1 / 19

Opportunities and Challenges: Update on the WSACC Heat to Energy Project

Opportunities and Challenges: Update on the WSACC Heat to Energy Project. Thomas Hahn, PE (CH2M HILL) Coleman Keeter (WSACC) Angela Roberts, PE (CH2M HILL). Agenda. Background / Existing Facilities Need for Project Description of Project Features Imported Biosolids Handling Facility

wing-palmer
Download Presentation

Opportunities and Challenges: Update on the WSACC Heat to Energy Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Opportunities and Challenges: Update on the WSACC Heat to Energy Project Thomas Hahn, PE (CH2M HILL) Coleman Keeter (WSACC) Angela Roberts, PE (CH2M HILL)

  2. Agenda • Background/ Existing Facilities • Need for Project • Description of Project Features • Imported Biosolids Handling Facility • Heat Recovery and Power Generation System • Challenges and Opportunities • Path Forward • Questions

  3. Background / RRRWWTP Facilities • Serving Cabarrus County • 26.5 mgd capacity • High-Purity Oxygen Activated Sludge • Solids Handling System • Primary and Secondary Clarifiers • Gravity Thickeners • Dewatering Centrifuges • Multiple Hearth Furnace (MHF)

  4. Need for Project • Historically: • MHF operating well below permitted capacity • Autogenous burn 4 – 5 days / week • Maintaining temperature in MHF with fuel oil for remaining days • With imported solids • Reduced need for fuel oil • Optimized MHF operation • Revenue from imported solids • Solids handling alternative for other utilities • Heat Recovery / Power Generation • Green energy and revenue for WSACC

  5. Imported Biosolids Handling Facility – Design Capacities • Design Maximum Imported Biosolids Delivery/Conveyance Rate = 5.25 wet tons / hour • Storage Capacity of Imported Biosolids Handling Facilities = At least 1 day at design maximum imported biosolids delivery/conveyance rate

  6. Imported Biosolids Handling Facility – Process Flow Diagram

  7. Imported Biosolids Handling Facility - Truck Unloading • Two unloading “lanes” – one per solids receiving bin • Solids analysis • Weighing / recordkeeping

  8. Imported Biosolids Handling Facility - Solids Receiving Bins • 96 CY each (192 CY total). • Electrically actuated retractable covers • Leveling screws • Live Bottom Screws with Variable Frequency Drives • Load cells • Extraction screws and sludge mixer

  9. Imported Biosolids Handling Facility - Dewatered Sludge Pump • 45 gallons per minute (gpm) at 30% total solids • Screw feeder integral to dewatered sludge pump • Lubrication system (water injection) included to ensure reliable conveyance of imported cake • Piping and valving set up for multiple conveyance options.

  10. Heat Recovery and Power Generation System – Process Flow Diagram

  11. Heat Recovery and Power Generation System - Heat Recovery Unit • Replacement of the existing heat recovery unit at the Incinerator Building • Heat recovery unit completely contained within the existing building

  12. Heat Recovery and Power Generation System – HRSG Components Steam Drum Down-Flow Section Cross-Flow Section

  13. Heat Recovery and Power Generation System – HRSG Components (Up-Flow Section)

  14. Heat Recovery and Power Generation System - Steam Turbine Generator • Installed in new metal building • Process piping provided between the existing Incinerator Building and new Steam Turbine Generator Building • Overhead power lines to provide the power generated at the site back to the electrical grid.

  15. Challenges • Coordination, scheduling, and procurement for Owner-furnished equipment • Solids storage / conveyance equipment for Imported Biosolids Handling Facility • HRSG and STG for Heat Recovery and Power Generation System • Timing for bid of Heat Recovery and Power Generation System installation work • Contractor involvement with Owner-furnished equipment manufacturers • Imported dewatered sludge with wide variety of characteristics • Handling and controls • Incinerator shutdown for installation of Heat Recovery and Power Generation System equipment

  16. Opportunities • Cost-competitive all-weather biosolids disposal alternative • Optimization of biosolids feed quantity / quality to existing incinerator • Generation of green energy • Generation of revenue at WSACC

  17. Path Forward • Continuing successful Imported Biosolids Handling Facility operations • Operating January 2013 – present • Heat Recovery and Power Generation System • Construction work at site started in August 2013 • Concrete placement and backfill for STG Building now • Continuing mechanical equipment procurement • Incinerator shutdown, equipment installation, and startup • Anticipated completion of construction in May 2014

  18. Considerations for Interested Surrounding Utilities • Imported sludge with higher Total Volatile Solids (TVS) preferred for optimum operation of the MHF • Surrounding utilities may choose not to digest solids • Significant savings in O&M costs for those facilities

  19. Opportunities and Challenges: Update on the WSACC Heat to Energy Project Thomas Hahn, PEthomas.hahn@ch2m.com NC AWWA-WEA 93rd Annual Conference November 12, 2013

More Related