bktz129083 construct cyber foc type a 2 presentation n.
Download
Skip this Video
Loading SlideShow in 5 Seconds..
BKTZ129083 CONSTRUCT CYBER FOC Type A-2 Presentation PowerPoint Presentation
Download Presentation
BKTZ129083 CONSTRUCT CYBER FOC Type A-2 Presentation

Loading in 2 Seconds...

play fullscreen
1 / 29

BKTZ129083 CONSTRUCT CYBER FOC Type A-2 Presentation - PowerPoint PPT Presentation


  • 108 Views
  • Uploaded on

BKTZ129083 CONSTRUCT CYBER FOC Type A-2 Presentation. LTC Craig Bradford Base Civil Engineer (BCE) March 19 th , 2014. Project Title. Introductions Meeting Handouts Current DD1391 Attendance Sheet. Overview. Project Scope Construction Costs AT/FP Site Plan Floor Plans

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'BKTZ129083 CONSTRUCT CYBER FOC Type A-2 Presentation' - tess


Download Now An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
bktz129083 construct cyber foc type a 2 presentation

BKTZ129083CONSTRUCT CYBER FOCType A-2 Presentation

LTC Craig Bradford

Base Civil Engineer (BCE)

March 19th, 2014

project title
Project Title
  • Introductions
  • Meeting Handouts
    • Current DD1391
    • Attendance Sheet
overview
Overview
  • Project Scope
  • Construction Costs
  • AT/FP
  • Site Plan
  • Floor Plans
  • Building Elevations/ Sections
  • Building Systems
  • Fire Flow Tests
  • Soils Report
  • Environmental Issues
  • Sustainability/LEED
  • EPAct/EISA
  • Renewable Energy
  • Unresolved Issues
  • Design Schedule
authority scope
Authority / Scope

FY15 MILCON

Sensitive Compartmental Information Facility (SCIF) - 6,900 SF

GRAND TOTAL

  • MCC = $1,522,500
authority scope1
Authority / Scope
  • LOWER LEVEL FLOOR PLAN
    • SCIF 3,441 SF
authority scope2
Authority / Scope
  • UPPER LEVEL FLOOR PLAN
    • SCIF 3,441 SF
estimate of probable cost
Estimate of Probable Cost
  • MCC
    • Base Amount $1,370,250
    • Options $152,250
    • TOTAL $ 1,522,500
  • Cost Estimate
    • Base Amount $1,440,000
    • Options $ 0
    • TOTAL $1,440,000
at fp narrative
AT/FP Narrative
  • Occupancy Type: Primary Gathering
    • Population – 206 (FOC + IOC)
    • Density – 1 person / 96 SF (FOC + IOC)
  • Wall Construction – Reinforced Masonry, Exterior Load Bearing Walls
  • Setbacks
site grading drainage
Site Grading & Drainage

Site Grading and Drainage is inconsequential

floor plan
Floor Plan

Lower Level Previously Reviewed

floor plan1
Floor Plan

Upper Level Previously Reviewed

building systems
Building Systems
  • Structural
    • Shallow Foundations
    • Slab on Grade
    • Exterior and Interior Reinforced Masonry Walls
    • Steel Joists supporting 2nd Floor
  • Roofing
    • Standing Seam Metal Roof
    • Steel Trusses
    • Capable of supporting future PV panel loads
building systems1
Building Systems
  • Mechanical
    • High efficiency heat pumps
    • Remote condensers
  • Electrical
    • 208Y/120V, 3-Phase, 4-wire extended form existing IOC building
    • 4 ftT8, 32W Fluorescent with energy saving lamps and ballast
fire protection
Fire Protection
  • Design Requirements
    • Sprinkler demand: 645 GPM @ 72 psi
    • Hose stream demand: 250 GPM
    • Total demand: 895 GPM
  • Hydrant Flow Test Results
    • Static pressure: 92 psi
    • Residual pressure: 63 psi
    • System flow rate: 1,325 GPM
  • Existing available flow and pressure can meet the design requirement
soils report
Soils Report
  • 5 Boreholes
      • Shallow auger refusal (5.6 ft – 16.4 ft)
  • N-Values (4-15 blows per ft) – soft to stiff
    • Soft soils require undercutting
    • Fill soils classified as stiff
  • Bearing Capacity – 2,500 psf
environmental issues
Environmental Issues
  • Not an IRP site
  • No asbestos present
  • No lead based paint present.
  • No Threatened or Endangered species affected.
renewable energy
Renewable Energy
  • Photovoltaic Roof Panels – Not selected. Payback period analysis indicates PV panels are not cost effective. Framing designed to accommodate future panels.
  • Solar Hot Water – No water services scheduled
  • Geothermal – Not selected. This is not the most cost effective system based on the Economic Comparison Report
unresolved issues
Unresolved Issues
  • Address all unresolved issues such as
    • Identification of Additive Bid Items
    • Check for adequacy of generator set and control house as provided in the IOC project by the government
construction phasing
Construction Phasing

There are no phasing requirements

design schedule
Design Schedule
  • Criteria Review Conference 10 Jan 14
  • Concept Proposal (A1) 25 Feb 14
  • Concept Development (A2) 14 Mar 14
  • Contract Documents (B1) 9 May 14
  • Pre-Final Submittal (B2) 27 Jun 14
  • Final Submittal (B3) 8 Aug 14
  • Bid Opening 1 Oct 15
  • Program Year: FY15