Click Here---> http://bit.ly/34xuK0Y <---Get complete detail on CPIM Part 2 exam guide to crack Production and Inventory Management. You can collect all information on CPIM Part 2 tutorial, practice test, books, study material, exam questions, and syllabus. Firm your knowledge on Production and Inventory Management and get ready to crack CPIM Part 2 certification. Explore all information on CPIM Part 2 exam with number of questions, passing percentage and time duration to complete test.
E N D
How to Prepare for APICS CPIM Part 2 Exam?
APICS Production and Inventory Management Exam Summary: Vendor Exam Code Full Exam Name APICS CPIM Part 2 APICS Certified in Production and Inventory Management - Part 2 Number of Questions 150 Sample Questions APICS CPIM Part 2 Exam Sample Questions and Answers Practice Exam APICS Certified in Production and Inventory Management (CPIM) Practice Test 300 / 350 Passing Score Time Limit 210 Minutes
CPIM Part 2 Certification Syllabus Content: Syllabus Topics: Weights Master Planning of Resources 25% Detailed Scheduling and Planning 25% Execution and Control of Operations 25% Strategic Management of Resources 25%
How much Fees of APICS CPIM Part 2 Exam? APICS CPIM Part 2 Fee Structure: PLUS member price Exam Fee: USD $495 CORE member/nonmember Exam Fee: USD $690 Retake Exam Fee: USD $250
CPIM Part 2 Study Guide: ● Know about APICS Production and Inventory Management book details. ● Go through APICS CPIM Part 2 exam syllabus. ● Go through APICS Production and Inventory Management sample questions. This will give you a clear idea about the real exam. ● Enroll for CPIM Part 2 practice test on ProcessExam.com. ● Identify your weak areas from CPIM Part 2 sample exam and do more practice with system.
APICS Production APICS Production and Inventory and Inventory Management Management Sample Questions Sample Questions
Que.: 1. Which of the following is the primary role for demand management? Options: a) Providing a tool for aggregation and disaggregation of demand. b) Linking the production plan to MRP. c) Providing input to the master schedule. d) Synchronizing of market activities and the production plan.
Answer: d) Synchronizing of market activities and the production plan.
Que.: 2. In which of the following environments would the capable-to-promise (CTP) functionality be LEAST helpful? Options: a) Make-to-stock. b) Make-to-order. c) Assemble-to-order. d) Engineer-to-order.
Answer: a) Make-to-stock.
Que.: 3. Who is responsible for evaluating the master schedule? Options: a) Shop manager. b) Middle manager. c) Top manager. d) Supervisor.
Answer: b) Middle manager.
Que.: 4. Your are a company master scheduler and just have scheduled the master schedule, which calculate ATP in demand time fence as 85 units. If 100 units of a customer order in demand time fence is demanding, which of the following action is the MOST appropriate as the master scheduler? Options: a) Accept this customer order and expedite production. b) Firstly accept 85 units of the customer order, request the decision making to the senior management for the remaining orders. c) Accept this customer order and replan the mater production schedule. d) Firstly accept 85 units of the customer order, promise the remaining order after demand time fence.
Answer: b) Firstly accept 85 units of the customer order, request the decision making to the senior management for the remaining orders.
Que.: 5. The customers of a company that implements Just-in- Time will MOST likely benefit from which of the following? Options: a) Increased delivery lead time. b) Small lot sizes. c) Improved quality of products shipped. d) Reduced freight costs.
Answer: c) Improved quality of products shipped.
Unique Features Continued…. ● ProcessExam.com has provided good quality CPIM Part 2 sample questions. ● One can go through the Production and Inventory Management sample questions before buying the CPIM Part 2 online practice test. ● One can take unlimited attempts to practice from the CPIM Part 2 practice test. ● It is available for two months. ● A candidate is able to measure his speed from the online practice test. ● Best CPIM Part 2 book links are also provided on the website syllabus page.
Unique Features Continued…. ● If a candidate wants to know about Production and Inventory Management training detail, our website provides information about that too. ● A candidate is able to know about his performance depending on the result section of Production and Inventory Management online test. ● Marks obtained could be a motivator factor to prepare more or less depending on the result. ● Last but not the least, we have a money back policy in our website,that makes us really unique. ● Testimonials written on the website, could be helpful to choose our website, as these are shared by our valuable users, who availed our online practice test.
To Know More about APICS CPIM Part 2 Certification VISIT www.processexam.com