Project No 2004/LV/16/C/PE/001 Development of water services in Ventspils, stage II

Project No 2004/LV/16/C/PE/001 Development of water services in Ventspils, stage II. General information. European Commission Decision signed on 28/12/2004 End date of eligible expenditure 31/12/2010 Total approved eligible expenditure for the project - EUR 21,783,620.00

erling
Download Presentation

Project No 2004/LV/16/C/PE/001 Development of water services in Ventspils, stage II

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project No 2004/LV/16/C/PE/001 Development ofwater services in Ventspils, stage II

  2. General information European Commission Decision signed on 28/12/2004 End date of eligible expenditure 31/12/2010 Total approved eligible expenditure for the project - EUR 21,783,620.00 CF funding – EUR 18,516,007.00 Absorbed funding ~ 72 % Status of agreements: Within the project 25 agreements were signed (19 for works, 2 for services and 4 for supplies), incl. 1 agreement for works that was terminated with mutual arrangement. In Q1-3 2008 it is planned to launch 5 procurements. Implementation of 9 agreements for works and 4 supply agreements has been completed. Municipal company SIA “ŪDEKA” 11 April 2008 2

  3. Project activities and objectives in stage II (2006-2009) 1. Reconstruction of water main and sewerage network of more than 70 km; 2. Extension of water main and sewerage network of more than 60 km; 3.Reconstruction of main pressure conduits (Ogsils-road to Kolka and mains within city borders) ~ 8 km; 4. Supply of equipment for maintenance of networks; 5. Installation of water consumption meters; 6. Replacement of hydrants and valves. Priority - increase network coverage in the city and provide centralised water supply and sewerage services for up to 92% of population in Ventspils, particularly those residing in private home areas where these services are not yet available Construction works planned in ~130 street sections and inner yards of multi-apartment buildings in Ventspils. Municipal company SIA “ŪDEKA” 11 April 2008 3

  4. Project funding for stage II (2006-2009)approved budget Municipal company SIA “ŪDEKA” 11 April 2008 4

  5. Project progress in stage II 2006-2007 (I) 2006 2007 1. Extension of water main network and reconstruction 5.9 km 9.03 km 2.  Household sewerage networks extension and reconstruction 8.2 km 10.5 km 3.Construction of rain wastewater networks 6.1 km 6.4 km 4. Reconstruction of main pressure conduit (km) 5.2 km ___________________________________________________________ TOTAL 20.2 km 31.13 km 4. Network servicing and maintenance equipment 15 pcs. 5. Installation of water consumption meters continues 6. Replacement of hydrants and valves started Municipal company SIA “ŪDEKA” 11 April 2008 5

  6. Project progress in stage II 2006-2007 (II) Number of sites put into operation: - in 2006 - 21 sites, incl. in 15 street sections of Ventspils city, in 4 inner yards of multi-apartment buildings. - in 2007 - 19 sites, incl. in 15 street sections of Ventspils city, in 3 inner yards of multi-apartment buildings, reconstructed water main from the water abstraction point "Ogsils" up to the road to Kolka. Municipal company SIA “ŪDEKA” 11 April 2008 6

  7. Further implementation of works in stage II of the project in 2008-2009(amended)(I) So far: Construction works started in 2007 continue,incl. in Gāliņciems (11 sites), on Rūpniecības Street (Durbes Street - Liepāja railway crossing point); Installation of duplicate power supply for the sewerage pumping station at 2 Muitas Street; replacement/installation of valves and hydrants; technical supervision of works. By 01/04/2008 Agreement for works to be signed for 2 objects, where the successful tenderer has been announced. Works to be completed by 12/2008; 03-05/2008 Procurement to be launched and agreements for works to be signed for 12 sites (planned in 2008), works to be completed by~12/2008. Municipal company SIA “ŪDEKA” 11 April 2008 7

  8. Further implementation of works in stage II of the project in 2008-2009(amended) (II) 06- 08/2008Procurement to be launched and agreements to be signed for works in 13 sites (planned in 2009). Works to be completed by~11/2009. By 12/2008 Construction to be completed in 28 sites in Gāliņciems, Kurpniekciems and reconstruct.sites; By 12/2008 Replacement of hydrants and valves completed; By 12/2008 Reconstr.of city water main completed0.73 km; 09/2008– 09/2009 Works to be completed in sites planned for 2009 (incl. works in Jāņciems (private home area inPārventa) planned to start in September 2008). 41 sites to be put into operation in 2008, installation/replacement of hydrants and valves to be completed. 19 sites to be put into operation in 2009, installation of water meters to be completed. Municipal company SIA “ŪDEKA” 11 April 2008 8

  9. Changes to scope of works and funding planned in stage II of the project (I) • REASONS for increase of project costs: • rapid growth of construction costs compared to the budget approved by the EC Decision in 2004; • lack of competition in the construction sector in Latvia; • increase in cost of resources globally. • CONSEQUENCES: • Total budget increases by 79 %, namely from EUR 21.7 M to EUR 38.9 M; • Due to insufficient funding the scope of works must be reduced (~36 sites); • Physical indicators set in the EC Decision not to be reached in at least 3 components - newly built water supply networks, sewerage networks, installation of water meters. • NOTES: • - The scope of works is planned to be reduced only to the extent that still would allow reaching the objectives set in the EC Decision • (at least 88-90% of population in Ventspils to be provided with centralised water services); • - amendments to the physical indicators and amount of funding in the EC Decision required; • - sites excluded to be included in stage III of the project to reach the original objectives (providing at least 95% of population in Ventspils with centralised water services), thus significantly increasing the scope of works in stage III and the co-financing part of the project implementer, which poses the risk for project not to be implemented at the scope initially planned. Municipal company SIA “ŪDEKA” 9 11 April 2008

  10. Funding for stage II of the project (2006-2009)Budget with increase in costs based on costs in agreements signed, forecasted costs for 2009, reduction of scope of works by ~36 sites. Municipal company SIA “ŪDEKA” 11 April 2008 10

  11. Changes to scope of works and funding planned in stage II of the project (II) • SOLUTIONS: • Additional funding received for increase in costs of the project in 2006-2007 - EUR 8.7 M, incl. EUR 7.4 M from State budget (85% of the increase in cost), while EUR 1.3 M (15% of the increase in cost) to be covered by the municipal company SIA “ŪDEKA”; • To cover the increase in costs on 19/02/2008 the Cabinet of Ministers approved allocation of 44% of state budget funding, provided the project implementer would co-finance 56%, and approval received from the EC for reduction of scope of the project. The estimated increase in cost is EUR 8.4 M, incl. • co-financing from Ventspils City Council EUR 3.2 M, • co-financing from SIA “ŪDEKA” EUR 1.4 M, • state budget co-financing EUR 3.7 M. Municipal company SIA “ŪDEKA” 11 April 2008 11

  12. Changes to scope of works and fundingplanned in stage II of the project (3) • In order to receive approval from the EC, an updated CBA for the feasibility study of stage II of the project has been started); • PSIA “Ūdeka” has identified ~36 sites where the works cannot be carried out for the funding from the period of 2000 – 2006 due to inflation. These sites will be a priority for the EU Funds in the 2007 - 2013 programming period.

  13. Proposed amendments to EC Decision Drafting of amendments to the EC Decision and physical indicators has been started. Submission to the Intermediate Body and the EC planned in 2009.

  14. THANK YOU FOR YOUR ATTENTION! Municipal company SIA “ŪDEKA”