NESHAPs for Surface Coating Metal & Plastic Parts. Melissa Ellis Air Toxics Coordinator 471-6624. NDEQ Training December 14, 2010. Training Agenda (con’t). Training Objectives 4M (Metal coating) and 4P (Plastic coating) Applicability Subcategories Compliance options and requirements

kellsie
Download Presentation

NESHAPs for Surface Coating Metal & Plastic Parts

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NESHAPs for Surface CoatingMetal & Plastic Parts Melissa Ellis Air Toxics Coordinator 471-6624 NDEQ Training December 14, 2010

  2. Training Agenda (con’t) • Training Objectives • 4M (Metal coating) and 4P (Plastic coating) • Applicability • Subcategories • Compliance options and requirements • Practical exercises • Case Study – Becton Dickinson

  3. Training Objectives • Identify applicable sources • Understand requirements • Obtain information needed to inspect or permit properly • Emission calculations • Challenges from past permitting/compliance staff • Obtain tools & resources to help do your job effectively

  4. Rule Background Applicability Compliance Monitoring Compliance Dates Notifications Reporting Recordkeeping MMMM and PPPP

  5. MMMM: Rule Background • Proposed Rule: 8/13/02 • Final Rule: 1/2/04 (same effective date) • Amendment: 4/26/04 = clarification of rule overlap • Title 129, Chapter 28, 001.81 • Two sources subject • BD Medical – Columbus • Case New Holland – Grand Island

  6. MMMM: Applicability • Apply surface coating to misc. metal parts & products • Coating = spray guns, dip tanks, etc. • Not coating = non-refillable aerosol, touch up markers, pens, or paper or plastic film • Major source = PTE > 10 tpy single HAP or 25 tpy combined HAPs

  7. MMMM: Applicability • Use ≥ 250 gal/yr of organic HAP containing coatings • Coatings <50 gal/yr exempt provided total volume exempt < 250 gal • Not subject • Not using organic HAP products or use <250 gal/yr • R & D, maintenance, or noncommercial hobby • Military installations, munitions, or NASA • Extrusion of plastic • If subject to another NESHAP as of rule date

  8. MMMM: New vs. Existing • New Source • Construction commenced after August 13, 2002 • Completely new coating facility • Existing Source • Not new or reconstructed • ONE affected source per facility

  9. MMMM MMMM: New Source Existing :General Use :High Performance

  10. MMMM: Subcategories

  11. PPPP: Rule Background • Proposed Rule: 12/4/02 • Final Rule: 4/19/04 (same effective date) • Amendment: 4/26/04 = clarification of rule overlap • Amendment: 4/24/07 = clarification of rule overlap • Title 129, Chapter 28, 001.85 • Two sources subject • BD Medical – Columbus • A-1 Fiberglass - Hastings

  12. PPPP: Applicability • Apply surface coating to plastic parts & products • Coating = spray guns, dip tanks, etc. • Not coating = non-refillable aerosol, touch up markers, pens, or paper or plastic film • Major source = PTE > 10 tpy single HAP or 25 tpy combined HAPs

  13. PPPP: Applicability • Use ≥ 100 gal/yr of HAP containing coatings • Not subject • Not using organic HAP products or use <100 gal/yr • R & D, maintenance, or noncommercial hobby • Military installations, munitions, or NASA • Extrusion of plastic • If subject to another NESHAP as of rule date • Fiberglass boats or boat parts • In-mold or gel coating reinforced plastic parts

  14. PPPP: New vs. Existing • New Source • Construction commenced after December 4, 2002 • Completely new coating facility • New equipment in a subcategory that was not previously performed • Existing Source • Not new or reconstructed • Can have several affected sources per facility

  15. PPPP PPPP: New Source Existing New :General Use :Automotive Lamp

  16. PPPP: Subcategories

  17. 4M & 4P: Compliance Options • Subject to more than one coating NESHAP • Comply with each OR • Comply with NESHAP for predominant activity OR • Predominant activity = 90% • Not for assembled vehicles or automotive lamps • Use gallons of solids to determine • Develop Facility-Specific Emission Limit (FSEL)

