1 / 14

Performance Contracting for Construction: Framework for Implementation

Performance Contracting for Construction: Framework for Implementation . Mark Robinson, Ph.D., P.Eng., PMP SAIC 1/22/07. Overview. Why Performance Contracting for Construction? Framework Purpose Stakeholder Involvement Framework Contents Relation to the Highways for LIFE Program

jermaine
Download Presentation

Performance Contracting for Construction: Framework for Implementation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Performance Contracting for Construction: Framework for Implementation Mark Robinson, Ph.D., P.Eng., PMP SAIC 1/22/07

  2. Overview • Why Performance Contracting for Construction? • Framework Purpose • Stakeholder Involvement • Framework Contents • Relation to the Highways for LIFE Program • Lessons Learned • Pilot Program • Next Steps

  3. Why Performance Contracting for Construction? • Much of America’s transportation infrastructure is reaching the end of its design life and needs to be re-constructed • Traffic levels and the resulting congestion levels continue to increase • FHWA is developing, identifying, and promoting new methods to reconstruct highways and bridges safer, faster, and better • Using performance contracting will allow State and local agencies to define and communicate to contractors specifically what they want to achieve • Contractors will have the flexibility to determine how they do the work

  4. Pros Introduction of Innovation Defined Outcomes Contractor Flexibility Share of risk and rewards Cons New approach that requires a culture shift May not be applicable to all projects Some Pros and Cons

  5. Framework Purpose • To provide State and local agencies with processes and materials that they can use to accelerate the development of a performance contract solicitation package for construction contracts • Meant to be used as a reference guide • Should help agencies to avoid common obstacles and pitfalls

  6. Stakeholder Involvement • The project team developed the materials working with: • A select group of stakeholders from State DOTs and Industry • Provided guidance and review at the 30%, 60%, and 90% stages • Subject matter experts from FHWA

  7. Scott Jarvis - Caltrans Chuck Suszko - Caltrans Gene Mallette - Caltrans Peggy Chandler - Texas DOT Steve DeWitt - North Carolina DOT Kevin Dayton - Washington State DOT Dexter Newman - the Kentucky Cabinet Sid Scott - Trauner Consulting Brian Deery - AGC Bob Lanham - Williams Brothers Construction- Brian Burgett - Kokosing Construction Rich Juliano - ARTBA State DOT and Industry Stakeholder Group Note: Participation did not involve formal endorsement of the final product

  8. Jim Sorenson Mary Huie Byron Lord Ken Jacoby King Gee Jerry Yakowenko Tracy Scriba Chung Eng Rudy Umbs John Baxter Mark Swanlund Peter Kopac Christopher Schneider David Geiger Tom Deddens Gus Shanine Rob Elliott Evan Wisniewski Jim Hatter John Bukowski Fred Skaer Shari Schaftlein Myint Lwin And others FHWA Subject Matter Experts

  9. Framework Contents • Overall process for performance contract development • Guidance on selecting appropriate projects • Processes, lessons learned, and sample solicitation package materials for: • Performance Goals • Measurement Methodology • Enhanced Low Bid Award Process • Best Value Award Process • SEP-14 Process

  10. Relation to the Highways for LIFE (HfL) Program • HfL’s mission is to improve the driving experience of the American public • HfL is looking for new ways to build highways and bridges safer, faster, better, and less costly • Performance contracting will be a tool in the HfL toolbox • HfL projects are not required to use performance contracting • Additional consideration will be given to projects that propose to use performance contracting

  11. Lessons Learned • Each project will be different – Processes, goals, and materials will need to be tailored to the individual application • Performance goals should be SMART – Specific, Measurable, Achievable, Results-Oriented, and Timely • Performance goals MUST be under the influence of the contractor • The contractor must have flexibility in how they perform the work • Ideally, the performance-based environment will start at the concept or design stage

  12. Pilot Program • FHWA is currently seeking 4 to 8 agencies that are interested in piloting the Performance Contracting Framework. • Pilot states will receive tailored technical assistance to help them implement this approach • Pilot states can propose the use of the framework as an innovative approach when applying for funding under the Highways for LIFE Program • For more information on becoming a pilot agency, contact Mary Huie at mary.huie@dot.gov or 202-366-3039

  13. Next Steps • Perform outreach to recruit agencies to pilot the framework • Provide technical assistance to 4 to 8 pilot projects • Capture information on successes and lessons learned • Prepare case study documents on each pilot application • Revise and update the Framework for broader release

  14. For More Information • Jim Sorenson, FHWA james.sorenson@dot.gov, 202-366-1333 • Mary Huie, FHWA mary.huie@dot.gov, 202-366-3039 • Mark Robinson, SAIC mark.d.robinson@saic.com, 703-676-2384

More Related