MUPS Anomally, July-Aug 2009

MUPS Anomally, July-Aug 2009. Timing: Cycle 11 targets approved, BUT not yet reviewed or in the ObsCat Initial Actions: No MUPS firing → restricted pointing, need larger target pool Ingest Cycle 11 GO targets to ObsCat rapidly

lexiss
Download Presentation

MUPS Anomally, July-Aug 2009

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MUPS Anomally, July-Aug 2009 • Timing: Cycle 11 targets approved, BUT not yet reviewed or in the ObsCat • Initial Actions: • No MUPS firing → restricted pointing, need larger target pool • Ingest Cycle 11 GO targets to ObsCat rapidly • Start IPPS process early (requests PI/Observers to check high-level pars) • Signed-off, unconstrained targets made available to MP • Announcement: website + bulletin #86 • warned observers of chance of early observation, request quick response if contacted • PI Non-response: USINT and CDO to approve observation • No detailed announcement, knowledge of situation evolving rapidly ChandraUsers’ Committee, 29-30 Oct 2009 Chandra Director’s Office

  2. MUPS Anomally, July-Aug 2009 (cont) • Subsequent Action: • Pitch angle restricted to >130 deg, small target pool • MP: identified unconstrained targets in required pitch range • USINT: contact PIs/Observers for detailed parameter check for observation readiness • All Clear: • Normal operations resumed immediately • IPPS process continued • CDO final checks of constrained/complex targets completed • CDO handover to USINT proceeded as usual ChandraUsers’ Committee, 29-30 Oct 2009 Chandra Director’s Office