An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Projects is one of the sectors of the engineering department that is paid a great attention because it supports all other departments to achieve its requirements and goals easily and according to the global standards and specially API standards and in time although the time provided to it is limited and critical. Projects

  2. Why we start any project? There are many points that could lead to start a project The company's expansion, by starting up a new rig. The company's equipment upgrading, by installing a new equipment. Modification done to simplify and assist the operation of the rig and make it comply with the global standards, especially API standard. Problems facing operation or maintenance crew due to breakdowns Rig in time &Safely Professional personnel All Materials Needed The Time Frame Project planning Engineering department does believe that project planning is the key to succeed any project; projects can run on time and interact effectively with both operators and suppliers. Everyone involved understands what is wanted and emerging problems are foreseen (and dealt with) long before they cause damage. EXCUTE SELECT ISSUE Plan

  3. Projects done 2-1 2-2 2-3 2-4 New rigs & Refurbishing old rigs Top Drive & new equipment installation Equipment overhaul In progress projects

  4. Rig up project for the following rigs: Rig ..………………………………………start operation ST# 1 (2000 HP)……………………………January,2006 ST# 2 (1500 HP)…………………………....January,2006 ST# 3 (2000 HP)……………………………January, 2007 ST# 4 (2000 HP)……………………………September,2007 ST# 5 (1500 HP)…………………………..April ,2008 ST# 6 (1500 HP)…………………………..End of April ,2008 ST# 7 (1000 HP)…………………………..July ,2008 ST# 8 (1500 HP)…………………………..June,2008 ST# 9 (2000 HP…………………………...March, 2008 ST# 10 (1500 HP)……………………….....End of June,2008 ST# 11 (2000 HP)……………………….....End of Oct.,2008 ST# 12 (2000 HP)………………………….Febrauary,2009 ST# 21 (650 HP-work over)………………January, 2007 ST# 22 (650 HP-work over)………………November ,2007 ST#23 (650 HP-work over)………………End of March ,2008 ST#24 (650 HP-work over)………………End of August,2008 2-1 Sinotharwa Rigs

  5. Rigs Refurbishing • St1 Refurbished , April 2007 Upgrade the rig (Mast, substructure sandblast including MPI) Mud System modification &upgrading upon the operator needs & operation demands

  6. Rigs Refurbishing St2 Refurbished , December 2007 Modify the Rigs (Mast, sub base sandblast steel fabrications, renew rig floor including MPI) Fabricated high pressure mud pump lines & standard standpipe manifold

  7. No need for traditional Kelly Drill complete stand 2-2 Top Drive & new equipment installation Eliminates the hazard of Drilling operation Reduce the Drilling time By 30% Reduce man power • 2-1) Top Drive • Reasons to use Top Drive over classical drilling equipment

  8. So we • Install the Top Drive on the following Rigs: • (Varco TDS-11SA) • ST#1,3,4,5,6,8,12 • (Tesco ECI900 ) • ST#9,10,11

  9. New installed equipments Man Rider Installation for all rigs Install H2S & LEL system on all rigs Install Fuel Purifier on all rigs Install new alarm panels for main engines Isolate all engines exhaust pipe manifolds Install SCR CO2 fire fighting system on all rigs

  10. 2-3 Equipment overhaul ST#1,9Complete overhaul for the Power TongST#2Top end overhaul for the ShanDong power engine Complete overhaul for the ShanDong power engineST#5,7Complete overhaul for the Air hoist 5 ton

  11. ST#10Complete overhaul for the Crown Block ST#1,21Complete overhaul for Mud Pump

  12. 2-4 In progress projects 2-4-1) Jack Up rig • Start fabrication : By End of year 2008 • Electrical Rig ,VFD system • MAST 170 ft clear height • Rotary table 49 ½ ” • TDS -8SA top drive system • Drawworks power: 4600 HP. • Operating water depth: 400 ft (122 m). • Drilling depth: 30000 ft (9,144 m). • Quarters capacity: 120 persons. • 3 -Mud pumps 2200 HP. • Power system of 5 Cat Engines ( 3516B) & 1 Emergency Cat Engine (3512). • Three pedestal cranes with 120 ft (36.6 m) boom. • Horizontal & vertical pipe handling systems. • Three lifeboats (60 person each). • Four life rafts (35 persons each). • Cascading shaker system & 1 vacuum degasser. • Storage of 4,720 bbls fuel oil. • Storage of 10,540 bbls drill water. • Storage of 2,180 bbls potable water. • Storage of 15,800 tons preload ballast. • Storage of 17,400 cu.m bulk mud/cement. • Storage of 3,960 bbls active & reserve pits. • 5000 sack storage.

  13. 2-4-2) Badr yardBadr yard is one of the expansion projects that our company is looking forward to complete as soon as possible.Badr yard will play a very big role for the engineering department which will deduct the outsourcing and hiringcost of workshops to make overhauls in.