TMT Instrument Development Cartoon. David Silva Observatory Scientist 3 November 2006. Constraints & Assumptions. Constraints = Board mandates No new money until 2012 Total available new money = 200 M$ (2006) Not certain that all new money will be available for instruments

xander
Download Presentation

TMT Instrument Development Cartoon

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TMT Instrument Development Cartoon David SilvaObservatory Scientist 3 November 2006 TMT.OPS.PRE.06.011.DRF01

  2. Constraints & Assumptions • Constraints = Board mandates • No new money until 2012 • Total available new money = 200 M$ (2006) • Not certain that all new money will be available for instruments • No more than 20 M$ per year • Assumptions = mutable • First two instruments + NFIRAOS + LGSF from Construction • AM2 not included anywhere • Eight years from preliminary SAC discussion to AIV/Comm • No more than one new start per year • No more than one commissioning cycle per year • Unit cost: 25 M$ TMT.OPS.PRE.06.011.DRF01

  3. Cartoon Model – I AIV/Com years highlightedIDO = Instrument Development OfficeFirst two instruments from Construction TMT.OPS.PRE.06.011.DRF01

  4. Cartoon Model – II Integrated: 175 M$ TMT.OPS.PRE.06.011.DRF01

  5. Discussion • Support NFIRAOS + LGSF investment • Range of possibilities, range of cost (10 M$ – 50 M$ per thing) • Need Instrument Development Roadmap • SRD vision update • Framework for science case for construction proposal(s) • Framework to attract “instrument donors” and “instrument associates” • Must commit to First Suite this year • Needed for coherent Construction proposals • The roadmap cannot be cast in stone… • Not necessary (or desirable) to lock-in exact future sequence now • Need to be sensitive to developments in astrophysics and technology • Roadmap should be reviewed and revised annual by SAC TMT.OPS.PRE.06.011.DRF01