1 / 104

PowerNex Associates Inc.

PowerNex Associates Inc. Module 3 Transmission and Distribution. www.pnxa.com. Module 3 Transmission and Distribution. Learning Objectives: To gain an understanding of the following: Transmission system overview (4A) Components Types of transmission limits

donar
Download Presentation

PowerNex Associates Inc.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PowerNex Associates Inc. Module 3 Transmission and Distribution www.pnxa.com

  2. Module 3Transmission and Distribution Learning Objectives: To gain an understanding of the following: • Transmission system overview (4A) • Components • Types of transmission limits • Major transmission limits in Ontario • Protection Control and Metering (4B) • Concepts of Special Protection Systems (4C) • Distribution (4D) • How it’s different to transmission

  3. Module 3ATransmission

  4. Module 3ATransmission What will be covered • Basic Transmission Components • Overview of Transmission System • Limits - where do they come from & why do we need them • Internal Key Interfaces and effects on Generation • Normal, High Risk and Emergency Operation • Ontario Interconnections • Transmission Impactive Outages

  5. Transmission • Basic Transmission Components • Overview of Transmission System • Limits - where do they come from & why do we need them • Internal Key Interfaces and effects on Generation • Normal, High Risk and Emergency Operation • Ontario Interconnections • Transmission Impactive Outages

  6. TransmissionThe Single Line Diagram • The Single Line Diagram is a simple representation of the power system or a portion of it. • It shows the system as only one phase rather than three. • Its purpose is to show the power system with minimum detail, ie an overview of what’s connected to what.

  7. TransmissionBasic Transmission ComponentsSingle Line Diagram

  8. SF6 Circuit Breaker Transmission

  9. Air Blast Circuit Breaker Transmission

  10. Bulk oil circuit breaker Transmission

  11. Disconnect switch Transmission

  12. Transmission • What happens when a disconnect switch is used instead of a circuit breaker? • Not pretty!

  13. A 3 phase Transformer Transmission

  14. TransmissionPower Transformer

  15. Transmission • Basic Transmission Components • Overview of Transmission System • Limits - where do they come from & why do we need them • Internal Key Interfaces and effects on Generation • Normal, High Risk and Emergency Operation • Ontario Interconnections • Transmission Impactive Outages

  16. Transmission • Transmission Lines in parallel, if lose one, flow is redistributed • Generally not so for Distribution lines (radial) • Parallel lines lower the impedance, the more parallel lines the higher the reliability and the lower the losses (I2R) • The higher the voltage, the greater the power carrying capacity (proportional to V squared) • Maximum power carrying ability at Surge Impedance Loading (when reactive inductance and reactive capacitance of line are equal and thus cancel each other, leaving only the resistance).

  17. Transmission Typical Power Grid System

  18. Transmission

  19. TransmissionElectrical Equivalent to Water Analogy Generator (tap - water supply) -Provides Energy (MW), voltage support, &frequency support Electrical Bus (Bucket) -Critical Voltage, Current, Frequency & Short Circuit Level Transmission Lines (Pipes) Impedance (Fixed Resistance to Flow) Variable Loads (tap - water removal) Absorb MW and Voltage Support, Critical Voltage and Frequency Levels

  20. Transmission • Typical Surge Impedance Loadings • 500 Kv - 1,000 Mw • 230 Kv – 200 Mw • 115 Kv – 50 Mw • Ontario System made up of 500 Kv, 230 Kv, 115 Kv. • Distribution voltages < 50 Kv

  21. Double circuit EHV Transmission line Transmission

  22. Transmission • Basic Transmission Components • Overview of Transmission System • Limits - where do they come from & why do we need them • Internal Key Interfaces and effects on Generation • Normal, High Risk and Emergency Operation • Ontario Interconnections • Transmission Impactive Outages

  23. TransmissionHistorical Note 1965 Northeast Blackout • One 230 kV circuit at Beck (Q29BD) tripped • Four other circuits at Beck cascade trip within 2.7s • 1700 MW power surge into New York causing a wide-spread blackout • NPCC formed to ensure utilities in the northeastern part of North America adopt practices to prevent another blackout

  24. Transmission

  25. Transmission • Three basic types of limits: • Thermal • Voltage Decline/ Rise • Stability • Also Short Circuit limits

  26. Transmission Thermal Limits • Lines designed to operate to specific “ground” clearance and maximum conductor temperature • Line clearance reduced as conductor temperature rises (sag) • Ground clearance decreases as • Current flow increases • Ambient temperature rises • Wind velocity decreases • Sunlight increases Safe Ground Clearance

  27. Transmission Thermal Limits – Limited Time Ratings

  28. Transmission Thermal Limits also apply to equipment other than lines • For example: Transformers • Rated in MVA • Require sufficient cooling to dissipate heating • Hot spot and oil temp limits • As with lines, limited time ratings

  29. Transmission Voltage Limits • Must be able to sustain Voltage levels both pre and post contingency • Low or high voltages can cause equipment damage to Hydro One or Generator assets and also customer equipment • Under normal conditions, continuous voltages are to be maintained within predefined levels. • For example: • 115 Kv voltage must be between 127* Kv and 113 Kv • 230 Kv voltage must be between 250Kv* and 220 Kv • 500 Kv must be between 550 Kv and 490 Kv * In Northern Ontario 132 Kv and 260 Kv

