Public Private Partnership Unit Finance Department Government of Sindh May, 2011

Partnership For Development. PPP PROJECTS IN SINDH. Public Private Partnership Unit Finance Department Government of Sindh May, 2011. PPP Unit. DG. RMU. Director. Director. Director. Director. Finance & Risk. Project. Market. Corporate Affairs. Management. Structuring.

xuefang-jun
Download Presentation

Public Private Partnership Unit Finance Department Government of Sindh May, 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Partnership For Development PPP PROJECTS IN SINDH Public Private Partnership Unit Finance Department Government of Sindh May, 2011

  2. PPP Unit DG RMU Director Director Director Director Finance & Risk Project Market Corporate Affairs Management Structuring Development Assistant Assistant Assistant Assistant Assistant Director - I Director - IV Director - V Director - II Director - III PPP Unit PPP Unit comprises of Public and Private Sector specialists having professional expertise and relevant certification

  3. Vision Vision and Objectives Objectives of PPP in Sindh • Provision of infrastructure services • Improve their reliability and quality for accelerating economic growth • Achieving the social objectives of the government • Mobilize private sector resources for infrastructure projects; • Incorporate principles of fairness, competition and transparency in public-private partnership projects; PPP Unit envisions that with out private sector participation, the public sector can not bring about efficiency in the Service Delivery System. Provision of private finance is also very important and the vision is to covert abundant public sector resources into commercial assets generating constant flow of funds

  4. What do we offer to private sector? • Administrative support • Licenses and clearances , Utility connections for power, gas and water, land or rights of way • Asset-based support • leasing land and infrastructure facilities • Direct financial assistance • Viability Gap Fund • Government guarantees • Political risks ,delay of agreed user fee adjustments,(MRG), • Credit Enhancement, Force majeure and Demand risk etc These contractual obligations form part of RFP Well thought out plan VGF Board has to decide about the project financing issue on the pattern of TIFU *UK, *TIFIA USA and *IIFCL India. The Risks of project are well defined and well quantified

  5. KEENJHAR LAKE

  6. Tourism Market Analysis Key Facts Outbound Tourism Expenditure by Pakistanis • World Travel & Tourism Council (WTTC) research is done in co-operation with Oxford Economics World • Travel & Tourism (T&T) contributes 9.2% to GDP (US$5,751 bn) in 2010 • Real GDP growth for the T&T Economy is expected to be 4.4% per annum over the coming 10 years Pakistan • T&T contributed 2.0% to GDP (US$ 9.1b) in 2009 • In 2007, Pakistanis have spent amounts exceeding US$ 2b on international travel and tourism Source: WTTC CAGR 13.5% Source: UNESCO Statistical Report 2009 Internationl Tourism Receipts as % of GDP

  7. Karachi Economy Key Facts • Household Income Distribution • Population is currently estimated around 16 – 18 million • Average annual income growth: 5.8% • Expected earnings top bracket of 14% is now expected to be PKR 47,000 per month FBR Yearbook 2006-07 40% of Financial activity 53% of total collection of FBR Karachi 40% of large scale manufacturing 50% Bank Deposits 25% Federal Revenue 95% foreign trade passes through Karachi Percentage Household Income Distribution • Commercial • Most of the port related activities through the two ports at Karachi and Bin Qasim • Home to most of the consumer products and pharmaceutical companies. • Financial Services hub of Pakistan Earnings Top Bracket

  8. The Lake • Largest freshwater lake in Pakistan (24 Km long, 8 Km wide, 192 Km Periphery) • Wetland of international importance (Ramsar Site) • Wildlife Sanctuary and home to several species of local and migrating birds • Major water reservoir • Perfect for short stay s away from the busy routine of city • Proximity to Thatta City , with its rich history and culture, enhances tourism potential • An ideal location for eco-friendly tourism and nature • Resort development can be a major economic stimulus

  9. Historical places near Keenjhar Lake • Tourist sites in and around Thatta having potential for development and organized tourism • History of Thatta goes back several millennia to the Indus Valley civilization. • Thatta Capital of Sindh and seat of power for 400 years for three Muslim dynasties • Architecture continues to inspire modern buildings • Close to 1000 year old lost city of Bhambhore • Chawkandi tombs date back over 1000 years • The tombs at Makli necropolis date back over 700 years • Shah Jahan Mosque, built back in 1647, one of the largest mosques with 100 domes Bhambore Chawkandi Tombs Makli Shah Jahan Mosque

  10. THE PROJECT

  11. N W E The Project Site • Located 10 Km from the National Highway • Direct connection with the Lake offering a 270 degree view with 8km shoreline • Limited access provides better Security • Maximized shoreline for waterfront development. • Offers great flexibility for articulation of various Integrated Resort Facilities • Large untouched land (with no existing man made structures/ facilities) • A raised site with flat terrain suitable for infrastructure and other development Project Site Project Site

  12. The Visualization of the Project

  13. FINANCIAL OVERVIEW

  14. ESTIMATED PROJECT COSTS DEVELOPMENT OUTLAYS • Land cost represents only 5% of the estimated project costs • 43% of the Resort Zone costs are estimated to be funded through sale of farmhouse components • 60% of the project finance is expected to be raised from Commercial Debt carrying interest @ 15% - 16% p.a. Resort Zone Recreation Zone

  15. INVESTMENT ANALYSIS KEY RESULTS Resort Zone Recreation Zone Quantitative Aspects • Resort Zone • Equity IRR: 23% • NPV @16%: PKR 1.3billion Qualitative Aspects • Flexibility in terms of developing the project • Reduced upfront investment • Land price is payable on deferred basis • Land is available for mortgage • Extensive work already undertaken • Feasibility shows bankable financial ratios Development Period Payback: Year 9 Operational Period Development Period Payback: Year 9 Operational Period

