1 / 53

Renovation of St. John Neumann High School

Renovation of St. John Neumann High School. Rocco D’Uva Introduction/Project Review Architectural Analysis & Design HVAC Analysis & Design Miguel Armijos Structural Analysis & Design Rick Howley Environmental Analysis & Design Budget. Project Review.

nfain
Download Presentation

Renovation of St. John Neumann High School

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Renovation of St. John Neumann High School Rocco D’Uva Introduction/Project Review Architectural Analysis & Design HVAC Analysis & Design Miguel Armijos Structural Analysis & Design Rick Howley Environmental Analysis & Design Budget

  2. Project Review Aerial Photo • Location: 2600 Moore St. Philadelphia, Pa • Size: 3 story building • Age: Built in 1955 Existing Footprint

  3. Problem Statement • Owner wants to change use from private school to residential apartments • Specific problems to solve: • What building systems are affected • How are they affected • What is their current state • How should they be redesigned

  4. ARCHITECTURALSYSTEM OUTLINE: • Existing Site & Floor Plans • New Site Plan • New Floor Plans

  5. 1. Entry Moved 2. Structural Walls Used 3. 11,000 SF Removed for Parking 4. 5,600 SF Added for Ballroom/Natatorium EXISTING SITE PLAN

  6. NEW SITE PLAN

  7. RESIDENTIAL SECTION – FLOOR PLANS 1, 2, 3

  8. COMMERCIAL SECTION 1ST FLOOR PLAN – BALLROOM

  9. COMMERCIAL SECTION 2ND FLOOR PLAN – NATATORIUM

  10. Architectural Program

  11. HVACSYSTEM OUTLINE: • Specific Design Focus • Residential Area Problems/Solutions • Natatorium Design Problems/Solutions • Optimal Solutions • Equipment Example

  12. Design Focus – What To Design? • Residential vs. Commercial Areas • Wide Array of Problems • Residential = More Common • Focus will be on the Natatorium

  13. Residential Areas • Design Parameters include: • Heating & Cooling during winter/summer • Low initial cost • Low operating cost • High efficiency • Assumptions: • Basic options include: Split VAV Rooftop units or PTAC Units • Alternative with the highest efficiency and lowest cost is the best solution

  14. Natatorium Design PROBLEMS • High Evaporation Rates • Humidity Control • Condensation • Loss of Pool Water (costs to refill) • Thermal Comfort • Air Quality/Exchange • Heating of Pool Water

  15. Evaporation Rate Formula • Evaporation Rate = ERF x AF x Pool Water Surface Area • Where: ERF = Evaporation Rate Factor (table) • AF = Activity Factor (assumed to be 0.65) • Pool Water Surface Area = Approx. 9500 ft2

  16. Evaporation Rate Factor Table

  17. Evaporation Rate Calculation

  18. Evaporation Rate Trend

  19. Condensation • Windows • Recommended 3-5 CFM per SF of exterior glass • Therefore, natatorium requires 2,400-4,200 CFM • Walls, Ceilings, Other Thermal Bridges • Vapor Retarder • Proper Air Distribution is Key to Minimizing Damage • Minimize Eddy Effects Over Window (Mullions) • Minimize Air Flow Over Pool Surface

  20. Loss of Pool Water • The amount of condensate recovered in a year by the HVAC system is approximately equal to one entire pool fill.

  21. Air Quality & Air Exchange • ASHRAE Recommendations: • 0.5 CFM of Outside air per FT2 of pool and wet deck Area… (For us, approx 4,800 CFM) • 15 CFM of Outside air per spectator/user… (For us, assume above is larger) • 4-6 Air Changes per Hour… (vs. 6-8 for spectator facilities) • 13 – 37 Pa of Negative Pressure (We will use multiple exhaust fans) • Must be able to purge if necessary

  22. Pool Water Heating

  23. Basic Equipment Example

  24. Pool Design

  25. Design of a Swimming Pool • Swimming pool on the 2nd floor • Dimensions: - 30ft by 90ft - 6ft deep

  26. Considerations • Water in pool become heavy loads 62.4 lb/ft x 30ft wide x 90ft long x 6ft deep = A total of 1,010,880 lbs • Architectural Considerations • Sizes of structural members • Column spacing

  27. Structural System • Pick a system that can handle heavy loads and is efficient:

  28. Structural System : Option 1 • One-way Joist Slab • Joists act as t- beams to distribute the loads to the girders • Span 15 to 36 ft • Economical system for heavy loads or long spans