  18. 4M & 4P: Predominant Activity Metal Parts Coating: 8,000 gal solids Plastic Parts coating: 800 gal solids 0.91 > 0.90 \ Predominant Activity will work as an option for this facility

  19. 4M & 4P: Facility Specific Emission Limit • Calculate monthly FSEL = Facility-specific emission limit for each 12-month compliance period, lb HAP per lb solids Limiti = Applicable emission limit, lb HAP per lb solids Solidsi = Solids used in operation, lb

  20. 4M & 4P: Compliance • Compliance options • Compliant material • Emission rate with no add-on controls • Emission rate with add-on controls • Work practice standards +

  21. 4M & 4P: Compliant Materials • All coating materials have HAP content less than emission limit • All thinners, additives & cleaning materials contain no HAP • Demonstrate compliance each month • No 12-month rolling totals

  22. 4M & 4P: Compliant Materials • For each material • Determine organic HAP mass fraction (Wc) • Method 311 • Method 24 • Mfg. formulation data or test data • Other approved method • Table 3 or 4 default values

  23. 4M & 4P: Compliant Materials • For each coating • Determine volume faction of coating solids (Vc) • ASTM D2697-86 or D6093-97 • Alternate approved • Mfg. or supplier data • Calculate • Determine density (Dc) • ASTM Method D1475 • Mfg. or supplier data • Specific gravity for pure chemicals • Calculate organic HAP content & compare to emission limit

  24. 4M & 4P: Compliant Materials • Calculation for Organic HAP Content Hc = Organic HAP content, lb/gallon solids Dc = Density, lb/gallon Wc = Mass fraction of organic HAP, lb HAP/lb coating Vs = Volume fraction coating solids, gal solids/gal coating

  25. 4M & 4P: Emission Rate (No Control) • Calculated as (HAP used)/(solids used) • Rolling 12-month compliance period • Calculated monthly • No operating limits or work practice standards • Can be used for • Each subcategory or source category • Predominant activity • Facility specific emission limit

  26. 4M & 4P: Emission Rate (No Control) • For each material • Determine organic HAP mass fraction (Wc) • Method 311 • Method 24 • Mfg. formulation data or test data • Other approved method • Table 3 or 4 default values

  27. 4M & 4P: Emission Rate (No Control) • For each coating • Determine volume faction of coating solids (Vc) • ASTM D2697-86 or D6093-97 • Alternate approved • Mfg. or supplier data • Calculate • Determine density (Dc) • ASTM Method D1475 or 5965 • Mfg. or supplier data • Specific gravity for pure chemicals • Determine volume of material used (Volc,i)

  28. 4M & 4P: Emission Rate (No Control) • Calculate Mass Organic HAP • Coatings, Additives/Thinners, Cleaners, & Waste • Calculation method same for each A = Total mass organic HAP, coatings, lb Volc,i= Total volume used, gallons Dc,i= Density, lb coating/gallon coating Wc,i= Mass fraction organic HAP, lb HAP/lb coating

  29. 4M & 4P: Emission Rate (No Control) • Calculate total mass organic HAP emissions • Can subtract organic HAP in waste He = Total mass organic HAP, lb A = Total mass organic HAP, coatings B = Total mass organic HAP, additives & thinners C = Total mass organic HAP, cleaning Rw = Total mass organic HAP, waste shipped or disposed

  30. 4M & 4P: Emission Rate (No Control) • Calculate total volume solids Vst = Volume coating solids used, gallons Volc,i= Total volume used, gallons Vs,i= Volume fraction coating solids, lb solids/lb coating

  31. 4M & 4P: Emission Rate (No Control) • Calculate Emission Rate = = • Compare to emission limit • Calculate 12-month rolling totals

  32. 4M & 4P: Emission Rate + Controls • Develop & implement Startup, Shutdown, & Malfunction (SSM) Plan** • Install Capture/Control system • Conduct performance test • Previously conducted tests can be used if… • Approved • Used specific method & conditions • No process or equipment changes made • Operating parameters can be established from previous data

