An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MicroSCADA ProSubstation AutomationRetrofit of Substation SILS Marcel Lenzin GEC Substation Automation Switzerland

  2. Agenda • The project • Key challenges • Chosen solution • Highlights / Room for Improvement • Lessons learned

  3. The Project - Location Baden

  4. The Project – Key Figures Station Extension of AIS Sils 380kV, Double Busbar Customer: Swiss Utility KHR, Kraftwerke Hinterrhein AG (www.khr.ch) Primary Equipment: Partially existing, Partially new CB‘s: new ABB, existing Sprecher&Schuh Isolators: Alpha (new and some existing), Sprecher&Schuh existing

  5. The Project – Scope of Supply • SAS630 • IEC61850 with GOOSE Interlocking • ICCP Gateway to NCC • 2 Ethernet Rings • Protection ABB REx670 & REB500 • Control with local Mimic/REC670 • Integration of existing equipment • Protection Siemens for Main 1 • Meters and Counters • Panels • Installation & Commissioning

  6. Key Challenges • Technology • First IEC61850 Project for this customer • Integration of Siemens Protection Relays • ICCP Communication to Network Control Centre • Retrofit • Existing Station in full operation • Preset shutdown window  tight time schedule • Commissioning to be done field by field during several months • GOOSE: How to ensure interlocking during commissioning phase

  7. Chosen solution – System Overview (1)

  8. Chosen solution – System Overview (2)

  9. Chosen solution – System Overview

  10. Chosen solution –Overview IEC Network

  11. Chosen solution – Station Overview

  12. Chosen solution – Bay Picture

  13. Chosen solution – Busbar Picture from REB500

  14. Chosen solution – Alarm Matrix

  15. Chosen solution – ICCP Gateway MicroSCADA Gateway OPC Server Data Exchange Substation at remote end Data Exchange Substation

  16. Chosen solution – Commissioning • SA System is tested completely at factory • All panels installed but not wired to process • Field by Field commissioning over 10 month • Station topology has to be simulated in panels for GOOSE interlocking

  17. Highlight • Close cooperation with customer (Work shops) • Commissioning on time (Energizing May 9th) • Good solution for ICCP Gateway • Matrikon OPC Data Manager • SISCO AX-S4 ICCP • Customer is happy with delivered Solution

  18. Room for Improvement • MicroSCADA Translation • RC WinTrans X8 works fine • Not all dialogs layout are in DLLs • Menus have to be translated separately (customizing) • MicroSCADA status texts with text translation tool

  19. Lessons Learned • Specification Phase in Project and Tendering is essential • Retrofit has it own rules to be considered • Requires flexible solution portfolio

  20. Question?