1 / 17

TRANSMISSION INFRASTRUCTURE IMPROVEMENTS — Current Projects —

TRANSMISSION INFRASTRUCTURE IMPROVEMENTS — Current Projects —. Steve Wheeler Executive Vice President Arizona Public Service Company. The Center for the New West “ The Sun Valley Energy Roundtables 2006” November 30 – December 1, 2006. About APS.

ellema
Download Presentation

TRANSMISSION INFRASTRUCTURE IMPROVEMENTS — Current Projects —

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TRANSMISSIONINFRASTRUCTURE IMPROVEMENTS— Current Projects — Steve WheelerExecutive Vice PresidentArizona Public Service Company The Center for the New West“The Sun Valley Energy Roundtables 2006”November 30 – December 1, 2006

  2. About APS A subsidiary of Pinnacle West Capital Corporation • Largest electric utility in Arizona • Second fastest growing utility in country • Peak Control Area load over 7700 MW • Over 1 million customers • $1 billion Ten-Year In-state transmission expansion plan

  3. Transmission – East vs. West

  4. Increasing Transmission Capability OPTIONS • Upgrade existing system • New conductor technologies • New facilities • Advanced technologies for control • Integrated resource planning

  5. Use of New Conductor Technology • Re-conductor West Phoenix-Lincoln Street 230kV line • 3M Aluminum Conductor Composite Reinforced (ACCR)

  6. Palo Verde Hub – TS5 – Raceway – Pinnacle Peak 500kV Project • New 500 kV system connecting SW Phoenix to NE Phoenix • Add 1500 MW import capability to Phoenix Area • Provide additional export capability for generation at Palo Verde Hub • Provide voltage support for NE Phoenix Area • $0.6B for 110 miles of line and substation equipment

  7. Palo Verde Hub to Yuma 500kV • Provide 2nd 500kV source from Palo Verde Hub to Yuma • Provide transmission import capability to serve rapid load growth in theYuma Area • Provide additional export capability for generation at the Palo Verde Hub • In service date 2012 • Permitting work underway • $300M cost estimate for 115 mile line and substation equipment

  8. Dave Johnston Conceptual TransWest Express ProjectDC Option

  9. TransWest Express Project Summary • Driven from LSE need • Enables renewable wind and advanced clean coal technologies • Open stakeholder process • Transmission and permitting feasibility analysis essentially complete • Coordinating with Frontier activities

  10. TransWest Express Project Timeline • 2006 Phase 1 feasibility study • 2007-2011 Phase 2 permitting • 2012-2015 Phase 3 construction • 2015 Phase 4 commercial operation

  11. Feasibility Study Conclusions • Technically feasible • Economics indicate DC or AC/DChybrid alternatives • Multiple routes viable with minimal impact on sensitive environmental areas • Existing plans for AZ-CA expansion provide increase transfer capability in excess of 3000MW

  12. TransWest ExpressCurrent Status • Phase 2 Agreement in negotiation • Participants: • APS • SRP • SCE • TEP • National Grid • Wyoming Infrastructure Authority

  13. Phase 2 Work Plan • Five year schedule 2007- 2011 • Estimated cost of approximately $115M • Engineering and design • Routing • Permitting and approvals • Outreach and coordination • Options on right of way

  14. Coordination with Frontier Line Activities • APS participant in Frontier Line feasibility study • TransWest Express one of transmission options in Frontier study • Frontier economic analysis will include TransWest Express • Possible participation in TransWest Express by Southern California load serving entities

  15. Increasing Transmission CapabilityKey Considerations • Resource needs • Renewable requirements • Resource diversity • Financial considerations • Business model • Siting feasibility • EPACT provisions • FERC initiatives

  16. Coordination of Generationand Transmission • Can’t invest in one without assuranceof the other • Timing issues • Permitting • Construction • FERC Standards of Conduct • IRPs • Regional transmission planning activities

  17. Conclusion • Transmission expansion remains a daunting exercise in engineering, siting, technology, economics, and public policy • Coordinated planning and cooperation at all levels is essential • A stout heart is required

More Related