  16. TRANSACTION STRUCTURE

  17. STRUCTURE Balance Bid Amount to be paid on or prior to COD at 8% p.a. Interest. Payment of Balance Bid Amount is a condition precedent to the COD. GoS The Concessionaire shall have a 95 years Lease on the Project Land with a right to mortgage subject to the provisions of the Concession Agreement Debt Commercial Lenders Project Revenues shall be governed by the Escrow Agreement whereby the proceeds will be appropriated between the KPC account, Lenders account and Project Development account Under Escrow Agreement Project Revenues Total Project Cost inclusive of Land 20% Upfront Bid Amount to be paid on or prior to signing of concession agreement Equity IRR: 23% Payback: 8.4 years (Yr 4 of operations) Equity Private Party Cash

  18. CONTRACTUAL WEB OVERVIEW • Quoted Bid Amount (QBA) is the price at which financial bids are invited from potential developers • QBA shall be: • Base land price; plus • premium on land • Developer can either be an individual or a consortium • Developer to incorporate a Project SPV which shall sign the Concession Agreement with the Government • GoS to implement project through Keenjhar Project Company, a wholly owned project entity Transfer of Project Land under Master Lease arrangement from DoT to KPC GOS KPC Tourism Department (DoT) Allocate Project Land to the DoT Concession Agreement Escrow Agreement Master Developer Shareholders Agreement Project SPV Financing Agreement Commercial Lenders Sub-Lease/ Sub-Contract Agreement Sub-Lease/ Sub-Contract Agreement Sub-Lease/ Sub-Contract Agreement Private Party 1 Contractor/ Private Party 2 Contractor/ Private Party 3 Contractor

  19. Hyderabad - Badin Road Project • Public sector partner • Government of Sindh • Project advisors • MM Pakistan (Pvt.) Ltd. (Technical and Lead Advisor) • KPMG Taseer Hadi & Co. (Financial Advisor) • Mandviwalla & Zafar (Legal Advisor • Procurement approach • GoS intends to award a Concession Agreement for the design, build, finance, operation and transfer of a 98.5 km road connecting Hyderabad to Badin through the towns of Tando Mohammad Khan, Matli and Talhar. It is currently envisaged that the contract term will be for a period of approximately 33 years. The Project (including the ownership of the Project related assets) shall be handed over to GoS at the end of the contract period. • Private partner’s role • The Service Provider will: • Finance the Project • Detailed designing of the Project based on conceptual designs provided by the Contracting Authority • Construct the Project • Satisfy all required tests on completion of construction of the Project • Operate the Project during the PPP Contract and collect tolls • Maintain and repair the Project during the PPP Contract period • Hand over the Project to the Contracting Authority at the end of the PPP Contract period Economic significance of project location • 6 major junctions at Siri, Tando Mohammad Khan - Sajawal, Tando Mohammad Khan - Tando Allah Yar, Matli - Tando Ghulam Ali - Digri, Talhar and Badin Cantt • Over 100 smaller link roads indicate mass-usage and importance of the Road • Collects traffic from southern Sindh and connects to the N-5 National Highway towards the North • Connects Hyderabad with many important industrial and commercial areas in the surroundings • Tharparkar District, with vast Coal reserves, is situated on the Eastern side of the Project area • Type of industries: Rice Mills, Sugar Mills & Oil Mills

  20. Run-of-River Power Generation • EOI for hiring Transaction Advisor floated on 3rd July, 2010 • Scope of work • Identify the potential sites for ROR Power Generation in the province particularly at Sukkur Barrage; • Conduct Feasibility Study in respect of the top four promising sites identified in the survey; • Assist Government of Sindh in marketing the project to the relevant mix of investors, and administering the bidding process for the selected sites • RFP issued to the 7 pre-qualified consulting consortia • Transaction advisor likely to start work by June 2011

  21. Gorakh Hill Resort Project Gorakh Hills Background Gorakh Hill Development project (GHDP) • Gorakh Hill is located 450 km North of Karachi, 300 Kms from Hyderabad, 93 Km in Northwest of Dadu and 46 Km from Sehwan Sharif    • Gorakh Hills development was initiated in 1998, with a plan to develop Gorakh Hills as a resort on lines of hill stations in northern Pakistan. A master plan was developed by M/s Naqvi & Siddiqui Associates in collaboration with M/s Shankland & Cox for the hills covering an area of about 1,908 Acres which included residential, recreational and hospitality components. • PKR 198.269 million has been spent on various development works which include road from Wahi Pandi to Gorakh Hill summit, water pumping stations and supply line to the summit, electricity supply to the summit, construction of police check posts along the road to the summit, construction of bridges, culverts etc. shades and fencing at the summit and construction of contractors cottage and residential quarters for workers. • The road from Wahi pandi to Gorakh Hill top has been prone to damage mainly due to seasonal torrents which flow through the numerous storm water drains that pass through the road and land slides at Khanwal Luk. • The development of Gorakh Hills fall under the Gorakh Hills Development Authority formed through an Act of Parliament in September 2008 • It was decided by the Government of Sindh in 2010 to develop Gorakh Hills under Public Private Partnership and mandated Transaction Advisors Ernst & Young in consortium with Meinhardt (Pakistan) Private Limited and Mohsin Tayebaly & Co to evaluate options for development of Gorakh Hills under PPP. • The initial studies suggested a need for development of better access road and development of basic facilities for tourists visiting the hill top • Detailed design of road that follows the existing route for most part that is reengineered to provide better road access has been completed • A conceptual design for the tourist facility at the hill top has also been completed.