  29. Structural System : Option 2 1. Concrete Waffle Slab • Because there are joists in both directions, this floor system is the strongest and will have the least deflection • 20 to 50 ft spans • Good for high gravity loads • High stiffness • Small deflections • Expensive due to formwork

  30. Structural System – One-Way Joist Slab

  31. Slab Design • ACI requires for the height of slab to be at least Height = (Length of span)/20 In our case ----- Minimum Height = 3.6 “ *But Code requires a 6” slab for in our design for fire requirements*

  32. Slab Design • Live Loads: Water • Dead Load: Weight of concrete slab • 6” slab • Reinforcement - # 4 @ 12” O.C • ACI Requirement – Ends of slab (length of span)/4 & Interior Spans (length of span)*(.3)

  33. Beam Design - Joist Layout • Skip Joists - Every 6 ft • Span - 30ft

  34. Trial Structural System Sizing

  35. Total Weight of Structural System

  36. Joists • Mu = 515.7 ft-kips • Span = 30 ft • Dimensions B = 11” D = 32” • Reinforcement - 6 #7’s - # 3 Stirrups

  37. Girder Design • Max Moment = 1092 Ft-Kips

  38. Girder Design • B = 22” D = 32” • Compression Rebar ( ACI required in this case) - 2 # 8 • Tension Rebar - 8 # 10’s • # 3 stirrups

  39. Column Design • Column layout

  40. Column Design • Dimension 18” x 18” 11 ft high • Reinforcement 8 # 9’s # 3 Ties • According to code Spacing = 18”

  41. Column Interaction Diagram • Evaluation of the strength of the column subjected to combined bending and axial loads • Balanced Failure limit @ P = 400 kips M = 250 ft-kips

  42. Stormwater Detention/Retention

  43. Why retain stormwater? • Impervious surfaces • High runoff flow • High river flow • Erosion of stream banks • Altered groundwater tables • Contamination of streams • Carried from streets • Turbidity Schuylkill River bank on Kelly Drive

  44. Drainage • Crest of the field • Roof and lot drainage to site storm drains • Swales direct current around field to basin

  45. Regulations Philadelphia City Codes • 1 inch must be infiltrated • Detention design for 100 year storm • Only storm water may enter drainage pipes • Design so that post-development infiltration equals pre-development infiltration

  46. Specs Reference: 100 year storm with duration of 1 hour (duration assumption based on size and slope of parcel) Area=379146.24ft2 -Half of the area is the impervious parking lot and roof, the other half is the football and baseball fields Soil Class C-Soils having slow infiltration rates if thoroughly wetted and consisting chiefly of soils with a layer that impedes the downward movement of water, or soils with moderately fine to fine texture. They have a slow rate of water transmission.

  47. Storm Analysis • Design for 100 year storm • Duration 1 hour (based on size and slope of parcel) • Rainfall Depth 3.25 inches from chart

  48. Pre-development Runoff Curve Number CN=79 (open space fair condition grass cover 50-75%) Potential Maximum Retention S=1000/79-10=2.66 Qrunoff=(P-0.2S)2/(P+0.85) Q=(3.25-.2*2.66)2/(3.25+0.85) Q=1.8in=0.15ft*A Q=56871.93ft3/hr I=3.25-1.8=1.45in Post-development CN=79 (field) CN=98 (Parking lots, roofs, etc.) f=0.5 CNw=CNp(1-f)+f(98) CNw=79(0.5)+0.5(98)=88.5 S=1000/88.5-10=1.3 Qrunoff=(3.25-0.2*1.3)2/(3.25+0.85) Q=2.18in=0.1817ft*A Q=68878.2ft3/hr I=3.25-2.18=1.07in Infiltration

  49. Underground Basin Design • Qpost-Qpre=68878.2-56871.9=12006.3ft3/hr • Must re-infiltrate this volume. • Design a detention basin with two tanks with weir flow from storage tank to discharge tank • Weir 1ft wide by 10ft tall by 60ft long=600ft3 • Storage Tank 20ft wide by 10ft tall by 60ft long=12000ft3 • Entire Tank 77ft wide by 15ft tall by 60ft long=69300ft3 • Maximum volume of basin=69300-600=68700ft3 • Storage Tank will supply sprinkler system • Discharge to storm sewer at Mifflin Street

  50. Underground Basin 5ft 10ft 60ft 57ft 20ft

More Related