This document provides a detailed overview of the HYSPEC project as of June 16, 2010, focusing on shielding specifications and the installation of key components. Key highlights include progress on external building shielding (15-33m), the chopper box installation, and updates on the detector vessel design, which is currently in procurement. Additional details encompass the delivery of shield blocks, installation of the secondary shutter, and the status of the monochromator, including lead pour updates. A removable hatch and O-ring provisions are also discussed for collimator access.
E N D
HYSPEC status June 16, 2010
HYSPEC Overview 6~15m Shielding External building 15~33m Shielding Chopper Box B Shielding Drum Shield Sample position Detector Vessel
Removable hatch for course collimator access 1/8” O-Ring Front section removable ¼” O-Ring (Hidden)