approved Post Authorization) – TBD • PCA Amendment (Approved Post Authorization) - TBD ARCF GRR: • Alternative Review Conference – Scheduled for Dec 2012 • Alternative Formulation Briefing – Scheduled for September 2013 ARCF WRDA 1996 & 1999 Sites: • Construction Start for Site R6 and Howe Avenue Site are on track for July 2012

  6. ARCFGeneral Reevaluation ReportProject Area

  7. ARCF WRDA 96 & 99 Sites Project Area

  8. Questions? Next Corps Briefing to SAFCA Board is on 17 May 2012 US Army Corps of Engineers Sacramento District Common Features Levee Programs Branch 1325 J Street, Suite 970 Sacramento, CA 95814-2922