Demolition of Structures containing Asbestos. Rak-43.3313 Repair Methods of Structures, exercise (4 cr ) Esko Sistonen. Safety risk factors at repair of construction. dust asbestos creosote PCB lead noise shake chemicals low Light biological Factors risk of falling

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Demolition of Structures containing Asbestos' - taya


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
demolition of structures containing asbestos

Demolition of Structures containing Asbestos

Rak-43.3313 Repair Methods of Structures, exercise (4 cr)

Esko Sistonen

slide2

Safety risk factors at repair of construction

dust

asbestos

creosote

PCB

lead

noise

shake

chemicals

low Light

biological Factors

risk of falling

tip-over Hazard

hoisting

demolition work

tamping work

risk of fire

danger of explosion

asbestos
Asbestos
  • The most common old harmful substance found in the building materials (in 1920 to 1990)
  • Improve the strength of the material, wear resistance, thermal insulation, fire resistance and acoustic properties
  • Banned the use of asbestos in Finland 1994
  • Asbestos fibers are harmful if migrated into the airways and lungs
  • Is not removed from organs
  • Asbestos-related diseases: lung cancer and asbestosis
demolition work
Demolition work
  • preliminary examinations
  • asbestos
  • hazardous waste
  • frame
  • demolition work plan
  • demolition order
  • supports and bindings
  • loading of structures
  • Protection against falling
  • waste treatment
  • dust and noise pollution prevention
  • check out the repaired building, you should not rely solely on research studies and plans
slide5

Asbestos Statement:

-asbestos and asbestos-containing materials inventory

documents

examinations

-inventory of asbestos-containing materials, their quantity and toxicity findings

Space inventory

-Floor coverings, plasters

coatings mapping

Asbestos Survey-

report

-Further research

mapping systems

-Heating-ventilation-system

Structural shell mapping

-Facade materials and coatings, asbestos cement roofing

Structural mapping

slide6

Demolition process selection

-dry method

compartments and vacuum

demolition-bag method

structures, a complete demolition

A wet method

-water jetting method

-encapsulation and coating

-asbestos waste stays to its location, but it is marked as

-broken lines are filled

surface fixed

Fig. TaATTL

harmful substances encapsulation or leave them to structures
Harmful substances encapsulation, or leave them to structures
  • In some cases, harmful substances can not be removed from structures, or it is not technically and economically rational
  • Harmful substances may then be left into structures, but it requires special technical measures for the structure, the design of which differs from the usual structural design and requires special expertise
  • Encapsulation materials used are various types of water insulation products, polyamide film and, to some extent, the conventional building products, such as water shut-off mortars
slide8

Hazardous waste survey (creosote, PCBs, lead, etc.):

-It is natural to do the same kind of inventory as in the case of the survey of asbestos

-careless handling of hazardous waste and the demolition work is harmful to the environment

-building materials are rarely in themselves hazardous waste (except asbestos, creosote, PCBs, lead containing especially when the products break)

-hazardous waste are generally derived from the use of the building:

fluorescent tubes, adhesives, intensity discharge lamps, solvents, thermometers, CFC (refrigerators), heavy-metal batteries, polyurethane insulation, batteries, paint waste, washings, oils

slide9

Creosote or coal tar

-A common water-insulating 1800 – early 1900

PAH (Polycyclic aromatic hydrocarbon)

-usually found in basements (walls and floor tiles), creosote is not visible

-black or dark brown goo

-a bad odour, pungent (smell of crosstie or water transport channel)

PCB and lead

-facades sealants

Keep in mind that the soil is potentially contaminated with hazardous waste!

slide10

Demolition work plan documents

-demolition plan

-demolition drawings

-specification of demolition work

-demolition work, safety notes

Asbestos in the old pipe installations.

-Only authorized companies are allowed to do asbestos removal work

typical asbestos enclosure for the removal of asbestos sprayed coating from beams
Typical asbestos enclosure for the removal of asbestos sprayed coating from beams.

http://en.wikipedia.org/wiki/File:UK_Asbestos_Removal_Enclosure.jpg

http://www.ttl.fi/fi/toimialat/rakennus/turvapakki/vaaralliset_aineet/eristeaineet/asbestituotteet/Documents/asbesti_rakennustyossa.pdf

http://www.tyoturva.fi/files/2134/Toimiva_asbestipurku.pdf

http://www.dammega.fi/documents/R1114ASBosasto.pdf