CVPS wetland review Presented by Central Vermont Public Service Corporation PowerPoint Presentation
Download Presentation
CVPS wetland review Presented by Central Vermont Public Service Corporation

Loading in 2 Seconds...

play fullscreen
1 / 18

CVPS wetland review Presented by Central Vermont Public Service Corporation - PowerPoint PPT Presentation


  • 140 Views
  • Uploaded on

CVPS wetland review Presented by Central Vermont Public Service Corporation. Vermont Water Resources Panel September 7, 2006. CVPS Service Territory ~8,000 miles distribution, 600+ miles transmission 100+ substations. Utility line project design CVPS Work Management System software.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'CVPS wetland review Presented by Central Vermont Public Service Corporation' - kevina


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
cvps wetland review presented by central vermont public service corporation

CVPS wetland reviewPresented by Central Vermont Public Service Corporation

Vermont Water Resources Panel

September 7, 2006

utility line project design cvps work management system software
Utility line project designCVPS Work Management System software
  • Computer-based design/inventory tool
  • Projects have four phases: Initiation, Design, Construction, Closed
  • All Pre-construction requirements must be complete before work tickets can be printed
  • Permitting requirements: Automatically activated for any design with more than three pole installations, or any amount of primary-voltage underground
  • Security features prevent anyone but the Permit Coordinator from completing or overriding permit requirements
  • Several thousand construction projects annually
framme
Framme
  • Intergraph mapping software
  • Construction prints generated through automated process, taking design information from WMS
  • Other information added by designers (roads, treelines, easement info, etc.)
gis data
GIS data
  • ArcView is used to review every project flagged through WMS, plus others identified by field designers
  • Project designs include X,Y coordinates for every pole (and foundation for underground cabinets/transformers)
  • Pole locations are overlaid onto roads, buildings, VSWI, NHI, surface waters, NAIP color aerial photos, and USGS topo maps
utility of maps
Utility of maps
  • VSWI maps, combined with other data, allow for very reliable screening of projects for possible review and permitting under state wetland rules.
  • Loss of VSWI maps with current system would guarantee non-compliance despite best efforts.
  • Loss of VSWI maps combined with state GP would slightly increase risk of non-compliance, significantly reduce the level of project review, and increase the amount of wetland impacts, however small and/or temporary they may be.