IBL Progress Meeting. Engineering progresses On IBL package. TASKS TO COMPLETE THE PACKAGe. C ompleted. TASKS TO COMPLETE THE PACKAGE. LAPP Maarten Sébastien. Service wrapping performed on A and C side From Monday 14 th to Wednesday 16 th Envelope check.
E N D
IBL Progress Meeting Engineering progresses On IBL package
TASKS TO COMPLETE THE PACKAGe Completed
TASKS TO COMPLETE THE PACKAGE LAPP Maarten Sébastien • Service wrapping performed on A and C side • From Monday 14th to Wednesday 16th • Envelope check
TASKS TO COMPLETE THE PACKAGE • Additional task: Bonding of sealing ring extension on side A • IST overlength 4 mm • Thursday 16th to Tuesday 22th
TASKS TO COMPLETE THE PACKAGE Maarten Sébastien • MPC extensions connection side A and C • Wednesday 23rd
TASKS TO COMPLETE THE PACKAGe Completed
TASKS TO COMPLETE THE PACKAGe Maarten Augusto Sébastien • Cooling manifold disconnection and removal Tursday24th • Prepare package for transport • End caps to install on both side • Accelerometers • Transversal beams