Problem #5 , p 137

Problem #5 , p 137. Expando, Inc. is considering the possibility of building an additional factory Small facility ($6M cost) Low demand - $10M High demand - $12M Large facility ($9M cost) Low demand - $10M High demand - $14M Probability of high demand is 0.40

Download Presentation

Problem #5 , p 137

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Problem #5 , p 137 • Expando, Inc. is considering the possibility of building an additional factory • Small facility ($6M cost) • Low demand - $10M • High demand - $12M • Large facility ($9M cost) • Low demand - $10M • High demand - $14M • Probability of high demand is 0.40 • Probability of low demand is 0.60 • No construction  no additional revenue

  2. Build small_high demand = $6M High demand (0.40) Build small factory $ 4.8M Low demand (0.60) Build small_low demand = $4M Expando, Inc. High demand (0.40) Build large_high demand = $5M Build large factory $ 2.6M Low demand (0.60) Build large_low demand = $1M

  3. Expected Values • Computing for Expected Values associated w/current decision alternatives • Sample computation: Build small factory Value of high demand alternative ($6M) x High demand probability (0.4) + Value of low demand alternative ($4M) x Low demand probability (0.6) = $ 4.8 M