CMAST Update

CMAST Update. March 25, 2014. CMAST Update. CMAST Improvement Project. On schedule and budget Approximately half way complete Concludes in December 2014. CMAST Update. CMAST Improvement Project. Completed to date Label Certificate improvement

lyle
Download Presentation

CMAST Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CMAST Update March 25, 2014

  2. CMAST Update CMAST Improvement Project • On schedule and budget • Approximately half way complete • Concludes in December 2014

  3. CMAST Update CMAST Improvement Project • Completed to date • Label Certificate improvement • Separating the Actual Size information from the Label Certificate to the Supplemental Info Report via the Supplemental Info checkbox • Product type modification (metal/nonmetal frame) • User interface • Type glass id • Double click for the frame configurator • Bid report improvements (Phase 1) • Make available on the server

  4. CMAST Update CMAST Changes (not Improvement Project) • CMAST billing changed since the beginning of the CMAST Improvement Project • Removed billing function from CMAST • Now billed from staff • IGDB updates to 33.0 • 34.0 will be with next release

  5. CMAST Update CMAST Improvement Project • Next on schedule • Smart Synchronization • Internal testing in April • May launch anticipated

  6. CMAST Update Next Items in Improvement project • WINDOW7/THERM7 integration (calculation changes) • Will begin to test now • Batch approval process • Will speed component upload • Update Document Trail Audit (change allowing the IA to reset the SA’s DTA if necessary) • Update Role Visibilities • Bid Report Phase 2 • Update Server DB (ongoing) • Update Client DB (ongoing)

  7. CMAST Update New Items for CMAST Improvement • Supplemental information revision on bid report • Staff and task group creating business case • Improved algorithm integration • NFRC 100 ballot must pass • Staff and task group creating business case