An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Omaha Public Power District “Substation Automation Project” Gregory W. Anderson, PE OPPD Substation Engineering Omaha, Nebraska phone: (402) 636-2561 gwanderson@oppd.com

  2. Publicly-owned ... 110+ subs (69, 161, 345 kV) • OPPD Builds “Smart Substations” -- Presently ... Modbus, IEDs to SEL-2020 to RTU • DistribuTech, February 2000 • Developed Internal 5-member Team (good mix) 1. Substation Engineering 2. System Protection 3. Operations/Dispatch 4. EMS/SCADA 5. Internal Liaison to DA • “Integration” vs. “Automation” • External Consultant -- KEMA Consulting • EPRI TC Project … UCA

  3. OPPD SA PROJECT 4-Step Process 1. “SA Plan” -- Internal 8-hr Seminar, 60 Individuals Attended -- Internal Department Interviews, 3 Days -- Develop Plan Document (completed Sept) 2. RFI (out to vendors in mid-Oct) 3. Specification / RFP ... Procure Equipment (Dec) 4. FAT / Install / SAT / Training (Spring 2001) … “teach us to fish” (technology transfer)

  4. Two Pilot Substations (two new stations) -- Sub 912 (69kV) -- energize Summer 2001 -- Sub 1345 (161kV) -- energize Spring 2002 • SA Lab (in crew’s offices, w/training focus) • Why Just Two Stations? • EMS Replacement -- spec in 2001 • Presently … -- Reviewing RFI Document -- IED Data List -- surveying internally -- Procuring IEDs (control/relay, monitoring, etc)

  5. Comparison -- HV Equip

  6. Comparison -- 13.8 kV Equip

  7. Comparison -- 13.8 kV Equip (con’t)