San Francisco-Oakland Bay Bridge East Span Seismic Safety Project Pre-Bid Meeting for Construction Contract 04-0102E4 March 12, 2003. SFOBB New East Span. Welcome - my name is Sarah Picker Purpose : networking for business relationships to construct SFOBB East Span Agenda Sign-In Please.
E N D
San Francisco-Oakland Bay BridgeEast Span Seismic Safety Project Pre-Bid Meeting for Construction Contract 04-0102E4 March 12, 2003
SFOBB New East Span • Welcome - my name is Sarah Picker • Purpose : networking for business relationships to construct SFOBB East Span • Agenda • Sign-In Please
General • collect business cards • other cost savings measures • handouts • sign-in sheets
Welcome • Opening Remarks by: Dan McElhinney Chief Deputy District Director Toll Bridge Program
San Francisco - Oakland Bay Bridge East Span Seismic Safety Replacement Project West Approach West Span Retrofit
Project Limits San Francisco Oakland Project Limits
East Span Replacement Contracts Hinge A Hinge E Nine Contracts One Contract Two Contracts Frame 1 Frame 2 Frame 3 Frame 4 Segment YBI SAS Skyway Oakland 1. 04-012054 Oakland Touchdown Geofill
East Span Replacement Contracts Segment YBI SAS Skyway Oakland Hinge A Hinge E Nine Contracts One Contract Two Contracts Frame 1 Frame 2 Frame 3 Frame 4 1. 04-012054 Oakland Touchdown Geofill 2. 04-012044 Oakland Touchdown Structures
East Span Replacement Contracts Segment YBI SAS Skyway Oakland Hinge A Hinge E Nine Contracts One Contract Two Contracts Frame 1 Frame 2 Frame 3 Frame 4 1. 04a1701 (R/W) YBI Building Demolition
East Span Replacement Contracts Segment YBI SAS Skyway Oakland Hinge A Hinge E Nine Contracts One Contract Two Contracts Frame 1 Frame 2 Frame 3 Frame 4 1. 04a1701 (R/W) YBI Building Demolition 2. 04-0120G4 YBI Substation, Viaduct Retrofit
East Span Replacement Contracts Segment YBI SAS Skyway Oakland Hinge A Hinge E Nine Contracts One Contract Two Contracts Frame 1 Frame 2 Frame 3 Frame 4 1. 04a1701 (R/W) YBI Building Demolition 2. 04-0120G4 YBI Substation, Viaduct Retrofit 3. 04-0120C4 SAS W2 Substructure 4. 04-0120E4 SAS E2/T1 Substructures 5. 04-0120F4 SAS Superstructure
East Span Replacement Contracts Segment YBI SAS Skyway Oakland Hinge A Hinge E Nine Contracts One Contract Two Contracts Frame 1 Frame 2 Frame 3 Frame 4 1. 04a1701 (R/W) YBI Building Demolition 2. 04-0120G4 YBI Substation, Viaduct Retrofit 3. 04-0120C4 SAS W2 Substructure 4. 04-0120E4 SAS E2/T1 Substructures 5. 04-0120F4 SAS Superstructure 6. 04-0120P4 YBI Transition Structures
East Span Replacement Contracts Segment YBI SAS Skyway Oakland Hinge A Hinge E Nine Contracts One Contract Two Contracts Frame 1 Frame 2 Frame 3 Frame 4 1. 04a1701 (R/W) YBI Building Demolition 2. 04-0120G4 YBI Substation, Viaduct Retrofit 3. 04-0120C4 SAS W2 Substructure 4. 04-0120E4 SAS E2/T1 Substructures 5. 04-0120F4 SAS Superstructure 6. 04-0120H4 YBI Transition Structures 7. 04-0120Q4 USCG Road Relocation
East Span Replacement Contracts Segment YBI SAS Skyway Oakland Hinge A Hinge E Nine Contracts One Contract Two Contracts Frame 1 Frame 2 Frame 3 Frame 4 1. 04a1701 (R/W) YBI Building Demolition 2. 04-0120G4 YBI Substation, Viaduct Retrofit 3. 04-0120C4 SAS W2 Substructure 4. 04-0120E4 SAS E2/T1 Substructures 5. 04-0120F4 SAS Superstructure 6. 04-0120H4 YBI Transition Structures 7. 04-0120Q4 USCG Rd. Relocation 8. 04-0120R4 South-South Detour
East Span Replacement Contracts Segment YBI SAS Skyway Oakland Hinge A Hinge E Nine Contracts One Contract Two Contracts Frame 1 Frame 2 Frame 3 Frame 4 1. 04a1701 (R/W) YBI Building Demolition 2. 04-0120G4 YBI Substation, Viaduct Retrofit 3. 04-0120C4 SAS W2 Substructure 4. 04-0120E4 SAS E2/T1 Substructures 5. 04-0120F4 SAS Superstructure 6. 04-0120H4 YBI Transition Structures 7. 04-0120Q4 USCG Rd. Relocation 8. 04-0120R4 South-South Detour 9. 04-012074 YBI Midden Site
East Span Replacement Contracts Oakland Skyway SAS Segment YBI Hinge A Hinge E Nine Contracts One Contract Two Contracts Frame 1 Frame 2 Frame 3 Frame 4 Skyway Contract No. 04-012024
