Lean Project Management. Project Management Overview. What is a Project? . A temporary endeavor to create a unique product, service, or result. Characteristics: Specific goal or deadline Complex, interrelated tasks, special skills Critical to organization Cross-functional.

Lean Project Management - slide 1
01 / 30Lean Project Management
1 / 17

Download Presentation

Lean Project Management
An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

More Related Content

Presentation Transcript
  1. Lean Project Management Project Management Overview

  2. What is a Project? • A temporary endeavor to create a unique product, service, or result. • Characteristics: • Specific goal or deadline • Complex, interrelated tasks, special skills • Critical to organization • Cross-functional

  3. Examples of Projects • Construction • Software development • New product development • Research • New business

  4. Management of Projects • Initiating - goal setting, defining the project, project charter team organization • Planning – scope statement, estimates, approval • Executing – project team, accomplish tasks of the project, manage expectations, test • Monitoring and Controlling - monitor resources, costs, quality, and budgets; revise plans and shift resources to meet time and cost demands • Closing – contract closure, project close PMBOK

  5. Project Management Techniques • Gantt chart • Critical Path Method (CPM) • Program Evaluation and Review Technique (PERT) • Critical Chain Project Management (CCPM) • Lean Project Management

  6. Gantt Charts • Horizontal bar chart showing time and task • Developed in 1910s by Henri Gantt • Can consider precedence relationships • Can use multiple or single task time estimates

  7. PERT and CPM • Network techniques • Developed in 1950s • CPM by DuPont for chemical plants (1957) • PERT by Booz, Allen & Hamilton with the U.S. Navy, for Polaris missile (1958) • Consider precedence relationships and interdependencies • Each uses a different estimate of activity times

  8. Six Steps PERT & CPM • Define the project and prepare the work breakdown structure • Develop relationships among the activities - decide which activities must precede and which must follow others • Draw the network connecting all of the activities

  9. Six Steps PERT & CPM • Assign time and/or cost estimates to each activity • Compute the longest time path through the network – this is called the critical path • Use the network to help plan, schedule, monitor, and control the project

  10. PERT and CPM: Network Analysis From the caketalkblog

  11. Questions PERT & CPM Can Answer • When will the entire project be completed? • What are the critical activities or tasks in the project? • Which are the noncritical activities? • What is the probability the project will be completed by a specific date?

  12. Questions PERT & CPM Can Answer • Is the project on schedule, behind schedule, or ahead of schedule? • Is the money spent equal to, less than, or greater than the budget? • Are there enough resources available to finish the project on time? • If the project must be finished in a shorter time, what is the way to accomplish this at least cost?

  13. Software for Managing Projects

  14. Excel

  15. Cost–Time Trade-Offs and Project Crashing It is not uncommon to face the following situations: • The project is behind schedule • The completion time has been moved forward Shortening the duration of the project is called project crashing

  16. Problems with Traditional PM • Late • Slow • Expensive

  17. Critical Chain Project Management • Moving buffers out of individual tasks • Two questions: • What task do I work on next? • When do I take actions to accelerate the project? • Emphasis on speed

  18. Lean Project ManagementEight Principles • Project System • Leading People • Charter • Right Solution

  19. Lean Project ManagementEight Principles • Managing Variation • Project Risk Management • Project Plan • Executing

  20. Project Management Body of Knowledge(PMBOK)