ZDC Status, 9th December ‘07

ZDC Status, 9th December ‘07. Fitting in the TAN slot Getting in and out of the TAN Schedule Trigger. Yasar Onel (Michael Murray) for ZDC group. Several problems fitting in TAN.

zinnia
Download Presentation

ZDC Status, 9th December ‘07

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ZDC Status, 9th December ‘07 • Fitting in the TAN slot • Getting in and out of the TAN • Schedule • Trigger Yasar Onel (Michael Murray) for ZDC group

  2. Several problems fitting in TAN • bumps in the ZDC, biggest bumps flattened & threaded rods were inserted through the empty screw holes in the 2 hadronic modules • Poor assembly of TAN improved • The slope of the LHC, the bottom of the ZDCs has been bevelled • Limitations of crane; Paul and Ianos have come up with a much better design that should be much cheaper than option proposed by CERN. (See ZDC_crane.ppt for full details)

  3. Partial Vertical Extraction Twin Lead screws (not shown) located vertically between each end of the Lift frame and outer frame pull ZDC from slot..

  4. Full Extraction

  5. Partial Rotation Clever Bell assembly is rotated slightly upward and out toward transport side of tunnel. Motion is again by a pair of lead screws which span between each set of fixed and rotating leaves.

  6. “Clever Bell” mated to Shielding Pig Clever Bell assembly mates on alignment pins to pig. Alignment blocks on sideof TAN allow accurate pre-placement of pig.

  7. ZDC Fully lowered into Pig Human intervention then to disconnect ZDC fromcrane. Pig is removed, pig containing copper bars put in place, affixed to crane and procedure reversed. Copper bar module must be built to duplicate the manner in which ZDC attaches to lift frame.

  8. Schedule • Right hand ZDC will most likely be installed sometime in weeks 7,8 or 9, left sometime between Feb 24 and Apr 9 • Getting crane approved and built by then is a great challenge but everyone on ZDC team will work on this • KU, Iowa will cover these times but we could do with help

  9. Trigger • ZDC has very simple “on”, “off” contributions to trigger that will be used for beam tuning, diffraction and heavy ion. • Need to start programming frim-ware for this. One student coming to CERN for 3 months, perhaps he could learn how to do this.

  10. ZDC => LHCC • We have not yet presented ZDC project to LHCC. Skuja approved the the report but we are trying to improve its “look and feel” • Oleg and David d’Enterrira are working on this