An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Progress Report NuPECC, Milano, 9/3/12

  2. 1st Birthday Signing of the FAIR Convention by representatives of the founding countriesFinland, France, Germany, India, Poland, Romania, Russia, Slovenia and Swedenin Wiesbaden on 4/10/2010 NuPECC, Milano, 9/3/12

  3. OrgChart FAIR Company FAIR Council AFC Scientific Council IKRB MAC ManagementBoard Staff Office LegalAdvisor CouncilIssues Secretariat BFC Internal Auditing Research TechnicalDivision Site &Buildings Admin. Expert C‘ttee Experiments Project OfficeExperiments Project Office Techn. Division Reporting Project Office Site & Buildings Internal Services APPA TechnicalServices M&E Advisor Civil Eng. Advisor Controlling CBM In-Kind Coordination M&E Eng. Automation, IT Finance NuSTAR TechnicalFollow-up M&E Eng.Power, Mat. Purchasing PANDA M&E Eng. Thermo, Refrig. Personnel M&E Eng.Liqu., Gases Constr. Eng.Building, Geo. Constr. Managem. Eng. NuPECC, Milano, 9/3/12

  4. OrgChart FAIR-GSI Collaboration NuPECC, Milano, 9/3/12

  5. Modularised Start Version M0 M3 M1 M3 M2 CBM/HADES APPA PANDA Experiments M1: APPA M1: CBM/HADES M2: NuSTAR M3: PANDA NuSTAR NuPECC, Milano, 9/3/12

  6. Costs MSV in 2005 € (inflationescalationuntil 2018: ca. +50%) * Total experimental end stations (excluding Super-FRS):ca. 210 M€ (2005) = 315 M€ (2018) NuPECC, Milano, 9/3/12

  7. Timeline 2011 2012 2013 2014 2015 2016 2017 2018 2019 9 11 12 6 7 8 10 Building permits Site preparation Civil construction contracts Building of accelerator & detector components Completion of civil construction work Installation & commissioning of accelerators and detectors Start Data taking 10 6 7 12 8 9 NuPECC, Milano, 9/3/12 11

  8. Civil Construction NuPECC, Milano, 9/3/12

  9. Applications & Permits 11.11.11 31.08.11 19.01.12 20.01.12 21./23.11 NuPECC, Milano, 9/3/12

  10. First Post Drilling 31/8/2011 NuPECC, Milano, 9/3/12

  11. Clearing Construction Site 6/12/2011 NuPECC, Milano, 9/3/12

  12. Further Preparatory Work NuPECC, Milano, 9/3/12

  13. Planning Activities NuPECC, Milano, 9/3/12

  14. Accelerators • Orderedfor SIS100 from Babcock Noell in Jan. 2012 (German in-kind contribution, BMBF grantto GSI) • Manyotherpartsof SIS100 and CR in preparation (in-kind ortender) • HESR readytogo out fortender (BMBF grantofferedto FZ Jülich) • IKRB meetingat FAIR on 28/3/12 • MAC meetingat FZ Jülich on 2/4/12 Compact & cost effective Fast cycling superconducting magnetsdB/dt~ 4T/s NuPECC, Milano, 9/3/12

  15. MSV Experiments NuPECC, Milano, 9/3/12

  16. APPA • Board of APPA Collaborationsestablished • SpokesmanandDeputyelected • Layout of APPA hall finalised • Options exploredforexperimentsat • HESR • Cryring @ ESR APPA NuPECC, Milano, 9/3/12

  17. CBM • HADES detectorupgraded • CollaborationwithDubna (NICA) beingconsidered • Finishing R&D work CBM NuPECC, Milano, 9/3/12

  18. NuSTAR • Hall LEB being considered by Collaboration • search for funds outside of MSV budget • Exp. @ HESR being considered Super-FRS NuSTAR NuPECC, Milano, 9/3/12

  19. PANDA • R&D being finished • Remaining TDRs being finalised • Premounting @ FZ Jülich being prepared PANDA NuPECC, Milano, 9/3/12

  20. Timeline Experiments • Finish R&D phase 2012 • Deliver prototypes of all essential parts • Submit complete sets of TDRs 2012 • Take decisions on alternative technical solutions • Co-ordinate with 2012 • Civil construction requirements & accelerator setup schedule • Identify critical pathways, submit risk management plan 2012 • Timelines, milestones, deliverables • Secure funding, negotiate MoUs between Collaborations,Funding Agencies and FAIR 2012/13 • (Europe-wide) tendering 2013 • Build detectors 2013-16 • Commission detectors 2017 • Initial period of data taking 2018-21 NuPECC, Milano, 9/3/12

  21. Commissioning & Operation • Commissioning MSV, Modules 0-3 • Top priority: Module 0 – SIS100 • Sequence of experiments depends on • Civil construction • Progress in • Prototyping & building of accelerators (storage rings) • Prototyping & building of production targets (RIB & anti-proton targets) • Prototyping & setting up of large-scale experimental equipment • Funding (majority from outwith FAIR MSV budget) • Operation MSV, Modules 0-3 • Signing of agreement on financing the FAIR operation budgetthree years after project has started (autumn 2013 at the latest) • Development of model for fair share of costs for operating FAIR • Explore • Contributions from participating countries that are not shareholders • Set up common collaboration funds for running the experiments (cf. DESY & CERN) • Modules 4 & 5, Phase B • Secure funding for civil construction, accelerators and experiments of Modules 4 & 5 • Continue R&D, in particular for SIS300, HESR Electron Cooler and NESR Electron Ring NuPECC, Milano, 9/3/12

  22. FAIR Open Space Planning NuPECC, Milano, 9/3/12 22

  23. Thank you very much NuPECC, Milano, 9/3/12