140 likes | 231 Views
Join us at the stakeholder meetings to review economic planning studies for the SIRPP process. Explore transmission system impacts, study timelines, and upcoming activities. Learn more about the study results and projected timelines.
E N D
2012 – 2013 SIRPP Welcome 1st Inter-Regional Stakeholder Meeting 9:00 AM – 10:00 AM CDT
Purpose and Goals 2011 – 2012 SIRPP Process Economic Planning Studies Review Stakeholder Feedback on Process 2012 – 2013 SIRPP Process Projected Timeline Economic Planning Studies Next Meeting Activities
2011 – 2012 Final Economic Planning Study Results
The Five Economic Planning Studies • SCE&G to Progress Energy Carolinas (200 MW) • Study Year: 2017 • Southern Company to Duke Energy Carolinas (50 MW) • Study Year: 2017 • SCRTP to FRCC (200 MW) • Study Year: 2017 • LG&E/KU to Southern Company (200 MW) • Study Year: 2013 • Southern Company to LG&E/KU (200 MW) • Study Year: 2013
SCE&G to PEC Transmission System Impacts for the SIRPP • Three (3) 230 kV Lines • One (1) 230/115 kV XFMR • Five (5) 115 kV Lines Total Cost: $26,415,000
SOCO to Duke Transmission System Impacts for the SIRPP • One (1) 230/115 kV XFMR • Four (4) 115 kV Lines Total Cost: $17,715,000
SCRTP to FRCC Transmission System Impacts for the SIRPP • One (1) 500 kV Static-Var Compensator • Two (2) 230 kV Lines • One (1) 230/115 kV XFMR • Three (3) 115 kV Lines Total Cost: $122,815,000
LG&E/KU to SOCO Transmission System Impacts for the SIRPP • None Reported Total Cost: $0
SOCO to LG&E/KU Transmission System Impacts for the SIRPP • None Reported Total Cost: $0
2012 – 2013 SIRPP Process Timeline
2012 – 2013 SIRPP 1st Inter-Regional Stakeholder Meeting SIRPPSG selects up to five Economic Planning Studies October 22, 2012 Economic Planning Study Scoping Meeting Verify study assumptions and address stakeholder feedback on scope document November / December 2012, if necessary 2nd Inter-Regional Stakeholder Meeting Discuss preliminary study results April / May 2013 3rd Inter-Regional Stakeholder Meeting Discuss final study results July / August 2013
2012 – 2013 Economic Planning Studies 12
Next Meetings Activities Economic Planning Study Scoping Meeting November / December 2012, if necessary Web / Phone Conference 2nd Inter-Regional Stakeholder Meeting April / May 2013 In Person w/ Web/Phone Conference Available