Pecan Campus. . Construction - Classroom Bldg.. HVAC duct system installation 89% completeDrywall systems (metal stud) installation 92% completeInterior domestic water and electrical rough-in 91% completeRoof completeExterior masonry and stucco 94% completeInterior tape, float and texture 75% complete.
E N D
1. STC Bond Construction and Planning Progress Report Coordinated Operations Council
July 6, 2004
2. Pecan Campus
3. Construction - Classroom Bldg. HVAC duct system installation 89% complete
Drywall systems (metal stud) installation 92% complete
Interior domestic water and electrical rough-in 91% complete
Roof complete
Exterior masonry and stucco 94% complete
Interior tape, float and texture 75% complete
4. Construction-Student Support Services Bldg. HVAC duct system installation 60% complete
Drywall systems (metal stud) installation 55% complete
Interior domestic water and electrical rough-in 45% complete
Roof 84% complete
5. Construction-Thermal Energy Plant Chillers installed
Cooling towers complete
Drywall systems (metal stud) installation 63% complete
Interior domestic water and electrical rough-in 63% complete
Roof complete
6. Planning-Phase II Building Projects Boultinghouse Simpson Architects is working on the Design Development Phase of the Institutional Support Services Building Project. The Architect’s consultants are reviewing the schematic design and are working on their initial design of the structural, mechanical and electrical systems. A cost estimate is also in progress.
A meeting was held with STC Staff to review the revised Schematic Design plans for the Information Technology Building on June 22nd. The plans are being revised per this meeting and will be re-visited during a follow-up meeting scheduled for July 1, 2004. Schematic design approval will be requested by the Board of Trustees at the July 15, 2004 Board meeting.
7. Planning-Phase II Building Projects The Communication Arts Building is tracking behind the Institutional Support Services and the Information Technology Buildings. A trip to visit facilities in Dallas similar to the one required by STC, was successful in providing the Architect with a glimpse of what STC’s expectations are for this building. A conceptual plan (diagram) of the proposed building is being developed to help describe the relationship of the targeted funding sources to the different functional areas of the building in order to assist in refining the scope of the final program.
ERO International architects continue to work on the Design Development Phase of the Remodeling of Building “C” on the Pecan Campus Renovation Projects. Based on a directive from the Facilities Committee, the Architects MEP consultants have developed a narrative scope of the work required to locate HVAC units inside the existing buildings. The Construction Manager at Risk, BFW, analyzed the cost impact of moving the A/C units from the roof into the existing buildings A & F. The information was inconclusive and required additional review by the project team. A more detailed breakdown, documented in a table format will be developed and presented at the next Facilities Committee meeting.
8. Classroom Building
9. Classroom Building
10. Classroom Building
11. Student Support Services Building
12. Student Support Services Building
13. Thermal Plant
14. Thermal Plant
15. Thermal Plant
16. Technology Center
17. Construction-New Classroom Building Drywall systems (metal studs and gyp. Bd.) installation 80% complete
Interior domestic water and electrical rough-in 56% complete
MEP rough-in 64% complete
18. Construction-Shipping & Receiving The Construction Manager at Risk has received a Temporary Certificate of Occupancy for this building and STC staff has occupied the building.
Substantial Completion recommendation will be presented at the July 15, 2004 board meeting for approval by STC Board of Trustees
19. Construction-Workforce Renovation Drywall systems (metal studs) installation complete
Air and water lines complete
Wall panels erected at addition
Roof complete at addition
A portion of this project is on hold pending pricing from Faulkner Construction concerning areas affected by flooding
20. Technology & Classroom Building
21. Technology & Classroom Building
22. Technology & Classroom Building
23. Technology & Classroom Building
24. Shipping & Receiving Building
25. Shipping & Receiving Building
26. Shipping & Receiving Building
27. Shipping & Receiving Building
28. Workforce Development Center
29. Workforce Development Center
30. Starr County Campus
31. Construction-Site work Chiller yard complete & chillers on-line
Water pressure augmentation released for construction
Construction of North end of Loop Road underway
Final topsoil fill underway
Sidewalks / hardscape 75% complete
32. Construction-Classroom Building Exterior finishes 98% complete
HVAC duct system installation 96% complete
Drywall systems (metal studs and sheetrock) installation 96% complete
Interior domestic water and electrical rough-in 91% complete
Interior tape-and-float and texture 60% complete
Painting 50% complete
Suspended ceiling 50% complete
Design and pricing of Biology lab student tables underway
Classroom cabinets/desks not requested by STC will be removed and credited
33. Construction-Student Activities Building Interior complete
Exterior complete
Building punched out July 1, 2004
Architect recommends Substantial Completion to be presented to STC board for approval at July 15, 2004 meeting
34. Construction-Student Support Services Building Interior complete
Exterior complete
Building punched out July 1, 2004
Architect recommends Substantial Completion to be presented to STC board for approval at July 15, 2004 meeting
35. Construction-Workforce Development Building Building pad excavation complete
Structural fill complete
Underground plumbing and electrical underway
36. Construction-Instructional Resource Building Building pad excavation complete
Structural fill complete
Underground plumbing and electrical underway
Slab underway
37. Classroom Building
38. Classroom Building
39. Classroom Building
40. Classroom Building
41. Student Support Services Building
42. Student Support Services Building
43. Student Support Services Building
44. Student Support Services Building
45. Student Activities Building
46. Student Activities Building
47. Cafeteria @ Student Activities Building
48. Student Activities Building
49. Student Activities Building
50. Instructional Resource Building
51. Mid-Valley Campus July 6, 2004
52. Construction-Sitework Fire line relocation complete
Additional piping not in original scope of work, requested by City of Weslaco, complete
WFD parking lot underway
Road work underway
53. Construction-Instructional Building Structural steel erection complete
Exterior sheathing and damp proofing complete
HVAC duct system installation 61% complete
Drywall systems (metal studs) installation 77% complete
Interior domestic water and electrical rough-in 77% complete
54. Construction-Instructional Resources Building Exterior sheathing and damp proofing 88% complete
HVAC duct system installation 36% complete
Drywall systems (metal stud) installation 40% complete
Interior domestic water and electrical rough-in 46% complete
55. Construction-Student Support Services Building Exterior sheathing and damp proofing complete
HVAC duct system installation 54% complete
Drywall systems (metal stud) installation 79% complete
Interior domestic water and electrical rough-in 54% complete
56. Construction-Workforce Development Building HVAC duct system installation complete
Drywall systems (metal studs and sheetrock) installation complete
Interior domestic water and electrical rough-in 56% complete
Tape-and-float and texture complete
Suspended ceiling complete
Exterior finished complete
57. Instructional Building
58. Instructional Building
59. Instructional Building-Lecture Hall
60. Student Support Services Building
61. Student Support Services Building
62. Instructional Resources Building
63. Instructional Resources Building
64. Workforce Development Building
65. Workforce Development Building
66. Workforce Development Building
67. Sitework-New Road to Workforce Building
68. Nursing & Allied Health Center
69. Construction-New Building Addition and Sitework Structural steel erection complete
All concrete floor decks poured
Drywall systems (metal stud) installation 28% complete
New parking area curb & gutter complete, asphalt complete except for punch-list
70. Nursing & Allied Health
71. Nursing & Allied Health Center Addition
72. Nursing & Allied Health Center Addition