Detailing the stator unloading process at Unit-III, including vehicle routing, crane positioning, and stator lifting onto rails in the cooling tower area.
E N D
1 X 700 MW BTPS STAGE-III STATOR UNLOADING 10-04-2014
Proposed Vehicle Movement Rout Material Gate Vehicle movement in forward direction Vehicle movement in reverse direction Stator Unloading Area unit-III Cooling Tower UNIT-3 POWER HOUSE UNIT-3 BOILER UNIT-3 ESP unit-III Chimney Crane Position Pipe Rack Unit-II Conveyor unit-I Chimney fabrication yard Technical Building
SITE INCHARGE/BHEL & OTHER BHEL EMPLOYEES AT UNLOADING LOCATION