Case Study: Renewable Energy Projects at the Pueblo of Jemez

Case Study: Renewable Energy Projects at the Pueblo of Jemez. Raymond R. Krueger Michael Best & Friedrich LLP • 100 East Wisconsin Avenue, Suite 3300 • Milwaukee, WI 53202 Phone: 414.225.2786 • Fax: 414.277.0656 • Email: rrkrueger@michaelbest.com. The Pueblo of Jemez.

denise
Download Presentation

Case Study: Renewable Energy Projects at the Pueblo of Jemez

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Case Study:Renewable Energy Projects at the Pueblo of Jemez Raymond R. Krueger Michael Best & Friedrich LLP • 100 East Wisconsin Avenue, Suite 3300 • Milwaukee, WI 53202 Phone: 414.225.2786 • Fax: 414.277.0656 • Email: rrkrueger@michaelbest.com

  2. The Pueblo of Jemez • Federally-recognized Tribe • 45 Miles NW of Albuquerque, NM • 2,500 Tribal members in village of Walatowa; 3,000 Tribal members total • Only Towa-speaking Tribe, very traditional • Has occupied the Jemez Valley for over 800 years

  3. Summary of the Jemez 3.5 MW ac Solar Project • Generate 3.5 MW ac of solar power using proven single axis flat plate PV on 30 acres of tribal trust land • Interconnect with Jemez Mountains Electrical Cooperative system at existing 69kV transmission line at site • Sell the power and Renewable Energy Credits generated by the project to a local utility • Revenue from power/REC sales go to Pueblo for much needed infrastructure improvements and community services

  4. Summary of the Jemez 3.5 MW ac Solar Project (cont’d) • Remains efficient on cloudy days • Lighter weight means better choice for mixed soil conditions • 30-year service life • Single-Axis, Flat Plate Solar Arrays • 30-year track record, highly reliable, easily maintained

  5. Summary of the Jemez 3.5 MW ac Solar Project (cont’d) ConceptualSite Plan – 30 Acres

  6. Summary of the Jemez 3.5 MW ac Solar Project (cont’d) Looking northeast from atop the mesita across main portion of solar site.

  7. Project Benefits • Environmental Benefits: • A coal-fired power plant emits 2,249 lbs. of CO2 gas per MW hour • Over the service life of the equipment, the Jemez Solar Project will offset over 278,876 tons of CO2 • First commercial scale, grid-tied solar project on tribal land nationwide • Project could be replicated by other tribes

  8. Project Benefits (cont’d) • Fiscal/Social Benefits: • Provide sustainable, profitable revenue stream to Pueblo • Could improve major infrastructure problems at the Pueblo • Creates track record for Pueblo as a competent renewable energy project developer leading to additional solar, wind, geothermal, and biomass projects • Sets positive example for Jemez students pursuing college and careers in hopes of contributing to the Pueblo and their people Source: U.S. EPA: The Emissions & Generation Resource Integrated Database (eGRID), 2008. http://www.epa.gov/solar/energy-resources/egrid/faq.html

  9. How is Project Being Funded? • The Pueblo does not have $20 million it will take to build the project and taking out a loan that big does not work economically • Tax credits work the same as bringing money to the table. They are the same as cash to the bank (equity) • Our Finance Model, developed by Red Mountain Energy Partners, uses three federal tax credits, the Investment Tax Credit, the New Market Tax Credit, and State Production Tax Credits • Combined, these three tax credits cover approximately half of the project cost • The remaining half will be funded by a loan

  10. What’s Next? • Complete negotiations on Power Purchase Agreement • Form a Project LLC with finance partners • Complete a geotechnical study and grading and drainage plan • Procure construction services • Break ground Fall, 2010 • Continue development of our geothermal and biomass projects

  11. Questions? Raymond R. Krueger Michael Best & Friedrich LLP 100 East Wisconsin Avenue Suite 3300 Milwaukee, WI 53202 414.225.2786 rrkrueger@michaelbest.com