slide1 n.
Download
Skip this Video
Loading SlideShow in 5 Seconds..
Presented to the Coastal Protection and Restoration Authority July 11, 2008 PowerPoint Presentation
Download Presentation
Presented to the Coastal Protection and Restoration Authority July 11, 2008

Loading in 2 Seconds...

play fullscreen
1 / 15

Presented to the Coastal Protection and Restoration Authority July 11, 2008 - PowerPoint PPT Presentation


  • 74 Views
  • Uploaded on

DRAFT CORPS OF ENGINEERS CONTRACTS: Louisiana Coastal Area, Mississippi River Gulf Outlet, and Lake Pontchartrain & Vicinity. Presented to the Coastal Protection and Restoration Authority July 11, 2008. Louisiana Coastal Area. Feasibility study on 6 ecosystem restoration projects

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Presented to the Coastal Protection and Restoration Authority July 11, 2008' - victor-turner


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

DRAFT CORPS OF ENGINEERS CONTRACTS:Louisiana Coastal Area,Mississippi River Gulf Outlet, andLake Pontchartrain & Vicinity

Presented to the Coastal Protection and Restoration Authority

July 11, 2008

louisiana coastal area
Louisiana Coastal Area
  • Feasibility study on 6 ecosystem restoration projects
    • Multipurpose operation of Houma navigation lock
    • Terrebonne basin barrier shoreline restoration
    • Small diversion at Convent/Blind River
    • Amite River diversion canal modification
    • Medium diversion at White’s Ditch
    • Convey Atchafalaya river water to northern Terrebonne marshes
louisiana coastal area continued
Louisiana Coastal Area(continued)
  • Cost Share Agreement
    • CPRA to be Non-Federal Sponsor
    • NFS & Corps each lead on 3 projects
    • 50% NFS cost share
    • NFS work-in-kind projected to be 50%, so no payment anticipated by NFS
  • Purpose is to determine feasibility of the projects
mississippi river gulf outlet
Mississippi River Gulf Outlet
  • Construction
    • MRGO closure structure
    • Ecosystem restoration measures
  • Memorandum of Agreement
    • Full federal cost
    • Corps to construct
    • CPRA to be Non-Federal Sponsor
    • NFS to operate and maintain, and acquire necessary property rights
lake pontchartrain vicinity
Lake Pontchartrain & Vicinity
  • Construction
    • Accelerate completion of unconstructed portions of original project
    • Modify original project to improve performance and armor critical portions
    • Raise levee heights and enhance original project to provide level of protection to achieve NFIP certification
lake pontchartrain vicinity continued
Lake Pontchartrain & Vicinity(continued)
  • CPRA to be Non-Federal Sponsor
  • Partnering and Cost Share Agreement
    • Full federal expense for completion of original project
    • Full federal expense for improvement of original project
    • 35% NFS cost share for raising levee heights and enhancing original project
  • NFS to perform WIK, O&M, property acquisition
common issues
Common issues
  • Corps has complete control
    • For full federal and cost-shared work, Corps determines completion and turnover
      • Protection and/or performance
      • O&M cost
    • For cost-shared work, Corps determines Corps costs and NFS credit
      • Amount of NFS payment for Corps work
      • Amount of credit for NFS work
      • Corps determines expenditure of State funds
common issues continued
Common issues(continued)
  • Hazardous substance remediation
    • CERCLA liability can be huge and unknown
    • Corps position is that this is 100% NFS cost
    • Property owner liable under CERCLA
  • Use of federal program funds
    • Corps requires express authorization
    • Has been a problem in the past
    • Standard should be absence of prohibition
lca specific issues
LCA-specific issues
  • Total costs capped, but Corps could “crowd out” NFS costs
    • Corps can incur more than 50% share
    • Corps can “allocate” NFS costs to excess category
    • As a practical matter, NFS may have to agree to increase total costs
  • Availability of credits for pre-Agreement work
  • NFS ability to audit Corps expenditures
mrgo specific issues
MRGO-specific issues
  • Construction at full federal expense, but:
    • NFS to acquire necessary property rights (agreed; credit if possible)
    • NFS to perform environmental investigation and remediation
  • Clarification of “completion” versus “maintenance”
  • No dispute resolution mechanism
lpv specific issues
LPV-specific issues
  • NFS cannot agree or disagree to include or incur costs
  • NFS cannot cost-share all of the same types of costs as Corps
  • Credit limitations
    • May be impermissible
    • No reimbursement for WIK above NFS cost share
lpv specific issues continued
LPV-specific issues(continued)
  • No NFS or third-party review of disagreement
    • NFS comments during construction
    • NFS comments on completion
    • NFS request for warranty work
    • Credit for property, relocations, and improvements
    • Corps determination of funds due
lpv specific issues continued1
LPV-specific issues(continued)
  • NFS responsible for:
    • Acquisition of necessary property rights
    • Relocations - Roads, railroads, pipelines
    • Building improvements for disposal of dredged material from construction
    • Interior drainage & pumping plants – No credit
    • Commandeering – No credit for defense
    • CERCLA remediation – No credit
lpv specific issues continued2
LPV-specific issues(continued)
  • Confusing cost-share payment scheme
    • Appears to require up-front payment despite credit for WIK, etc., with reimbursement later
  • Problematic property rights process
    • Preference for commandeering
    • Provision of other gov’t agency property
    • Unrealistic time frames for acquisition
conclusion
Conclusion
  • All three Agreements are more favorable to NFS than past PCAs
    • Corps has agreed to some improvements
  • Some additional improvements are still necessary
  • Negotiations are ongoing