1 / 19

William J Marshall & Partners CONSULTING ENGINEERS AND ARCHITECTS, UK

William J Marshall & Partners CONSULTING ENGINEERS AND ARCHITECTS, UK SPECIALISTS IN FORENSIC INVESTIGATION. Investigation of the causes of movement and damage to an office building in the UK founded on Carboniferous Coal Measures mudstone. Robert Jessep MEng CEng MICE MIStructE FGS

pepper
Download Presentation

William J Marshall & Partners CONSULTING ENGINEERS AND ARCHITECTS, UK

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. William J Marshall & PartnersCONSULTING ENGINEERS AND ARCHITECTS, UK SPECIALISTS IN FORENSIC INVESTIGATION Investigation of the causes of movement and damage to an office building in the UK founded on Carboniferous Coal Measures mudstone. Robert Jessep MEngCEng MICE MIStructE FGS Associate Head of Geotechnical Engineering

  2. Introduction • Appointed as an independent Expert under English Law (Civil Procedures) by Solicitors acting for a developer of an office building. • The brief was to establish:- • The causes of movement and damage to the building; (which was about 6 years old at the time of receipt of the instructions) • Whether the movement was ongoing or had ceased; • An appropriate remedial scheme; and • Who was responsible for the shortcomings which led to the damage. William J Marshall & PartnersCONSULTING ENGINEERS AND ARCHITECTS

  3. Description of the site • Geology – Carboniferous Coal Measures • Mainly mudstone weathered to a soft to stiff clay at surface. • Complex site history:- • Storage of steelworks waste for 30 years • Stockpiling of up to ~32m depth of opencast mining arisings • Above material removed about 10 years before development • Re-compacted Coal Measures mudstone fill placed in 800mm thick layers • Granular fill containing slag placed as a working platform. • Trial pits sunk before building • No boreholes sunk in the mudstone • Ground Conditions:- William J Marshall & PartnersCONSULTING ENGINEERS AND ARCHITECTS

  4. Description of the building • 4 Storey Office building with a plan area of ~1000m2, formed of:- • Steel framed construction with precast concrete floors, built on • Pile caps with perimeter ground beams, founded on • Hollow steel piles of 244mm diameter driven to 4 to 6 metres depth. • Masonry built of ground beams with glazing and curtain walling above. • Ground level floor slab formed from ground bearing reinforced concrete slab. • Piles driven to a set which indicates high dynamic resistance. • Dynamic re-strike tests on piles with CAPWAP analysis. • No static maintained load testing of the piles. William J Marshall & PartnersCONSULTING ENGINEERS AND ARCHITECTS

  5. Description of the damage • Crushed partitions • Cracking and distortion of partitions and glazing William J Marshall & PartnersCONSULTING ENGINEERS AND ARCHITECTS

  6. Description of the damage • Cracking in blockwork walls • Cracking in between blockwork walls and columns William J Marshall & PartnersCONSULTING ENGINEERS AND ARCHITECTS

  7. Results of soil investigations • Samples of ‘soil’ subject to oedometer swelling test Results:- • Up to 4.4% strain in fill • 1% strain in a sample of mudstone • Slag chemical analysis/tests Results:- • Little expansion potential in slag • Evidence of past expansion • Mudstone rotary cored Results:- • Slightly to completely weathered • Very stiff clay in places above 6m depth • Very weak rock below 6m depth William J Marshall & PartnersCONSULTING ENGINEERS AND ARCHITECTS

  8. Results of level surveys Precise level surveys were carried out for twelve months. • Followed BRE Digest 386 guidance using two deep ‘stable’ datums. • 2.5m grid of points on the ground slab. • Selected low-level perimeter brickcourse. • Underside of accessible first floor level steel beams. Ground slab Relative levels of the slab 7 years after construction (m) • Floor slab showed variation in levels of 70mm. William J Marshall & PartnersCONSULTING ENGINEERS AND ARCHITECTS

