1 / 14

Production Summary

Production Summary. Tony Smith (Production Coordinator). Overview. Introduction to production process Logistics / yield Delivery Rate Critical path items Risks Issues Summary . Production process. Top level view of production process See Talk for process control and QA.

nile
Download Presentation

Production Summary

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Production Summary Tony Smith (Production Coordinator)

  2. Overview • Introduction to production process • Logistics / yield • Delivery Rate • Critical path items • Risks • Issues • Summary Tony Smith – VELO PRR

  3. Production process • Top level view of production process • See Talk for process control and QA Tony Smith – VELO PRR

  4. VELO specific • Cash critical • Time critical • These mean component wastage is BAD • See next transparancy • Delicate high value items • Limited prototyping Tony Smith – VELO PRR

  5. Limiting factors in production • How many could we make? Tony Smith – VELO PRR

  6. Comments on yield • Safe on all components • Silicon tight if unexpected breakages occur • Approx 20% loss on silicon accounted for in production • Recommend – purchase of 10 more R&Phi • This would make approximately 50 + modules • Currently cannot release R’s for Veto (6 requested) Tony Smith – VELO PRR

  7. Steady state delivery rate • Gantt chart analysis is dominated by obvious common sense factors • Glue curing • (eg 24 hours for hybrid to paddle ) • Testing times • Bonding times • Burn-in in Vacuum Time • Limited equipment and manpower (e.g. Bonders ) Tony Smith – VELO PRR

  8. Delivery rate – ctd. • Using realistic work weeks and load on equipment and people • Back of envelope 2 per week • Gantt analysis – 2 per week • We have yet to prove this in practice • Most stages have been proven and timed – see Gantt Chart Tony Smith – VELO PRR

  9. Ramping to delivery rate • Rushing things is DANGEROUS • Lost 4 electrical candidate hybrids in weeks to PRR • Need semi-sequential startup (approx 3 modules at 1-2 weeks each). Tony Smith – VELO PRR

  10. Rate Tony Smith – VELO PRR

  11. Critical path to PRR • Prove Sensor-Sensor  • Electrical Modules (~days based on 710) • Base-sensor (2 week) • Vacuum tank qualification(2 weeks) • Improved jigging for handling (2 weeks) Tony Smith – VELO PRR

  12. High risk and impact • Risks with equipment • Follows common sense • Not perfect (PPARC +TJVB algorithm adhoc) • Indicative of expense and risk e.g. cables now as high as sensor delivery • Requires attention • 8090 problem dropping as 710 comes online • Parts and contract for spares evaluated ! low risk or impact Tony Smith – VELO PRR

  13. Issues • Chronic problem we need to resolve • 8090 is a lemon (same device as used by US for CMS production) • Transfer to 710? • Safety of modules • Insist on more handling jigs needed (2 weeks?) • Enforce 2 person module procedures as with sensor testing (onerous) • db entry discipline • Contamination • Cleanliness of the hybrid • Storage and transport • Vacuum distortion needs to be measured Tony Smith – VELO PRR

  14. Summary • Our view is at least 3 weeks from production readiness • Including improving handling • Aim to start up over a month at ~ 1 /week • Transition to 2/week in second month • Increasing risk with cables • 710 qualification likely to offset problems with 8090 Tony Smith – VELO PRR

More Related