An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    1. ICT System Impact Study Process Bruce Rew LPSC Technical Conference September 11, 2006 Houston, TX

    2. Status & Overview Our project plan is to go live 11/1 pending final approval ICT System Impact Study Process is defined in the Transmission Service Protocol Appendix to Attachment S of the Entergy OATT

    3. System Impact Study Cutover After the Tariff Administration function transitions to ICT, ICT Planning will begin to process GI and TSR studies Any studies started by Entergy will be completed by Entergy Any studies in queue yet to be started will be handled by ICT

    4. System Impact Study Process ICT is primary point of contact for customer System Impact Study Agreements and Facility Study Agreements administered by ICT ICT performs SIS with Entergy Transmission assisting as needed in Transmission Service evaluation

    5. System Impact Study Process Full service availability, partial service availability, or no service availability determined by ICT ICT provides mitigation plan and cost estimates when limited or no service is available across existing facilities

    6. System Impact Study Process ICT posts final report to OASIS and notifies Customer and Entergy ICT sends Facility Study Agreement to Customer if required

    7. System Impact Study Process ICT sends Facility Study Agreement to Customer if required ICT determines utilization of supplemental upgrade capacity and financial compensation ICT forwards models from System Impact Study and other relevant data to Entergy

    8. Facility Study Process ICT reviews and validates inputs and results of Facility Study ICT incorporates Entergy input, including disagreements, into report ICT posts final report to OASIS and notifies Customer and Entergy

    9. FS Study Process ICT reviews and validates inputs and results of Facility Study prior to OASIS posting ICT bills Customer for ICT and Entergy time and expense ICT responds to work paper requests Entergy is responsible for administering the Transmission Service Agreement process

    10. Questions or Comments? Bruce Rew (501) 614-3214 brew@spp.org