  9. Results of level surveys Ground slab movement in the 4th to 6th years (mm) • Generally heave • Up to 7mm • Isolated settlement • Up to 7mm Ground slab movement in the 7th year (mm) • Continuing heave • Up to 4mm • Isolated settlement • Up to 1mm • Some reversal from above William J Marshall & PartnersCONSULTING ENGINEERS AND ARCHITECTS

  10. Results of level surveys Brickcourse • Survey points at pile/column locations and mid-span between those locations • Level differences of 40mm • Typically low points at piles and high points at mid-span points • Maximum differential of nearly 30mm or a slope of 1:130 • Settlement at 3 pile locations of up to about 1mm in 7th year • One part of the building heaved by 3.3mm in 7th year Relative levels of a perimeter brickcourse 7 years after construction (mm) William J Marshall & PartnersCONSULTING ENGINEERS AND ARCHITECTS

  11. Results of level surveys Steelwork • Limited surveys in 6th year showed settlement of up to 9mm at pile locations • Precise levelling showed the level of the steel beams spanning from the perimeter to internal columns was lower at the internal end. • Typically by 10mm • Up to 22mm • Precise levelling in 7th year generally showed little ongoing movement but • Settlement at some internal columns of up to 1.5mm • 2.5mm heave in one part of the building corresponding with the brickcourse William J Marshall & PartnersCONSULTING ENGINEERS AND ARCHITECTS

  12. Analysis – movement of foundations • Anticipate pile end bearing limited by weaker softer Coal Measures • Ultimate end bearing capacity of the piles would be less than 280kN • Normally ignore limited shaft resistance in design • Pile design loads ranged from 270 to 640kN (only around 60% ever applied) • Given disparity in loads and capacity – excessive settlements not surprising • Surveys suggest settlements of up to 40mm or 15% of pile diameter • Dynamic pile tests predicted a factor of safety ranging from 2.3 to 3.6 • It is recommended that these tests are calibrated with a static load test because: • The results can be in error, typically by a factor of 2 • Dynamic testing in Coal Measures may be unrepresentative due to relaxation • No static load tests were carried out at this site • Undue pile settlement caused by shortcomings in the design due to a lack of site investigation • Static load tests would probably have revealed the inadequate pile load capacity William J Marshall & PartnersCONSULTING ENGINEERS AND ARCHITECTS

  13. Analysis – movement of ground slab • The working platform contained slag • Largely blastfurnace slag which is less expansive than other slags • Petrographic analysis showed evidence of past expansion • Accelerated expansion tests showed little future expansion potential • May only have contributed to a minor extent to the heave of the building • Fill from mudstone normally subject to settlement • In particular collapse settlement upon inundation or percolation with water • Probable explanation for settlements observed in the past in areas of the slab • The fill at this site came from a mine that was up to 95m deep • Stress relief could be expected to give rise to long term swelling with water absorption • Particularly with gravel and boulder sized lumps of mudstone • Swelling tests indicate potential for up to 100mm future heave but probably 40mm • Likely swelling of this fill has been the significant cause of the heave at this site • Minor contribution to heave from swelling of Coal Measures caused by stockpiling surcharge and subsequent unloading • Excessive heave and settlement caused by inadequacies in the design due to a lack of adequate desk study, site investigation and testing of the subsoils William J Marshall & PartnersCONSULTING ENGINEERS AND ARCHITECTS

  14. Conclusions • The movement and damage at this building has been largely caused by:- • Lack of adequate desk study, and • Lack of adequate site investigation • This case study highlights:- • The importance of good desk study and site investigation • The need to consider stress history of sub-soils • The general risks associated with fill materials • The need to calibrate dynamic pile tests with static maintained load tests William J Marshall & PartnersCONSULTING ENGINEERS AND ARCHITECTS

  15. Thank you ... Discussion William J Marshall & PartnersCONSULTING ENGINEERS AND ARCHITECTS

More Related