  30. Transmission Voltage Limits • Transformer Voltages • Steady State Ratings, Maximum Acceptable Levels • 110% of Input Winding Rating, • 105% of Output Winding Rating at Full Load

  31. Transmission Stability Limits • These are the most complex limits • Instability can cause cascading outages • Affects generators, they go out of synchronism, “pole slipping”, “out of step” are terms used. • Stability usually a problem on a system with long transmission lines • If the receiving end voltage “angle” lags the sending end voltage “angle” by 90 or more degrees, then unstable

  32. TransmissionStability

  33. TransmissionStability

  34. TransmissionSummary ofSecurity Criteria • Voltage Levels,meet customer and equipment voltage limits • Stability, acceptable damping • Element Loading, operate to appropriate thermal rating of equipment • Short Circuit, breakers have capability of clearing worst short circuit condition

  35. Transmission“Bad Things happen” • What bad things can happen? • Virtually anything, but must be practical and reasonable. • Following 1965 Blackout NPCC developed a practical list of “bad things” • All members of NPCC must operate their systems by being able to recover from events on this list without having adverse effects on the systems of other members. • This costs money due to congestion. But the costs of a cascading blackout far outweigh the congestion costs.

  36. TransmissionRecognized “Bad Things” (Contingencies) - NPCC Criteria • Permanent 3-Phase fault (worst kind of fault) – with normal fault clearing • Simultaneous permanent phase to ground faults on adjacent circuits (same tower) – with normal fault clearing • Permanent phase to ground fault on any generator, circuit, transformer or bus section - with delayed fault clearing (Breaker Failure) • Loss of any element without a fault • Permanent phase to ground fault on circuit breaker - with normal fault clearing • Failure of a circuit breaker, associated with a Special Protection Scheme, to operate

  37. TransmissionHow are limits developed? • Limits are developed using computerised simulation studies. • A data base representing all of the power system components, their electrical characteristics and their connectivity has been developed and is constantly being updated when new equipment is added to the system. • This data base also includes data on interconnected systems (electrically it’s all one big system) • Application software is used by engineers to run fault simulation studies and test the operation of the system following a particular fault. • From the results of these studies operational security limits are produced.

  38. TransmissionHow are limits developed? Thermal Limits • Fairly simple • Off line load flows predict the change in flows on remaining elements post contingency, ie distribution factors • In real time these distribution factors are used to predict change in loading on the remaining elements following a contingency • Thus the operator can determine pre-contingency loading on other lines

  39. TransmissionHow are limits developed? Voltage Limits • Developed by off line simulation studies • Use NPCC criteria to “throw” faults at the system • Calculate the post contingency effects on voltage • Are post contingency voltages within limits? If OK move on to next simulation. If not OK then reduce pre contingency loadings (by redispatch) in the simulation until can meet post contingency voltage criteria. • This then becomes the Operating Security Limit. • Pre-contingency loadings not to exceed these.

  40. TransmissionHow are limits developed? Stability Limits • Developed by off line simulation studies, simulating the system dynamics • Use NPCC criteria to “throw” faults at the system • Calculate the post contingency effects on stability • Is the system stable pre contingency, during the contingency and post contingency? If OK move on to next simulation. If not OK then redispatch system to reduce pre contingency loadings in the simulation until post contingency stability achieved. • This loading limit becomes the Operating Security Limit. • Pre-contingency loadings must not exceed these.

  41. TransmissionHow are Limits Developed? • Some notes re simulation studies performed: • time consuming • only study a limited number of contingencies and system conditions (eg winter peak, summer minimum, summer peak) • study conditions set up for most severe contingency usually at peak power transfers • successful study results reduced (nominally10%) to provide acceptable margins • results simplified for easier computer monitoring

  42. TransmissionOperating Security Limits System needs to be secure • Pre-contingency • Post-contingency • Stable During Contingency (Transient Stability-non faulted generators not removed from system, acceptable equipment operation during/immediately after fault clearing, non cascading outages)

  43. Transmission • Basic Transmission Components • Overview of Transmission System • Limits - where do they come from & why do we need them • Internal Key Interfaces and effects on Generation • Normal, High Risk and Emergency Operation • Ontario Interconnections • Transmission Impactive Outages

  44. TransmissionInternal Ontario Key Interfaces • Because of the dynamic nature of the power system and its multiple parallel paths, limits generally are not expressed in terms of individual line loadings (other than some thermal limits) • Rather, limits are expressed in terms of interface flows and are called Operating Security Limits. • An interface is defined as a group of Transmission lines and the limit is expressed as the sum of the flows on this group of lines.

  45. TransmissionInterface Limit Characteristics • ‘Base’ limit • All transmission facilities are in-service • Directional • Certain outages result in a penalty in MW • Some limits simple constants; • others more complex, and have multiple parameters including other limits!

  46. TransmissionHistorical Flows

  47. TransmissionHistorical Flows

  48. Transmission • Basic Transmission Components • Overview of Transmission System • Limits - where do they come from & why do we need them • Internal Key Interfaces and effects on Generation • Normal, High Risk and Emergency Operation • Ontario Interconnections • Transmission Impactive Outages

  49. Transmission The End

  50. Module 3BProtection, Control and Metering

More Related