  33. 4M & 4P: Emission Rate + Controls • Establish operating limits • Unless using recovery system & using liquid-liquid mass balance • Continuous Parameter Monitoring System (CPMS) • Develop & implement work practice plan • Minimize emissions from storing, spilling, handling, mixing, & cleaning

  34. 4M & 4P: Emission Rate + Controls • Calculated as (HAP used)/(solids used) • Include capture and control efficiency • Rolling 12-month compliance period • Calculated monthly

  35. 4M & 4P: Emission Rate + Controls • Similar to Emission Rate with no add-on controls • Calculate mass organic HAP before add-on controls • Calculate mass organic HAP emission reduction Hunc=Mass of organic HAP during deviations CE= Capture efficiency DRE = Destruction or removal efficiency

  36. 4M & 4P: Emission Rate + Controls • Calculate mass of organic HAP emissions HHAP= Total mass of organic HAP He = Total mass of organic HAP before add-on controls Hc,i = Total mass of organic HAP emission reduction, not using liquid-liquid HCSR,j = Total mass of organic HAP emission reduction, using liquid-liquid

  37. 4M & 4P: Emission Rate + Controls • Calculate Emission Rate = = • Compare to emission limit • Calculate 12-month rolling totals

  38. 4M & 4P: Continuous Compliance • Perform monthly compliance calculations for 12 month compliance period • Submit semiannual compliance reports • Keep records • Monitor operating limits for add-on controls • Apply work practice standards for add-on controls

  39. 4M & 4P: Monitoring • Continuous Parameter Monitoring System • One reading every 15 minutes • 4 equally spaced readings per hour • Average all recorded readings for each successive 3-hour period • Inspection, calibration, validation check results • Maintain CPMS, spare parts available • Operate CPMS when coating operation in operation

  40. 4M & 4P: Compliance Dates • MMMM • Existing source = 1/2/07 • New source (after 8/13/02) = 1/2/04 or startup • PPPP • Existing source = 4/19/07 • New source (after 12/4/02) = 4/19/04 or startup • Area increases to major • Existing source = 1 year after becoming major or 3 years after 1/2/04 (4M) or 4/19/04 (4P), whichever is later • New source = Initial startup

  41. 4M & 4P: Notifications • Initial Notification • MMMM • Existing source = 1/2/05 • New source = 5/1/04 or 120 days after startup • PPPP • Existing source = 4/19/05 • New source = 4/19/04 or 120 days after startup

  42. 4M & 4P: Notifications • Notification to Conduct Performance Test • 60 days prior to test • Compliance Status Notification • 30 days after initial compliance period • Initial compliance period ends on last day of the 12th full month after compliance date

  43. 4M & 4P: Reports • Performance Test Report • 60 days after test • SSM Report • Immediate if not consistent with plan • Semiannual if consistent • Semiannual Compliance Report • Covers 1/1-6/30 or 7/1-12/31 • Due January 31 and July 31

  44. 4M & 4P: Records I • Notifications/reports & documentation • Mfg. & supplier data • Test reports • Data/documentation supporting capture efficiency • Compliance options for each operation • Compliance calculations and documentation

  45. 4M & 4P: Records II • Waste disposal records, calculations, & documentation • SSM plan & records • Monitoring data • Work practice plan documentation • Deviations info • Keep records for 5 years • Last 2 years on-site

  46. MMMM lbs HAP/gal solids PPPP lbs HAP/lb solids Differences: Units

  47. MMMM ≥ 250 gal/yr HAP Coating PPPP ≥ 100 gal/yr HAP Coating Differences: Applicability

  48. MMMM Individual coatings < 50 gal/year (total 250 gal max) PPPP No Specific Exemptions Differences: Exemptions

  49. MMMM Completely new facility PPPP New coating equipment at new subcategory Differences: New Source

  50. MMMM PPPP Differences: New Source Existing Existing New :General Use :High Performance :Automotive Lamp