An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LHC injection and dump re-commissioning 2012 W. Bartmann, M. Barnes, C. Bracco, E. Carlier, L. Drosdal, B. Goddard, M. Meddahi, V. Kain, J. Uythoven LBOC Meeting, 21-Feb-2012

  2. MPS task list for checkout and beam com. https://espace.cern.ch/LHC-Machine-Protection/default.aspx LHC inj/dump recommissioning

  3. Normal commissioning with beam • Injection system: • MKI softstart tests • Synchronisation SPS extraction kicker and MKI • Synchronisation of MKI with the AGK interlock • Injection set up • TL steering and save reference (TI 8 realigned) • TCDI- setup and validation (phase space coverage) • TDI/TCLI – angular setup and validation (TDI grazing with MKI knob) • Injection cleaning • Beam dump system: • TCSG/TCDQ set-up and validation (asynch dump tests) • 14/15 MKD test • MKD/B and MSD energy tracking (4 TeV) • Synchronisation of abort gap and RF • Interlock checks: RF, BPMS (SW/HW), TCSG/TCDQ position (SW/HW), MSD FMCM • XPOC checks • BI acquisition and logging (BTVs blocked, might be used for special cases) • Test of procedures when BD system does not trigger via BIS • Abort gap monitor/cleaning LHC inj/dump recommissioning

  4. Additional tests for 2012 start-up (I) • TSU • Need 4 h with BIS loops closed and no beam • Few hours with beam in circulate and dump to check if synchronisation OK • TCDQ • TCDQ for B2 has been realigned and recalibrated • New interlock for β* function to be checked or decided to have it maskable and check at a later point? (need β* published for tests) • Abort gap window reduced by 50 ns – to be checked with AGK and SIS updated, can be done in frame of normal checks • Set-up and calibration of Diamond BLMs at SPS extr and LHC inj (together with BI) • Asynchronous dump follow up checks (check situation before) • Extraction channel aperture (fill machine with pilots in 2 us spacing and dump) LHC inj/dump recommissioning

  5. Additional tests for 2012 start-up (II) • TDI/TCLIA • Aperture scan with circulating beam with open TDI jaws • Check if we find same grazing asymmetry in P2 • Measure with Diamond BLMs if losses from circulating or injected beam • Angular alignment of TCLIA.P2? • Seperated beam process for injection protection collimators • TL stability checks with beam on downstream TED (Indiv, EPC to be informed) LHC inj/dump recommissioning

  6. Summary • 2011 we had about 15 min of machine check-out... ... and as a consequence a lot of access requests during slow intensity ramp up • A serious time period is required to test machine protection critical hardware! (BIS loops closed, no beam) • Checkout time needed for: • injection: 1 shift • dump: 4 shifts + 0.5 shifts for TSU • TL: 2 shifts (with beam permit and beam on downstream TED) • Beam commissioning time needed for: • injection: 4 shifts+ 0.5 shifts for TDI/TCLIA • dump: 4 shifts + 0.5 shifts for TSU • Some tasks possible in parallel with other tests LHC inj/dump recommissioning