This report provides an overview of the implementation and testing of PLC control and communication routines for the high voltage system. Key highlights include successful integration of the PVSS interface, testing of safety features, and ongoing installations at P2. The document outlines the technical note on device implementation, safety checks, and the state diagram within the PVSS user interface. Current steps involve completing cabling, testing the system, and integrating the FSM with DCS prior to releasing the technical note.
E N D
TPC Very High Voltage Control Status report 20/04/2006 Marco Boccioli
Summary • PLC control and communication routines implemented and tested • PVSS interface implemented • Safety features tested • System being installed at P2 • Draft technical note: \\pcaitdc21\share\TPC
Safety • Electrical safety checked • PLC safety routines tested
Installing the system Supervisory • PVSS with FSM • Schneider OPC server
Installing the system PLC • Schneider Electric Premium P57 5634M
Installing the system Power Supply • Heinzinger PNC 150000
Installing the system ELMB • One for each side
Installing the system Cabling • Seven points for each side
What next… • End the cabling • Test the installed system • Integrate the FSM with DCS • Release the technical note (\\pcaitdc21\share\TPC)