An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TerraCORE Hospitality DivisionPREFAB BATHROOM AND FLOORS

  2. PREFAB SYSTEM USED404 Rooms—Ponte 16 Macau Why Prefabrication Features Material Production Installation Cost Formulation

  3. Why Prefabrication? • Reduce site works • More efficient in factories • Improve workmanship • Production lines & factory QC • Speed up installation • Production ahead site progress • No wet work on site • Eliminated; changed to dry work • Site management • Wastage/debris in factories

  4. Prefab Bathroom System Features • Light-weight panels • Ease of handle for semi-skilled • Watertightness • Suitable for shower/bath areas • Adaptation to design • Any design or materials • Match with site tolerances • Within reasonable tolerances, work with site dimensions • Proven high speed production • 400 bathrooms per month

  5. Material Aluminum Honeycomb Aluminum Sheet Aluminum Sheet Natural marble

  6. Production Marble / Tile • Marble Cutting • Pre-lay • Polish • Watertight Joints • Openings for Sanitary Fitments Panels Piping Sanitary Fitting & Wares Ship to Site Installation

  7. Production Process

  8. Samples • Max panel size • 1.5M X 3M • Most common size • 1.2M X 2.4M • Floor / Wall Panel • Patterns or inlays • Close / 1mm joint • Shower Panel • Openings formed

  9. Prefab Stone /Natural Marble/Thin Tiles

  10. FINAL PROCESSING

  11. PROTECTION & QUALITY

  12. SMART PACKING Room labeling & packing Marble panels for 1 bath One Box = One Bath

  13. Installation – Sequence

  14. Installation – 4-days cycle

  15. Site installation Bath Tub & Frame Waterproof & Level Screed Wall Panels Floor Panels

  16. PONTE 16 MACAUno of site workersfinish 404 baths in 2 months • Conventional Wet Trade Method (Estimated) • 300 skilled workers • 120 cleaner • Prefab Bathroom (Actual) • 40 semi-skilled • 8 stoneworkers (minor repair) • 10 cleaner

  17. Cost Formulation MATERIAL COSTS OTHER COSTS • Cost of Stone Slab • Split into Halves • Honeycomb panel • Lamination + Glue • Polishing • Watertight Joints • Final Processing • Skirting & Trimming • Design & Mock-ups • Shop drawings • Control mock-up • Site mock-up • Packing & Transport • Taxes & Duties • Overhead & Profit

  18. Summary of Advantages • Competitive price for expensive stone • Reduce site labour • Semi-skilled workers • Light-weight & Thin • Fast production • Fast installation • Quality workmanship • Clean site • Best for high quality finishes • Reduced lead-time • Shop dwg & mock-ups • Economical with few repetitions • Less than 100 nos. • Retrofit changes possible

  19. Large Prefab Stone Size Prefab-Stone > 3 M

  20. Modular Toilet Cubiclein Stone Finish

  21. PHOTOS – PONTE 16 RESORT, MACAU

  22. PHOTOS – PONTE 16 RESORT, MACAU

  23. PHOTOS – PONTE 16 RESORT, MACAU

  24. PHOTOS - SANDS,SINGAPORE

  25. PHOTOS - SANDS,SINGAPORE

  26. PHOTOS - SANDS,SINGAPORE

  27. PHOTOS RECORD- SANDS,SINGAPORE

  28. 2030 Irving Blvd Dallas, TX75207 P 214.749.0999 F 214.742.2804 www.TerraCOREPanels.com

More Related