An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Outer Tracker Module Production at NIKHEF • Produced 60 modules • Production Progress • Quality Assurance Half way! OT Meeting - LHCb week - Production and QA , Niels Tuning

  2. Module Production at NIKHEF Courtesy of Jan Spelt OT Meeting - LHCb week - Production and QA , Niels Tuning

  3. 50% Milestone met 04/2004: EDR (Electronics Design Review) 05/2004: PRR (Production Readiness Review) 15/05/2003: EDR (Engineering Design Review) 03/2005: 50% prod. 02/2004: 10% prod. 12/2005: 100% prod OT Meeting - LHCb week - Production and QA , Niels Tuning

  4. Module Production at NIKHEF (1) Poor man’s logbook OT Meeting - LHCb week - Production and QA , Niels Tuning

  5. Module Production at NIKHEF (2) Poor man’s logbook OT Meeting - LHCb week - Production and QA , Niels Tuning

  6. Module Production at NIKHEF (3) • Production process: some minor problems: • Watch glue on connectors • Module 58: 4 broken wires • Module 59: peculiar wire response OT Meeting - LHCb week - Production and QA , Niels Tuning

  7. Glue on Connector (1) Traces of glue. Affects leakage current for wires 1 and 64 (~20-100nA) OT Meeting - LHCb week - Production and QA , Niels Tuning

  8. Glue on Connector (2) • Discovered on Heidelberg modules 21 and 22 • 8 channels with high currents (10 – 270 nA) • Checked at NIKHEF: found 6 wires • 64L: M16A M19A M26A • 1L: M20A M26A M41B • Investigated influence of humidity on M16 and M19: • measure current after production; • measure current after drying; • put module in cold, wet environment (= outside); • measure current; • scratch of glue; • measure current. Traces of glue. Affects leakage current for wires 1 and 64 (~20-100nA) OT Meeting - LHCb week - Production and QA , Niels Tuning

  9. Broken wires in Mod 58 • Discovered 4 broken wires in Mod 58 • History: • 23 FebWired full panel • 24 Feb50U broken • 01 Mar60U broken, just before gluing module • 04 Mar 56U short circuit • 07 Mar55U short circuit after shaking the module • Hypothesis: • Middle print tilted ? ? OT Meeting - LHCb week - Production and QA , Niels Tuning

  10. We foresee 10% spares Which ones would we select as spares? How many bad channels are we left with? Selection of 10% spares OT Meeting - LHCb week - Production and QA , Niels Tuning

  11. Quality Criteria Number of bad wires from 90Sr scan. Define bad: • Low response: <15% on average • Typically disconnected due to tripping HV supply • High response: >15% on average • Typically noisy • High response: >100% at any place on the wire • Spikes • Self-sustained currents • Missing wire locators • Not used in quality criteria now: • HV in air : correlated to the 90Sr numbers • HV training : correlated to the 90Sr numbers • Wire Tension: OK. • Ignore modules 5012 and 0… • Consider only modules 1-60 OT Meeting - LHCb week - Production and QA , Niels Tuning

  12. Module Data (1) OT Meeting - LHCb week - Production and QA , Niels Tuning

  13. Module Data (2) OT Meeting - LHCb week - Production and QA , Niels Tuning

  14. Module 60 about to be scanned… Just found peculiar wire in Mod 59: Low current, then self-sustained current Being investigated Module Data (3) Wire locator position  Current 90Sr source Position OT Meeting - LHCb week - Production and QA , Niels Tuning

  15. Module Selection Selection of 6 worst modules: OT Meeting - LHCb week - Production and QA , Niels Tuning

  16. The worst modules from the rest… • Probably module 16, 26 or 30: OT Meeting - LHCb week - Production and QA , Niels Tuning

  17. Special Tests see Peter • Weighing all panel and module components • Calculate X/X0 • Survey of module flatness • Requirement: dZ < +/- 500 um • Result: dZ < +/- 400 um • Humidity of modules • Compare in-leak between leaky and gas-tight module •  Confirm gas-tightness requirements LHCb 2004-114 LHCb 2005-009 in preparation OT Meeting - LHCb week - Production and QA , Niels Tuning

  18. Summary • Production: • Only minor changes in production process • Satisfactory production speed • Wire quality very good now • Gas tightness OK, with occasional leaky exceptions • 17 bad channels in best 90% of the modules = 1.2 ‰ • 11 bad channels in best 85% of the modules= 0.8 ‰ OT Meeting - LHCb week - Production and QA , Niels Tuning

  19. References • LHCb week September 2004, Chia • Scan of 4 Warsaw modules • NIKHEF – Results Mod 0-10 • LHCb week December 2004, CERN • NIKHEF - Module glueing, Connector soldering • OT meeting February 2005, Warsaw • NIKHEF - Module selection 1-50 All quality plots for each module can be found here: http://www.nikhef.nl/pub/experiments/bfys/lhcb/outerTracker/QualityPlots/ OT Meeting - LHCb week - Production and QA , Niels Tuning