Self Anchored Suspension (SAS) Pier W2W Tower Hinge A C C C C C L L L L L Pier E2W Hinge K Pier W2 Pier 1 (Tower) Pier E2 Mean Sea Level Elev 0.000 Approx OG along PG Line 04-0120C4 W2 Structures Bid Opening 4/29/03 04-0120E4 E2/T1 Structures Bid Opening 4/15/03 04-0120F4 SAS Superstructure Bid Opening 6/03/03
Aerial View of Self Anchored Suspension (SAS)
04-0120P4 YBI Transition Structure YBI Viaduct W2 Transition Structure 04-0120P4 Scheduled Bid Opening: 6/22/04
04-0120Q4 USCG Road Relocation USCG Access
04-012044Oakland Touchdown Structures CL Hinge E Advertise 12/1/03 Bid Opening: 3/2/04
04-0120R4 South-South Detour South-South Detour
readvertisement • YBI Foundation W2 04-0120C4 • a contract to construct Self Anchored Suspension Span Land Foundation W2 • advertise 3/17/03 • bid opens 4/22/03
SAS E2/T1 Structures 04-0120E4 • a contract to construct the Self-Anchored Suspension bridge in-bay foundations, the main tower (T1) and pier E2 just to the east of YBI • advertise Jan 21, 2003 • bid open April 15, 2003
SAS Superstructures 04-0120F4 • a contract to construct the tower and superstructure of the Self-Anchored Suspension bridge • advertise Feb 3, 2003 • bid open June 3, 2003
South-South Detour 04-0120R4 • a contract to construct a 580 meter temporary two-level traffic bypass structure • Contractor required to design according to criteria, means and methods to be described in advertised documents and to prepare construction plans and specifications • advertise 4/7/03 • bid open 8/5/03
Recap of SFOBB East Span Seismic Safety Project • PIDP 04-012084 • Skyway 04-012024 • Geofill 04-012054 • Archeological Excavation and Midden Site 04-012074 • YBI Building Demolition(R/W) • SAS W2 Structures 04-0120C4
Recap of SFOBB East Span Seismic Safety Project • YBI Substation & Viaduct Retrofit 04-0120G4 • SAS E2/T1 Structures 04-0120E4 • SAS Superstructures 04-0120F4 • YBI Structures 04-0120P4 • south south detour 04-0120R4 • 04-0120Q4 New Road for USCG • Oakland Touchdown 04-012044 • Existing Bridge Demolition 04-012094
SFOBB East Span • Today’s discussions relate to the Construction Contract In Bay Foundation T1 and E2 04-0120E4 • advertised for bid January 21, 2003 • bid opens April 15, 2003
Other Introductions • Will the Potential Prime Contractors in the room volunteer to raise their hands? • Would the DBE certified businesses raise their hands? • Would the potential DBE or small businesses raise their hands?
San Francisco-Oakland Bay BridgeEast Span Seismic Safety Project
Roadway Items Bob Zandipour Branch Chief, Toll Bridge Program
T1/E2 foundations (04-0120E4) Transition structure (04-0120H4) E2 Retrofit/Substation (04-0120G4) T1 SAS superstructure (04-0120F4) W2 foundation (04-0120C4) Building demolition (04A1701) Yerba Buena Island YBI/SAS Contracts
Yerba Buena Island • Varied topography -- 60 meter elevation change • Steep slopes • Narrow winding roads • USCG base for 24 hour Search and Rescue unit • Lots of underground utilities
Environmental Constraints at YBI Historic Structures USCG Facilities
Special Aquatic Site and Trestle Locations-Yerba Buena Island Trestle locations T1 E2 Yerba Buena Island
Roadway Items Items Description Unit Quantity Electronic Mobile Daily Diary Computer System Data Delivery LS Lump Sum Transportation for the Engineer LS Lump Sum Construction Surveying LS Lump Sum Pile Corrosion Monitoring System LS Lump Sum Progress Schedule (Critical Path) LS Lump Sum Time Related Overhead LS Lump Sum Prepare Storm Water Pollution Prevention Plan LS Lump Sum Water Pollution Control LS Lump Sum Non Storm Water Discharge LS Lump Sum Turbidity Control LS Lump Sum Temporary Concrete Washout Facility LS Lump Sum Chain Link Fence (Type CL-1.8) M 146 Concrete Barrier (Type K) M 72 Grounding for Pier E2 and T1 Foundations LS Lump Sum Navigation Lighting System LS Lump Sum Strong Motion Detection Downhole LS Lump Sum
San Francisco-Oakland Bay BridgeEast Span Seismic Safety Project
Structure Items Structural Design, Toll Bridge Program