Constructing and Analyzing the Project Network Diagram Chapter 6

Constructing and Analyzing the Project Network Diagram Chapter 6. CSSE 372 22.Sep.2008. Outline. Definitions Starts Critical path Slack MR Activity. What is a network diagram?. “A pictorial representation of the sequence in which the project work can be done.”

suchin
Download Presentation

Constructing and Analyzing the Project Network Diagram Chapter 6

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Constructing and Analyzing the Project Network DiagramChapter 6 CSSE 372 22.Sep.2008

  2. Outline • Definitions • Starts • Critical path • Slack • MR • Activity

  3. What is a network diagram? • “A pictorial representation of the sequence in which the project work can be done.” • What is needed to construct diagram? • Tasks • Task Duration • Earliest time to start task • Earliest expected completion date for the project

  4. Uses • Planning • Implementation & Control

  5. Types Task-On-the-Arrow (TOA) Precedence Diagramming Method (PDM)

  6. Using PDM

  7. Using PDM (cont.)

  8. Starts…

  9. CotD

  10. Constraints • Technical • Discretionary • Best-practices • Logical • Unique • Management • Interproject • Date

  11. Putting it together… Forward pass Backward pass

  12. Using PDM ID: Number from WBS E: Duration Work forward: ES: Earliest Start Predecessor? ES = Efpre + 1 No pred? ES = 1 EF: Earliest Finish ((ES + E) – One Time Unit) Work backward: LF: Latest finish Last task? LF = EFCalculated Not last? Min(LSea. succ.) - 1 LS: Latest start ((LF – E) + One Time Unit)

  13. Critical path – what is it? • “The longest duration path in the network diagram” • “The sequence of tasks whose early schedule and late schedule are the same” • “The sequence of tasks with zero slack or float” The Critical Path Determines the Completion Date of the Project

  14. How do you calculate it? • Add up all of the path’s durations • The longest one is the critical path • Compute slack

  15. Slack = LF - EF 0 0 0 0 1 4

  16. How do you calculate Critical Path? • Compute slack • Two types of slack • Free slack – amount of delay for a task without causing a delay in the early start of immediate successor task(s) • Total slack – amount of delay for a task without delaying the project completion date

  17. Schedule compression

  18. Management reserve • Padding task duration • Individual task level • Project level • Bad at the task level • BUT, good at the project level • Accounts for risk • Incentive (management reserve time not used can be the basis for bonus)

  19. Coming up! Plus/delta feedback– Please turn in at end of the hour • Add your estimate of how much time you’re spending per week, on the bottom of the form Microsoft Project – Bring your laptops with this installed on Thursday, we’ll use it in class • In Thursday’s Angel files – an example project, WBS word document, and mpp project file to test with Exam 1 – What’s going to be on the 372 exam? • Effective Project Management (Fourth Edition) • Chapters 1 – 7 • Exam Date will be…

  20. Activity Look at the WBS and estimates for your team’s project Start with an activity that looks like it starts on day 1 See how far you can build the PDM from there, putting in reasonable dependencies Try to make them all FS dependencies, to begin with Record the ES, EF, LS, LF, and slack for each task Reexamine the tasks to see what’s really appropriate as an FS, FF, SS, or SF dependency relationship Find and indicate the critical chain If there’s time left, re-evaluate your dependency relationships to see if you can compress the schedule Time: 20 minutes

  21. Questions?