PIP Update. Sept 12 2012. Agenda. Summary Update Current Activities Updates/Talks: Trevor Butler - Linac Modulator Dan Bollinger - New Source for the RFQ Salah Chaurize - RFQ Platform Installation. Update. General Info Current Work

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'PIP Update' - tara-pickett


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
pip update

PIP Update

Sept 12 2012

agenda
Agenda
  • Summary Update
    • Current Activities
  • Updates/Talks:
    • Trevor Butler - Linac Modulator
    • Dan Bollinger - New Source for the RFQ
    • SalahChaurize - RFQ Platform Installation
update
Update

General Info

  • Current Work
    • Booster RF cavity [Tuners on – testing underway] Results?
    • Linac Transformer – No Install/Moving to Indoors/MCC Work
    • Booster Transformer – Have PO but not likely to happen now
    • LCW – Work finishing up – fill the system soon
    • RFQ – Sources are off and removal underway!! No going back!
    • High Power RF – A req has made it way into the system for 2M!
    • High Power Ferrite Testing - National has order for some M4 ferrites
    • Booster Absorber – Working on marble face and motion control
    • Linac Modulator – Planning for FY13 effort (In house mostly/SLAC)
    • Booster Solid State – No more installs this FY but work continues
    • Booster Modulator work (six done and 4 more almost ready) Production?
    • Tuner with new ferrite (plan is have it fully assembled today)

Shutdown - comments (Fernanda, Todd, Mary)

END OF Fiscal Year - I have stopped signing PO’s due to purchase of Klystron

I have received a lot more requests since yesterday – I am holding them for now. Meeting with Ann to go over numbers – to see where we stand. There is very little left in Division or Lab and are being very tight with spending. No guarantee that reqs in process will be approved!

talks
Talks

Trevor Butler - Linac Modulator

Dan Bollinger - New Source for the RFQ

SalahChaurize - RFQ Platform Installation