An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Scheduling Professor Stephen Lawrence Graduate School of Business Administration University of Colorado Boulder, CO 80309-0419

  2. Project Management When to use: • Management complex projects • Many parallel tasks • Deadlines and milestones must be met • Difficult to know “what to do first” • Difficult to know when project is in trouble • Often have competition for limited resources

  3. Examples • Building a new airport • Designing a new computer product • Launching an advertising campaign • Construction projects of all types • Maintenance projects • Curriculum reviews

  4. Project Mgmt Techniques • Critical Path Method (CPM) • Developed by DuPont (1950’s) • Plan and control maintenance of chemical plants • Credited with reducing length of maintenance shutdown by 40% • Project Evaluation and Review Technique (PERT) • Developed by Navy (early 1960’s) • Plan and control the Polaris missile project • Credited with speeding up project by 2 years

  5. Critical Path Method(CPM)

  6. Critical Path Method (CPM) • Graphical method of portraying relationship of project activities • An activity is any discrete part or task of a project which takes resources and time to complete • Activities exhibit precedence relations (some must be completed before others can start) • Activities with their precedence relations form a project network • Critical Path Method finds the longest path through the resulting project network

  7. A (Start) B A C A D B, C Precedence Relations Activity Immediate Predecessor Duration (days)

  8. Simple Project Network B D A C

  9. Activity Name Early Start Time Early Finish Time ES EF LS LF Late Finish Time Late Start Time Activity Duration Activity Start/Finish Times

  10. A Finding the Critical Path B 3 D 4 2 C 5

  11. CPM Terminology • Critical Path: the chain of activities along which the delay of any activity will delay the project • Early Start Time (ES): the earliest that an activity could possibly start, given precedence relations • Late Start Time (LS): the latest that an activity could possibly start without delaying the project • Early Finish Time (EF):the earliest that an activity could possibly finish • Late Finish Time (LF):the latest that an activity could possibly finish without delaying the project • Activity Slack: the amount of “play” in the timing of the activity; slack = LST-EST = LFT-EFT

  12. Example Suppose you are an advertising manager responsible for the launch of a new media advertising campaign. The campaign (project) has the following activities: Activity Predecessors Time A. Media bids none 2 wks B. Ad concept none 6 C. Pilot layouts B 3 D. Select media A 8 E. Client check-off A,C 6 F. Pre-production B 8 G. Final production E,F 5 H. Launch campaign D,G 0

  13. Example Project Network D 8 A 2 H 0 Start E 6 C 3 B 6 G 5 F 8

  14. Program Evaluation and Review Technique (PERT)

  15. PERT • Similar to Critical Path Method (CPM) • Accounts for uncertainty in activity duration estimates • Provides estimates of project duration probabilities • Best used for highly uncertain projects • new product development • unique or first-time projects • research and development

  16. Simple Project Network B D A C

  17. A Simple Example a m b Activity Most Optimistic Most Likely Most Pessimistic A 2 3 10 B 1 7 2.5 C 4 6 5 D 0.5 5.5 1.5

  18. Distribution Assumption Assume a “Beta” distribution density activity duration a m b

  19. a + 4m + b 6 (b - a)2 36 Expected Duration & Variance For the Beta Distribution: Expected Time = Variance =

  20. Distribution Assumption expected duration density activity duration a m b

  21. a + 4m + b 6 2+4(3)+10 6 = = 4.0 (b - a)2 36 (10-2)2 36 1.778 = = Expected Duration & Variance Activity A ET = Var =

  22. Critical Path of the Example B 3 A D 4 2 C 5 Critical Path Duration =

  23. Time and Variance Example Activity Expected Time Variance Critical Path? A 4 1.778 B 3 1.0 C 5 0.111 D 2 0.694

  24. Sum of the Variances on the Critical Path z Probability of Completion What is the probability that a project will be completed by a specified due date? Due Date - Expected Completion Date z= Expected Completion NormalDistribution Due Date

  25. 12 - 11 1.778 + 0.111 + 0.694 Completion Probability Example What is the probability of completing the project within 12 days? = z = From a Z-table for standard Normal distributions: Probability of completion =

  26. Larger Example Suppose the duration of the activities of the ad campaign are, in fact, uncertain: (a) (m) (b) ActivityPredsOptimisticLikelyPessimistic A. none 1 2 3 wks B. none 4 6 8 C. B 3 3 3 D. A 2 8 10 E. A,C 3 6 9 F. B 1 8 15 G. E,F 4 5 6 H. D,G 0 0 0

  27. Activity D Suppose the duration of the activities of the ad campaign are, in fact, uncertain: (a) (m) (b) ActivityPredsOptimisticLikelyPessimistic A. none 1 2 3 wks B. none 4 6 8 C. B 3 3 3 D. A 2 8 10 E. A,C 3 6 9 F. B 1 8 15 G. E,F 4 5 6 H. D,G 0 0 0

  28. a + 4m + b 6 2+4(8)+10 6 = (b - a)2 36 (10-2)2 36 = Activity D Expected Activity Duration for “D”: ET = Variance of Activity Duration for “D”: Var =

  29. D A 2 H 0 Start E 6 C 3 B 6 G 5 F 8 Example Project Network 7.33 Critical Path Duration = 20 days

  30. Project Duration Statistics ActivityCritical? MeanVar C.P. Var A. 2 0.11 B. 6 0.44 C. 3 0.00 E. 6 1.00 F. 8 5.44 G. 5 0.11 H. 0 0.00 D. 7.33 1.78

  31. x -   18 - 20 sqrt(1.55) Z = = Using Project Statistics What is the probability that the ad campaign can be completed in 18 weeks? 20? 24? 18 weeks: Corresponding probability from standard normal Z-Table is 0.9463: Prob(x<18) = 1 - 0.9463 =

  32. 18 weeks: Z = -1.61 Prob(x<18) = 20 weeks: Z = 0.00 Prob(x<20) = 24 weeks: Z = 3.21 Prob(x<24) = Using Project Statistics What is the probability that the ad campaign can be completed in 18 weeks? 20? 24?

  33. Other Project Mgmt Techniques • Project crashing • where to devote extra resources to reduce activity/project durations while minimizing costs • Resource leveling • how to schedule resources (equipment, people) to minimizes peaks and valleys • Multiple resource scheduling • how to schedule resources when activities can require more than one resource type • Cash flow and budgeting • combine cash and budget information with project scheduling to track expenditures, project cash flows